PMP Lesson#07.2 (Cost & Quality & Resourcses & Communication & Stakeholders)
PMP Lesson#07.2 (Cost & Quality & Resourcses & Communication & Stakeholders)
C R E A T E & E X C H A N G E
Planning
C R E A T E & E X C H A N G E
Project Management
Budget Reserve
Contingency
Cost Cost Reserve
Baseline Accounts Activity
Contingency Reserve
Work Package
Cost Estimates Activity Cost
Total Amount
Estimates
Funding Requirements
Expenditures
Cost Baseline
Time
A. $496,000
B. $400,000
C. $320,000
D. $200,000
Rates
C R E A T E & E X C H A N G E
Quality vs Grade
Process vs Deliverable
Prevention vs Inspection
Cost of Quality
Planning
C R E A T E & E X C H A N G E
Reward and Recognition Plans
Rewards Recognition
• Organizational Theory: The study of how people, teams, and organizations behave.
• Purpose of organizational theory
▪ Maximize efficiency and productivity
▪ Solve problems
▪ Motivate people
▪ Meet stakeholder requirements
Planning
C R E A T E & E X C H A N G E
C D
High Keep Satisfied Key Players
Power
Low A B
Minimal Effort Keep Informed
Low High
Level of Interest
Planning
C R E A T E & E X C H A N G E
Example: Communications Management Plan
▪ Push Communication
▪ Pull Communication
▪ Interactive Communication
Communication Methods
▪ Written/Verbal
▪ Formal/Informal
Transmit
Current Message Current
Emotional Emotional
State Encode Noise Decode State
Culture: Acknowledge Culture:
• Generational Noise • Generational
Message
• National Sender Receiver • National
• Professional Medium • Professional
discipline discipline
• Gender • Gender
Personality Decode Encode Personality
biases Feedback biases
(assumptions) Noise Message (assumptions)
Face-to-Face
at whiteboard
Phone
Interactivity
Instant
Messaging
Video
Recording
Audio
Recording
E-mail
Paper
Bandwidth/Information Density
Information Radiators
PV -Planned Value PV =Schedule % complete x BAC CV -Cost Variance CV= EV-AC Neutral - On planned cost
If both CPI and SPI influence the EAC =AC+ [(BAC - EV)/(CPI x SPI)]
remaining work
The efficiency that should be maintained TCPI = (BAC -EV)/(BAC -AC) Greater than 1.0 - Harder to complete
in order to complete on time Exactly 1 . 0 - Same to complete Less
than 1.0 -Easier to complete
TCPI
The efficiency that should be maintained TCPI = (BAC - EV)/(EAC - AC) Greater than 1.0 - Harder to complete
in order to complete the current EAC Exactly 1.0 -Same to complete Less than
1.0-Easier to complete
Free float/slack Total Free Float= Early start of Successor activity - Early Finish -1
Three-Point Estimating
Duration Estimate Standard Deviation
Number of
For N people, the number of
communication
communication channels = (N2 – N)/2
channels