Rahma
Rahma
By
Rahma Abdourahman Mohamed
To
Internship tutor
Hassan Mohamed Ali
Ing. Electrical network
Faculty tutor
Dr. Dorsaf GHOZZI
The work contained within this document has been submitted by the student in partial
fulfilment of the requirement of their course and award
I
UNIVERSITY OF DJIBOUTI – FACULTY OF ENGINEERS
By
Rahma Abdourahman Mohamed
Performed at
Electricity of Djibouti
October, 2024
The work contained within this document has been submitted by the student in
partial fulfilment of the requirement of their course and award
II
ACKOWLEDGMENT
Special thanks go to my supervisor, Mr. Hassan Mohamed Ali, whose mentorship and
constructive feedback played a crucial role in enhancing my learning and understanding
of the field. I also want to acknowledge the entire team in the [Department/Division
Name] for their collaborative spirit and for making me feel welcome.
I am also grateful to my academic advisors at [Your University] for their encouragement
and support throughout this internship journey. The knowledge and skills I have
developed would not have been possible without the support of all these individuals and
institutions.
Finally, I would like to thank my family and friends for their continuous support and
encouragement, which motivated me throughout this process.
III
Table contents
ACKOWLEDGMENT ............................................................................................................................... III
LIST OF TABLES ...................................................................................................................................... V
LIST OF FIGURES ................................................................................................................................... VI
ABBREVIATION .................................................................................................................................... VII
INTRODUCTION ..................................................................................................................................... 1
I. PRESENTATION OF HOSTING COMPANY ....................................................................................... 2
I.1 HISTORY ............................................................................................................................................ 2
I.2 IDENTITY ............................................................................................................................................ 3
I.3 STD .................................................................................................................................................. 3
I.3.1 Presentation of STD ................................................................................................................ 3
I.3.2 Organizational chart of STD ................................................................................................... 4
I.3.3 Departments .......................................................................................................................... 4
I.4 DAILY ACTIVITY .................................................................................................................................... 6
II. DESCRIPTION OF THE PROJECT ...................................................................................................... 7
II.1 LOCATION OF BARWAQO 2 EXTENSION ................................................................................................ 7
II.2 SOMELEC .................................................................................................................................... 8
II.3 IMPORTANCE OF ELECTRIFICATION ...................................................................................................... 8
II.3.1 Decree .................................................................................................................................... 9
II.3.2 Standard ................................................................................................................................. 9
II.4 OBJECTIVES OF THE POWER SUPPLY STUDY .......................................................................................... 9
III. POWER SUPPLY DESIGN FOR BARWAQO 2 EXTENSION ............................................................... 10
III.1 DESIGN OF THE DISTRIBUTION NETWORK DESIGN ................................................................................. 10
III.2 SUBSTATION REQUIREMENT ................................................................................................................... 11
III.3 TRANSFORMER SIZING AND PLACEMENT ................................................................................................... 13
III.4 CABLE SIZING AND ROUTING ................................................................................................................... 16
IV. RELIABILITY AND STABILITY ANALYSIS .................................................................................... 20
IV.1 POWER SUPPLY RELIABILITY ............................................................................................................. 20
IV.2 POWER QUALITY AND STABILITY........................................................................................................ 21
IV.3 CONTINGENCY PLANS ..................................................................................................................... 24
V. ECONOMIC ANALYSIS .................................................................................................................. 24
V.1 CAPITAL INVESTMENT..................................................................................................................... 25
V.2 OPERATING AND MAINTENANCE COSTS ............................................................................................. 26
V.3 FINANCIAL FEASIBILITY.................................................................................................................... 28
CONCLUSION AND RECOMMENDATION FOR FUTURE RESEARCH ........................................................ 31
REFERENCES ........................................................................................................................................ 32
APPENDICES ........................................................................................................................................ 33
SUMMARY ........................................................................................................................................... 38
RESUME: ............................................................................................................................................. 38
IV
LIST OF TABLES
Table III.1: Comparison between overhead and underground distribution network. ............... 11
Table III.3.1: Corresponding demand factor for a given group of consumers. ........................... 14
Table1III.3.2: Characteristics of 400 kVA, MV/LV transformer ................................................... 15
Table2III.4.2: characteristic of a given cable ............................................................................... 19
Table IV.2.1: Cable Cross-Sections and Characteristics .............................................................. 22
Table IV.2.2: Voltage Drop Calculations ...................................................................................... 23
Table V.1: The total capital investment ...................................................................................... 26
Table V.2: The annual operating and maintenance cost ............................................................ 28
V
LIST OF FIGURES
Figure II: District plan from google earth ...................................................................................... 8
Figure III.1: Blank plan of the city, before the design of the LV network ................................... 10
Figure III.2.2: The different sections of the substation ............................................................... 12
Figure III.2.1: The front view of the substation........................................................................... 12
Figure III.4.2: Different low voltage departures.......................................................................... 17
Figure III.4.3: Lighting type for small road .................................................................................. 18
Figure IV.2: voltage drop percentage for each departure. ......................................................... 24
Figure V.1: capital investment breakdown ................................................................................. 26
Figure V.2: Operating and maintenance breakdown .................................................................. 28
Figure A.1: prices street lightning ............................................................................................... 33
Table A.1: list of localization of the poles by zones .................................................................... 33
Figure A.2: material prices .......................................................................................................... 34
Figure A.3: single phase electronic meter .................................................................................. 34
Figure B.2: replacing an old metallic poles by a new one ........................................................... 35
Figure B.3: Setting up a new urban distribution board............................................................... 35
Figure B.4: Repair of a defective NF C33-226 cable using a junction box................................... 36
Figure C.4: Dimensioning Process of power supply project........................................................ 37
VI
ABBREVIATION
DT Department of Transmission
VII
INTRODUCTION
My final year at the Faculty of Engineering included a six-month internship that I had to
finish in order to broaden my knowledge and help me make a more seamless transition
into the working world. This report is based on my internship at "Electricité de Djibouti
(EDD)", specifically in the Transmission and Distribution (STD) service. My training
encouraged me to apply academic principles in a real-world setting, gaining a better
understanding of the complexities of the electrical distribution network.
The purpose of this report is to describe the process of conducting a power supply study
for the Barwaqo 2 Extension. This includes studying population growth estimates,
forecasting electricity demand, building the distribution network, and connecting the new
network to the existing grid. Additionally, the report investigates the reliability and
stability of the power system, economic feasibility.
1
I. PRESENTATION OF HOSTING COMPANY
I.1 History
Djibouti, a country with limited natural resources and no oil, gas, or coal reserves, heavily
relies on imported fuel for its energy needs. The BOULAOS power plant, established in
1976, has undergone numerous renovations and expansions to meet the country's growing
energy demands. The plant began by relocating five PIELESTICK generators from the
previous MARABOUT power plant and installing a new G1 generator. The production
capacity was increased by 10MW with the addition of a G7 generator in 1980 and a G8
generator in 1982. In 1985, the plant saw its first significant expansion, adding 31.5MW.
In 1988, the facility transferred two MAN generators from Saudi Arabia, adding 10MW.
In the same year, a fire damaged the BOULAOS 1 facilities, causing extensive damage.
Following a rehabilitation project, four new WARTSILLA-GMT generators were
installed, increasing the plant's capacity to 24 MW. Over the years, the plant continued to
grow, adding CATERPILLAR generators in 2003 and 2004. In 2009, the G23 engine was
severely damaged, leading to an additional 15MW expansion in 2010.
In 2011, an electrical connecting line with Ethiopia was installed, allowing Djibouti to
import electricity and stabilize its energy supply. In 2015, a dispatching system was
implemented to optimize the plant's operations and improve energy distribution
efficiency. Despite the country's reliance on imported fuels, the BOULAOS power plant
has become an essential part of Djibouti's electricity generation.
2
I.2 Identity
SOCIAL REASON: THE ELECTRICITY IN DJIBOUTI
TEL: +253 21 35 28 51
MAILBOX: 175
WEBSITE: WWW.EDD.DJ
LOGO:
I.3 STD
3
documentation to the STD service, which grants them electricity.
Head of
Exploitation Of The Distribution Laboratory and small interventions Design and Planning Office
Sustainable Electrification Project Network
I.3.3 Departments
Transportation and distribution services STD is responsible for a wide range of operations
within the EDD and is made up of five departments, each of which is further split into
different divisions. Each department has a distinct mission that differs from the others.
4
- Public lighting division: Public lighting division is a division that takes care of
the lighting of the country. They install public lighting throughout the city but he
also takes care of their maintenance.
- New embranchment division: The new embranchment division carried out
various works, including the installation of LV meters, the connection of new
customers to the network, the removal and re-installation of meters, and the
relocation and power reinforcement of existing connections at the request of
customers.
- Troubleshooting division: The troubleshooting division is an emergency service
that customers contact in case of problems with the electricity supplied by EDD.
They also intervene in case of house fires to cut off the power to prevent the fire
from spreading.
The transmission department is in charge of monitoring the energy that flows via our
national network, as well as the maintenance and proper operation of the electrical
equipment. This department is in charge of testing and inspecting generators, as well as
determining load in MV/LV substations. They intercede when the transformer station's
circuit breakers fail. They are in charge of maintaining and repairing radios for
communication.
5
Study and Planning Department (BEP):
Customer service orders are sent to a department for site study, which is then executed
by the distribution department, which includes various divisions:
Project Department.
The project department is in charge of the study of the projects submitted to the STD,
such as the realization of network studies in Djibouti and the regions (Ali-Sabieh, Dikhil,
Tadjourah, Weah, Damerjog), inventories of vulnerable families who are the main
beneficiaries of the World Bank's support for the final connection, reception of the
project's materials and management of the Jaban'As stock, and finalization of network
extensions under the rural electrification project
6
From 15/04/2024 to 14/06/2024, I worked with the BEP Department, responsible
for studies and planning. I conducted electrical connection studies, analyzed
power consumption for housing estates, and collaborated with civil engineers on
substation constructions and trench digging.
From 15/06/2024 to 14/08/2024, I worked in the DERD Department, handling
cable maintenance, public lighting installations, and managing new customer
connections.
From 15/08/2024 to 14/09/2024, I worked in the DLPI Department, gaining
experience in technical management, including meter calibration and
maintenance of medium and low-voltage systems.
From 15/09/2024 to 07/10/2024, I worked with the DT Department, monitoring
energy flow and maintaining key electrical equipment. This structured approach
allowed me to apply theoretical knowledge in a practical environment while
interacting with power distribution experts.
II. DESCRIPTION OF THE PROJECT
II.1 Location of Barwaqo 2 extension
The Barwaqo 2 extension is located in the recently build sector city Barwaqo 2, which
has been growing rapidly over the past few years. This area is a mix of residential
neighborhoods, businesses, and small industries. With more people moving in and
businesses expanding, the need for reliable electricity has increased significantly.
Currently, the existing infrastructure isn’t enough to meet this demand, so this extension
project is crucial to support the ongoing development of the region.
7
Figure II: District plan from google earth
II.2 SOMELEC
SOMELEC, a well-known construction company in Djibouti, has worked on a number of
infrastructure and electricity projects. Since its founding, SOMELEC has worked with
Electricity of Djibouti (EDD) to improve the country's electrical infrastructure. The
Barwaqo 2 extension project intends to provide reliable power supply solutions to the
developing residential community. The agreement brings together EDD's regulatory
monitoring and technical experience with SOMELEC's practical construction
capabilities. The collaborative efforts are centered on planning and implementing the
distribution network effectively, maintaining safety standards, and accommodating future
development. SOMELEC and EDD intend to create a standard for modern electrification
projects, while contributing to the region's infrastructural development and fast
urbanization.
II.3 Importance of electrification
Given all of the advantages; better living conditions for locals, easier commercial
operations, and support for vital services like hospitals and schools; electrification is
essential for this area. It also decreases dependency on obsolete and inefficient power
8
sources, paving the way for future integration of cleaner, renewable energy sources,
thereby boosting long-term growth and environmental sustainability. As a result, reliable
electricity is critical for the local economy and general well-being.
II.3.1 Decree
The Electricity of Djibouti (EDD) is a public institution responsible for the production
and distribution of electricity in the Republic of Djibouti. It is authorized to build thermal
factories, transformation stations, transmission or distribution lines, and other necessary
installations. The EDD is managed by a Board of Directors appointed by the Council of
Ministers. The decree n° 74-131 / 5G / CG of January 23, 1974, outlines the methods of
exploitation for the production, transport, and distribution of electrical energy. EDD has
the right to use public roads, establish and maintain structures or pipelines for
transportation and distribution, and occupy public and private domains for exploitation
works. Construction of electrical installations is subject to authorization from the Ministry
of Housing; Urbanism; Regional Planning and Environment with the agreement of the
Civil Protection. A certificate of conformity is issued at the end of the works.
II.3.2 Standard
9
III. POWER SUPPLY DESIGN FOR BARWAQO 2 EXTENSION
The design of the power supply system for Barwaqo 2 Extension is a critical part of the
overall infrastructure development. This section covers the key components involved in
delivering reliable and efficient electrical power to the extension area, ensuring it meets
current and future demand. The power supply design process includes considerations for
the distribution network, substation requirements, transformer sizing and placement, and
cable sizing and routing.
Figure III.1: Blank plan of the city, before the design of the LV network
The distribution network for Barwaqo 2 Extension will be based on an overhead design.
After a comprehensive comparison between overhead and underground distribution
systems, the overhead option was chosen due to several key advantages:
10
Ease of Maintenance: Overhead lines are easier to maintain and repair, especially
in case of faults, as they allow for faster fault detection and access.
In addition, the geographical location and terrain of Barwaqo 2 are not conducive to
underground cabling, further solidifying the decision for overhead network deployment.
11
Compliance with Specifications: The substation construction must adhere to the
specifications provided by EDD, including structural dimensions, cable routing,
and access points for future maintenance and expansions.
The substation will play a pivotal role in converting medium voltage (MV) power from
the main supply into low voltage (LV) power suitable for distribution to residential and
commercial users in the extension.
12
III.3 Transformer sizing and placement
Transformers are a key component in ensuring that the electricity delivered to Barwaqo
2 Extension meets both current and future demand.
After being informed about the cost of renting, its geological location and especially the
life style of future occupants, it can be deduced the energy consumption by the area of
the buildings: As a result, the consumer power capacity per domestic is set as follow:
- ≥ 250m² = 9Kva
- ≤250-300≥ = 12Kva
- > 300 m² = 18kva
The loads of different types of dwellings were calculated and then summed to find the
total load of Barwaqo 2 extension.
𝐿𝑜𝑎𝑑2 = 12 × 8 = 96 𝑘𝑉𝐴
The demand factor, often known as the load factor, is a variable that lets us estimate the
approximate load that houses or other structures need. The table below demonstrates the
corresponding demand factor by consumers:
13
Table III.3.1: Corresponding demand factor for a given group of consumers.
In our study, we will use the load coefficient of 0.46, 0.78 and 0.53 for respectively for
the numbers of consumers using 9 kVA, 12 kVA and 18 kVA. The new value of the total
electrical load using the demand factor would be:
𝐿𝑜𝑎𝑑 𝑇 = 𝐿𝑜𝑎𝑑1 + 𝐿𝑜𝑎𝑑2 + 𝐿𝑜𝑎𝑑3 = 243 × 0.46 + 96 × 0.78 + 306 × 0.53 𝑘𝑉𝐴 =
𝟑𝟒𝟖. 𝟖𝟒 𝑘𝑉𝐴
Power transformers are classified according to their kVA capacity in accordance with the
energy requirements of the consumer. The different levels of electrical transformers are:
250 kVA
400 kVA
630 kVA
800 kVA
1000 kVA
The power demand for the extension of Barwaqo 2 is forecasted to reach 348,84 kVA
with a 20% safety margin for future growth, bringing the total demand to approximately
418.61 kVA. The total load forecast for the extension of Barwaqo 2 necessitates the
installation of a 630 kVA transformer.
14
418,61
𝑳𝒐𝒂𝒅 𝒄𝒉𝒂𝒓𝒈𝒆 𝒕𝒓𝒂𝒏𝒔𝒇𝒐𝒓𝒎𝒆𝒓= × 100=66.44%.
630
it is important to load the transformer to less than 70% of the substation when connected
to the overhead line. This size is chosen to ensure the network operates efficiently while
leaving room for future load growth. The substation will be placed in top front within the
extension to minimize voltage drop and reduce transmission losses. In the primary side
of the transformer will be wired in delta configuration and in the secondary side it will be
connected using star connection.
- Assigned frequency: 50 Hz
- Ambient temperature: 40 C
- Type: Depressor
- Immersed in mineral oil
- Standardized to French standard NF C 52-100
Electric characteristics:
The expected demand for Barwaqo 2 is around 418.61 kVA, with a 20% margin for
potential development. A 630 kVA transformer was chosen to fulfill this demand while
keeping the network underused to allow for future development.
Overall, numerous important elements must be considered when selecting a transformer,
including safety margin, transformer placement, and specifications. To avoid overloading
and to accommodate future demand increases, the transformer should be run at less than
70% capacity. It should be located in the front of the study area to reduce transmission
15
losses and voltage drops, as well as for easy access from the road in the event of a repair.
The transformer should meet the French standard NF C 52-100, which specifies a primary
voltage of 20 kV and a secondary voltage of 400V or 230V. It should be oil-immersed
for efficient cooling.
III.4 cable sizing and routing
The cable network is one of the most important components of the distribution system.
Proper cable size guarantees that the network can carry the predicted electrical load,
minimize losses, and maintain voltage stability.
After I made the calculation of the energy need of the consumers I decided to partition
the city into 6 different departures. Each departure can carry a charge of 200 kVA.
Figure III.4.1: The plan of the district after the design of the network
Legends and indication for the distribution network (see picture above):
16
Color pink: Departure 5
Poles numbering
The STD's design office assigns numbers to poles in different districts to avoid confusion
and ensure easy navigation. The first pole in Barwaqo 2 district is assigned 17101, starting
with the initial code 171. However, the numbering of second stage poles has not been
completed due to ongoing project progress.
Pole sizing
After having realized the lines as well as the different departures, we sized the quantities
and the types of poles needed to complete the distribution network. Below, we have
gathered in a table the type of poles, their characteristics and their quantities
17
Table III.4.1: Distribution of pole types and forces for consumer support.
Type Characteristic Quantity by consumer
Public lighting is an important factor when we talk about the dimensioning of the habitat
network. It allows people (pedestrian, driver) to illuminate the road and ensure security
for the residents.
Positioning of lighting
Lanterns on poles provide lighting, powered by 16mm² wire from the substation. They
are set every 30m for the little road and every 60m for the roadway.
The public lighting, often known as the lumandar, is an aluminum light sensor that
measures brightness in outdoor lighting circuits. The photoresistor determines brightness
depending on light quantity. When the brightness threshold is met, the switch can be
closed or opened, with options ranging from 2 lux (night) to 2000 lux (sunny day). The
switch is timed, so it is unaffected by rapid brightness fluctuations. Control can also be
performed manually from the substation. The lights utilized are sodium and mercury-
vapor lamps with power ratings ranging from 100 to 200 W.
18
The main cables used for the Barwaqo 2 extension will be made of aluminum and will
have the following features:
Aluminum cables have been selected over copper cables because they are less expensive
and lighter weight, making them easier to install and maintain. Although copper has
higher conductivity, the price difference makes aluminum a superior alternative for
overhead systems, especially in residential locality like Barwaqo 2 extensions.
The neutral core is round and connected with aluminum alloy. The insulator is
polyethylene.
19
Phase/street lighting: The core is round and wired with aluminum. The insulator
is polyethylene.
The reliability and stability of a power supply system are important factors in maintaining
continuous service to consumers. Any power supply system must be built to handle any
failures while providing a consistent and high-quality source of electricity. This part
investigates the reliability of the Barwaqo 2 Extension power system by examining
potential faults, measuring system stability, and defining power loss contingency
measures.
IV.1 Power supply reliability
One of the most common challenges influencing power supply reliability is the presence
of faults in the distribution network. There are two basic forms of faults: voltage drops
and short circuits. These problems can cause power outages, damage to electrical
equipment, and general inefficiency in the power supply. It is critical to understand the
causes of these problems and the methods taken to minimize them.
A short circuit occurs when an unexpected connection is made between two points in an
electrical circuit, resulting in an excessive current flow. This usually occurs when the
insulation between conductors fails due to factors like fallen trees, overheating, or
equipment damage. Short circuits can cause unsafe levels of current, which can destroy
electrical infrastructure if not adequately controlled.
1. Symmetrical Faults: These occur when there is a fault between all three phases
of the electrical supply.
2. Unsymmetrical Faults: These faults involve one or two phases, often leading to
phase-to-ground or phase-to-neutral faults.
20
To verify that the system can withstand short circuits, we must calculate the short circuit
current, which is determined by the transformer rating and impedance. The transformer
selected for the Barwaqo 2 Extension has a rating of 630 kVA and a secondary voltage
of 400 V for the three-phase system.
The formula for calculating the short circuit current for a three-phase transformer is:
𝐼𝑓𝑙
𝐼𝑆𝐶 =
𝑍
Where:
630 000
Using the transformer data: 𝐼𝑓𝑙 = = 909.72 𝐴
√3×400
909.72
𝐼𝑆𝐶 = = 22,743 A
0.04
This result indicates that the system must be able to withstand short circuit currents up to
22,743 A. Proper protective mechanisms, such as circuit breakers, will be placed to
instantly disconnect the problematic portion, preventing further harm to the system.
Power quality refers to the electrical supply's ability to provide consistent voltage and
frequency levels without fluctuation. Voltage instability can cause equipment failure,
decreased system efficiency, and customer dissatisfaction Maintaining a consistent
voltage supply is crucial to Barwaqo 2 Extension's overall system stability.
One method for ensuring stability is to calculate the voltage drop across the network.
Voltage drop occurs when power passes through distribution wires, and high drops might
21
result in insufficient voltage reaching customers. To ensure power quality, the voltage
loss must be less than 5%.
In our case, the cross-sections of cables are 70 mm2 for the three phases (conductors) and
54.6mm2 for the neutral. For this, the cable moment of 2.6 kW.km is used according to
the table below.
Where,
S: cable cross-section
We must first calculate the electric moment of the cable to determine the voltage drop.
Where:
𝑀𝑒
𝑈% =
𝑀𝑐
22
Where:
The network in the Barwaqo 2 extension is divided into six "departures" or circuit
sections, each serving a specific locality. For example, the Red Departure has a 0.149 km
line and delivers 72 kVA of power to four consumers. Using the appropriate demand
factors, the voltage drop for each departure is calculated and tuned to ensure that it stays
within permissible limits. The following table shows an example of voltage drop
calculations for each departure:
Me
f
(d) in Sn n°of SF in Ps in In
departure km =𝑃×𝑛 consummer kVA kW (kW*km): U in %
Red 0,149 72 4 1 72 57,6 8,5824 3,30092308
Green 0,156 138 12 0,63 86,94 69,552 10,850112 4,17312
Orange 0,155 108 12 0,63 68,04 54,432 8,43696 3,24498462
Jaune 0,154 138 11 0,63 86,94 69,552 10,711008 4,11961846
Rose 0,2 96 7 0,78 74,88 59,904 11,9808 4,608
bleu 0,174 93 6 0,78 72,54 58,032 10,097568 3,88368
23
Figure IV.2: voltage drop percentage for each departure.
As shown in the table, all the calculated voltage drops are kept under the 5% limit,
ensuring efficient power delivery across the network.
IV.3 Contingency Plans
V. ECONOMIC ANALYSIS
The economic analysis for the Barwaqo 2 Extension power supply project is crucial in
determining its overall financial viability. This part assesses the initial capital investment
24
required to build the system, forecasts long-term operating and maintenance costs, and
analyzes the project's financial feasibility. Such analyses contribute to a solid
understanding of the cost structures involved and support decision-making on the
project's financial sustainability.
1. Substation Costs:
The 630 kVA transformer for Barwaqo 2 costs around 9,000,000 DJF .
The civil construction for the substation, which includes the building, ventilation systems,
and foundations, is anticipated to cost 3,560,000 DJF (20,000 USD), which includes
materials, labor, and regulatory compliance.
2. Transformer Costs:
The transformer installation, which includes wiring and safety equipment, costs
1,780,000 DJF.
Therefore, the total cost of the transformer and installation is 7,120,000 DJF.
Aluminum overhead cables cost 1,780 DJF per meter for the 70 mm² conductor, 1,246
DJF for the 54.6 mm² neutral conductor, and 890 DJF for the 16 mm² public lighting
cables. Cable costs for a total length of 5 kilometers are calculated as follows:
Each wooden pole costs 89,000 DJF, and around 50 poles are needed for the extension.
So, the total cost of poles is:
25
5. Labor and Miscellaneous Costs:
The entire capital investment for the project includes 8,900,000 DJF in labor and
transportation costs for installation and construction, as well as 3,560,000 DJF for
permits, inspections, and contingency allowances.
The total capital investment is estimated to be 56,170,000 DJF, which includes all
necessary infrastructure and equipment for the successful deployment of the Barwaqo 2
power supply system.
26
protective equipment, as well as operational expenses spent during normal system
operation.
The 630 kVA transformer requires routine checks, oil refills, and inspections. Annual
transformer maintenance is projected to cost roughly 534,000 DJF, which includes labor
and materials.
The substation itself requires frequent cleaning, ventilation checks, and routine repairs,
which are projected to cost 356,000 DJF annually.
Aluminum cables require less maintenance than copper cables, but overhead lines must
still be inspected for damage, especially after storms or other severe weather conditions.
Annual maintenance of the cables and poles is anticipated to cost 890,000 DJF for
inspections and minor repairs, including the replacement of damaged sections or poles.
The public lighting system placed on the poles requires maintenance, such as replacing
light bulbs and fixing wiring. The annual maintenance cost for the public lighting system
is estimated at 356,000 DJF.
Operating costs include energy losses during transmission, which, according to voltage
drop calculations, are projected to account for around 3% of total energy transferred. The
annual cost of these energy losses can be computed using the extension's total load
(348.84 kVA) and the average electricity cost per kWh.
Given an average cost of electricity of 50 DJF per kWh , the annual cost of energy losses
is: Energy used in one year = 348.84kVA × 8760hours/year = 3,054,158.4kWh/
year
27
Therefore, the annual operating and maintenance costs are:
28
The primary source of revenue for the Barwaqo 2 Extension project will be derived from
the sale of electricity to consumers within the extension. Given that the estimated total
load demand for the extension is 348.84 kVA, with the system running for 8760 hours
annually (24 hours/day, 365 days/year), the total energy consumption is projected as:
Using the electricity rate of 50 DJF per kWh, the total annual revenue from electricity
sales is calculated as:
Thus, the total annual revenue from electricity sales is projected to be 152,707,920 DJF.
Payback period
The payback period is the time it takes for the project to get back its initial capital
investment. To calculate this, remove the annual operating and maintenance expenditures
from the annual revenue to get the net annual revenue. From the breakdown provided in
Section V.2, the total annual O&M costs, including energy losses, amount to 10,277,238
DJF. Therefore, the net annual revenue is:
The capital investment for the project, as calculated earlier, is 56,170,000 DJF. The
payback period is calculated by dividing the capital investment by the net annual revenue:
The project is expected to return its initial investment in less than a year, suggesting a
positive short-term financial return and demonstrating the project's strong financial base
and the efficiency of the power supply design.Net Present Value (NPV)
The net present value (NPV) is a financial data that determines the time value of money
by discounting future cash flows. A positive NPV shows that a project will provide more
value than it costs, making it financially viable. It is determined using a 10% discount
rate over a 10-year period.
29
𝑇
𝑅𝑡
𝐍𝐏𝐕 = ∑ − 𝑪𝒐
(1 + 𝑟)𝑡
𝑡=1
Where:
To determine the project's net present value (NPV), divide the net annual revenue by the
discounted future cash flows over a 10-year period, minus the initial capital investment.
The project is predicted to have a positive net present value (NPV), indicating increased
financial stability due to discounted future cash flows.
The internal rate of return (IRR) is the discount rate at which the project's net present
value (NPV) equals zero, indicating a high return on investment. With a payback period
of less than a year, the IRR is predicted to be much greater than the 10% discount rate,
maybe surpassing 100%, validating the Barwaqo 2 Extension's strong profitability.
30
CONCLUSION AND RECOMMENDATION FOR FUTURE RESEARCH
The study on the Barwaqo 2 extension's electric power supply emphasizes the importance
of a well-planned approach, considering factors like power consumption, network
architecture, transformer sizing, and substation needs. The 630 kVA transformer and
overhead distribution network were chosen for their cost-effectiveness, dependability,
and scalability. The project is profitable, with a payback period of less than a year, and
adaptable to future growth and urbanization.
This study shows that the Barwaqo 2 extension electrification project is technically and
economically feasible, and it emphasizes the importance of forward-thinking strategies
that incorporate future research into demand forecasting, renewable energy integration,
and system adaptability to support Djibouti's sustainable growth and energy resilience.
31
REFERENCES
[1] (2024) Cité résidentielle Barwaqo 2 extension -SOMELEC Real estate Investment co.
[2] Idris Bexi Warsama (2017) PROGRAMME D’ELECTRIFICATION DURABLE
Etude d’Impact Environnemental et Social Actualisée.
[3] (2017) Realisation de postes HTA/BT de distribution publique.
Link:https://www.enedis.fr/sites/default/files/SeQuelec_Guide_9.pdf[Accessed:13/11/2
018]
[4] "How do the streetlights turn on automatically at night?"
link: https://science.howstuffworks.com/environmental/energy/question363.htm
[5] Hadi Saadat, “Power System Analysis”, Milwaukee Scholl of Engineering. WBC
McGraw Hill.
[6] B. METZ-NOBLAT, F. DUMAS, C. POULAIN (2005) Calculation of short-circuit
currents.
[7] How Voltage Drop Affect Electrical Equipment and Installations.
Link: https://www.electricalengineeringtoolbox.com/2016/01/how-voltage-drop-affect-
electrical.html
[8] Differential circuit breakers.
Link: http://www.gefit.com/en/printpdf/608
[9] Dr. Tom Van Doren, Van.Company, Rolla. WHY and HOW to GROUND
ELECTRICAL SYSTEMS?
Link:
https://dce.mst.edu/media/extendedlearning/dce/documents/facetofacecourses/Why%20
and%20How%20to%20Ground%20Electrical%20Systems%20Ground.pdf
[10] Electricité de_Djibouti_WIkipedia available on link
32
APPENDICES
33
Figure A.2: material prices
34
Appendices B: Low Voltage network and urban distribution setup
35
Figure B.4: Repair of a defective NF C33-226 cable using a junction box.
Figure C.1: repaired low voltage networks in residential district future city.
36
Figure C.3: Neutral connection
37
Faculty of Engineering & Energy Department
RESUME:
Ce rapport présente une étude complète du projet d'électrification de l'extension Barwaqo
2. Le projet vise à concevoir et à mettre en œuvre un système d'alimentation électrique
fiable pour une nouvelle zone résidentielle. L'étude couvre l'analyse de la demande en
électricité, la conception du réseau, la construction de sous-stations et le
dimensionnement des transformateurs. La faisabilité économique et l'efficacité technique
ont également été évaluées, garantissant que l'infrastructure réponde aux besoins
énergétiques actuels et futurs. Le transformateur proposé de 630 kVA pourra répondre à
la croissance attendue de la demande tout en maintenant la stabilité et la qualité de
l'alimentation. Le projet est financièrement viable avec un délai de récupération court,
améliorant ainsi les conditions de vie à Barwaqo 2.
The work contained within this document has been submitted by the student in
partial fulfilment of the requirement of their course and award
38