IPPTChap 010
IPPTChap 010
PROJECT ANALYSIS
• Capital Budget
• List of investment projects under consideration
by a firm
• Do not add fudge factors to cost of capital
• Postaudit
• Review of project to see if met forecasts
10-2
10-2 SENSITIVITY ANALYSIS
• Types of Analysis
• Sensitivity
• Analyzes effects of changes in sales, costs, etc., on project
• Scenario
• Project analysis given particular combination of
assumptions
• Simulation
• Estimates probabilities of different outcomes
• Break Even
• Level of sales (or other variable) at which project breaks
even
10-3
10-2 SENSITIVITY ANALYSIS
• Example
• Given expected cash-flow forecasts for Otobai
Company’s Motor Scooter project, determine
the NPV of project given changes in cash- flow
components using 10% cost of capital. Assume
constant variables, except the one you are
changing.
10-4
10-2 SENSITIVITY ANALYSIS
• Example, continued
Year 0 Years 1 - 10
Investment - 15
Sales 37.5
Variable costs 30
Fixed costs 3
Depreciati on 1.5
Pretax profit 3.0
Taxes @ 50% 1.5
Profit after tax 1.5
Operating cash flow 3.0
Net Cash Flow - 15 3
10-5
10-2 SENSITIVITY ANALYSIS
• Example, continued
Outcomes
Variable Pessimisti c Expected Optimistic
Market size .9 mil 1.0 mil 1.1 mil
Market share .04 .1 .16
Unit price 350,000 375,000 380,000
Unit var cost 360,000 300,000 275,000
Fixed cost 4 bil 3 bil 2 bil
10-6
10-2 SENSITIVITY ANALYSIS
• Example, continued
• NPV calculations—Optimistic scenario
Year 0 Years 1 - 10
Investment - 15
Sales 41.25
Variable costs 33
Fixed costs 3
Depreciati on 1.5
Pretax profit 3.75
Taxes @ 50% 1.88
Profit after tax 1.88
Operating cash flow 3.38
Net Cash Flow - 15 3.38
10-7
10-2 SENSITIVITY ANALYSIS
• Example, continued
10-8
TABLE 10.3 NPV OF ELECTRIC SCOOTER
10-9
TABLE 10.3 ELECTRIC SCOOTER ASSUMPTIONS
10-10
TABLE 10.4 ELECTRIC SCOOTER SCENARIOS
10-11
TABLE 10.5 ELECTRIC SCOOTER ACCOUNTING
PROFIT
10-12
TABLE 10.1 ELECTRIC SCOOTER CASH-FLOW
FORECASTS
10-13
FIGURE 10.1 BREAK-EVEN CHART
• Point at which NPV=0 is break-even point
• Otobai Motors has a break-even point of 85,000
units sold
PV (Yen) PV inflows
Billions
Break-even
400 NPV = 0
200 PV
Outflows
19.6
Sales, thousands
60 200 10-15
10-2 SENSITIVITY ANALYSIS
• Operating Leverage
• Degree to which costs are fixed
or
fixed costs
DOL 1
profits
10-16
10-2 SENSITIVITY ANALYSIS
• Example
• Using the data from the Otobai scooter project,
calculate the DOL
(3 1.5)
DOL = 1 2 .5
3
10-17
10-3 MONTE CARLO SIMULATION
• Modeling Process
• Step 1: Model Project
• Step 2: Specify Probabilities
• Step 3: Simulate Cash Flows
• Step 4: Calculate Present Value
10-18
FIGURE 10.3 SIMULATION OF CASH FLOWS
10-19
10-4 REAL OPTIONS AND DECISION TREES
• Decision Trees
• Diagram of sequential decisions and possible
outcomes
• Help companies analyze options by showing
various choices and outcomes
• Option to avoid a loss or produce extra profit
has value
• Ability to create option has value that can be
bought or sold
10-20
FIGURE 10.4 FEDEX’S EXPANSION OPTION
10-21
FIGURE 10.4 FEDEX’S EXPANSION OPTION
• Real Options
• Option to expand
• Option to abandon
• Timing option
• Flexible production facilities
10-22
FIGURE 10.6 DECISION TREE
$700 (.80)
- $130
.25
$ 0 (.20)
$ 300 (.80)
- $18 .44 .50 - $130
Invest .56
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= ? - $130
$ 0 (.20)
10-23
FIGURE 10.6 DECISION TREE
$700 (.80)
- $130
560
.25
$ 0 (.20)
$ 300 (.80)
- $18 .44 .50 - $130
240
Invest .56
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= ? - $130
80
$ 0 (.20)
10-24
FIGURE 10.6 DECISION TREE
$700 (.80)
- $130
560
.25
$ 0 (.20)
$ 300 (.80)
- $18 .44 .50 - $130
240
Invest .56
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= ? - $130
$ 0 (.20)
10-25
FIGURE 10.6 DECISION TREE
$700 (.80)
NPV = $295
- $130
560
.25
$ 0 (.20)
$ 300 (.80)
560
- $18 .50 130
NPV (upside)
.44
- $130 295
1.096 3
240
Invest .56
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= ? - $130
80
$ 0 (.20)
10-26
FIGURE 10.6 DECISION TREE
$700 (.80)
NPV = $295
- $130
560
.25
$ 0 (.20)
$ 300 (.80)
- $18 .44 .50 - $130
240
Invest .56 NPV = $52
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= ? - $130
80
NPV = - $69
(do not invest, so NPV =
$ 0 (.20)
0)
10-27
FIGURE 10.6 DECISION TREE
$700 (.80)
NPV = $295
- $130
560
.25
$ 0 (.20)
NPV = $83 $ 300 (.80)
- $18 .44 .50 - $130
240
NPV = $52
Invest .56
Yes / No $0 $ 0 (.20)
.25 (0 .25) (52 .5) (295 .25)
NPV $2 100 (.80)
NPV= ? - $130 1.096
NPV = - $69 $83
80
(do not invest, so NPV =
$ 0 (.20)
0)
10-28
FIGURE 10.6 DECISION TREE
$700 (.80)
NPV = $295
- $130
560
.25
$ 0 (.20)
NPV = $83 $ 300 (.80)
- $18 .44 .50 - $130
240
NPV = $52
Invest .56
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= $19 NPV 18 (.-44 83) (.56 0)
$130
$19
NPV = - $69
80
(do not invest, so NPV =
$ 0 (.20)
0)
10-29
FIGURE 10.6 DECISION TREE
$700 (.80)
NPV = $295
- $130
560
.25
$ 0 (.20)
NPV = $83 $ 300 (.80)
- $18 .44 .50 - $130
240
NPV = $52
Invest .56
Yes / No $0 $ 0 (.20)
.25
$ 100 (.80)
NPV= $19 - $130
80
NPV = - $69
(do not invest, so NPV =
$ 0 (.20)
0)
10-30