PS Operation Final
PS Operation Final
1
Author: Belchior Conde
So, it is essential that the system which is the theoretical maximum phase
operator keep spinning reserve online so angle, until the shaft eventually break, so
as to supply anticipated maximum demand separating the two components, the engine
even if a large generator is unexpectedly and the conveyor. The same is true of an
tripped-off of the system. Spinning reserve electrical system, but, in a power system
consists of spare capacity, that is, transmission lines and generators might
generators already synchronized and trip, synchronism may be lost, load might
available. If spinning reserve is not enough be shed and power blackout might occur.
then the frequency will continue to drop, in
Systems which lose synchronism
this case load must be shed until the
are said to be unstable. In a real world of
generator load balance is again reached.
course, the phase angle limit is well below
Let us return to our mechanical the 90°, since system operators need to
system and take a closer look at the have plenty of margin for emergencies. In
connection between the engine and the fact, the phase angle will rarely exceed 10°
conveyor. All of the power used by the or 15° across any given line, nor will it very
conveyor is transferred across the shaft. It often exceed 30° or 40° from one end of the
is difficult to see, or even imagining, but system to the other. When we talk about
there is in fact a twist developed in the the load angle on a generator, we are
shaft. It would be much easier to imagine looking at the position of the rotor field
this twist if we consider the shaft to be relative to the stator field. On a
made of heavy rubber. transmission line, we are talking about
angular difference between the voltage at
By increasing the load, the
one end of the line and the voltage at the
receiving-end lags behind the driving-end,
other end.
conversely, by increasing the power driving
it, then the driving-end advances in angle. PER-UNIT
There is a distinct angular displacement
For convenience, engineers very
between one end of the shaft and the other.
often work with electrical quantities such as
The greater the load transfer across the
voltage, current and impedance on a per-
shaft, the greater will be the twist or the
unit basis, instead of an actual volts, amps
angle between the two ends. The amount
or ohms. Per-unit values are obtained by
of twist, measured in degrees, is referred to
dividing the actual value by an assumed
as phase angle or load angle and it is
base value. For example, if the actual
directly proportional to the load.
impedance of a circuit element, say a
If an overload occurs, by adding transmission line, is 80 ohms and the base
more coal to the conveyor, then the load impedance is 100 ohms, then the line’s per-
angle advances, up to a maximum of 90° –
2
Author: Belchior Conde
unit impedance is simply 0.8 per-unit or 80 the assignment of input and output
%. units.
3
Author: Belchior Conde
the PSS/E package. The user does not generation, network separation and
need to become proficient with a so on.
complicated computer command language
4. Correct data errors by adding,
and, is therefore, able to apply effort to the
editing or removing data.
task at hand – solving the engineering
5. Check network condition:
problem.
a) If it has weak diagonal
The casual PSS/E user will need to
dominance, then don’t use
become comfortable with the basic
Gauss-Seidel method.
capabilities of the text editor and a small
subset of system keyboard commands. b) If R/X is high, say 0.5, then
More advanced users will find it to their don’t use decoupled
advantage to familiarize themselves with Newton-Raphson method.
the various disk file and related utility 6. Check boundary condition:
programs. A fundamental understanding of
a) If network voltage profile is
the host computer’s file system
not flat, then use Gauss-
organization will also be useful.
Seidel method.
The more sophisticated user, on the
7. Select a method, solve the case,
other hand, may use the full power of the
Fortran language in the connection adjust system conditions and
4
Author: Belchior Conde
4. Network is not solvable – check
network and boundary
conditions.
5
Author: Belchior Conde