9.3 Operations Strategy
9.3 Operations Strategy
4
paper
Operations decision
Strategic operations decisions include:
• expanding or reducing capacity
• locating a business or relocating it
• offshoring or reshoring
• outsourcing
• changing operations (production) methods
• application of IT and AI
Operations decision
The influence of human, marketing and finance
resource availability on operations decisions :
all department involve !
cost &
Process innovation :
- the use of new or much – improved production methods or
service delivery methods.
Flexibility and innovation eg . buy from
> send
-
by
PRIME
drone
or
in
AMAZON
an hour
-
can deliver on time
word
WASTE MANAGEMENT
came- Lean production approach is about reducing the
causes of waste in business organisation.
- Specifically, the waste of physical resources, resulting
from damage in inventory or defective products
that have to be rejected, can be reduced by:
• JIT to reduce inventory holdings and the risk of
damage before materials and components are
needed in production.
total quality management
• Adopting TQM and zero-defect principles. These
-
~
4. Efficiency >
-
less waste >
-
copt
5. Quality>
-
no" detect less waste
OPERATION PLANNING
The need for operation planning:
b. Put the tasks that make up the project into the right sequence and
draw a network diagram
e. Use the network as a control tool when problems occur during the
project
Main elements of a network diagram: activities,
dummy activities, nodes
1.NODE
start time
number · -> earliest
5 3
of [ EST A EST B EST
activity I > &
2
LFT 3
LFT LFT
& G
↓
latest finish time duration 5
-------
2.ACTIVITIES ↓
not an
3. DUMMY ACTIVITIES
Construction of a network
(after (
after BB (
network diagram .
976738
J
> O
22
322 T & 53 38
4
El 7
7
14
D
H
6 14
C
A
288 12
3 420
2/
G
7 1) Minimum duration : 42 days (actual =
80 days
z
I
2) Critical path/activities
:
G
B
Cimportant activity that needs
to be done A S A P without
. . .
6
no delay (
critical path
y
a)A + E + F + G + 1 + j =
42 days
+ c + D + G + 1 + 3 41 day
b)A
=
+ c + H + 1 + j =
41 days
c)A
D + G + 1 + 7 = 22 days
a)b +
+
H 1 + 7 =
27 days
e) B
+
3) Non-critical path :
(can be delayed
=
B , C ,
D ,
It (all that are not in critical
LFT-duration -
EST EST (next activity
-
duration -
EST (these activity (
Total float Free float
0 = 15
B21 -
6 -
- 6 -
0 = 14
20
1
8 =
0
8
=
12
-
1
-
(21
-
20
6 20 = 6 = 6
6 2
-
D 32 3
- -
-o
-
just a -
count of value total
EST· highest 20 = 1
no des
35 14 1 35
-
14 -
H 20 =
- -
(don't
matter the LFT
count
position (
4 .
R to L
·
minus
· lowest value total
B 18 D 22 F 25
A 4 >
5 2 H 28
> 2
j3 18
12
22
3 6 7 7
4 4 25 3 28
1
& 7
I
&
C Il E
7 4
7 13 9
16
Free float
Total float EST (now
duration
-
LFT-duration -
2 7 - 4 = 0
4 =
I
-
13 7-
C
-
2
9 11 =
1 = 2 -
22
-
a
E
-
22
= 5
Minimum duration : 5 -
4
= 16
4 25
-
25 16
-
-
=
28 days E
Critical path :
A + B + D + F + H =
28
C ,
E
, a
2
18
g 3 14 16
j 3 14 16
18
18
critical :
5. < ESSAY GUIDE
5
non
critical path :
H 16
4
=
+
+ D +
b)n 2) Can be a control tool for the manager
-
F float
.
-
if don't have this - all delay > cost for the project ↑
-
to pay
- -
-
compensation to
B 6 2 0 = 4
-
however ,
pandemic is beyond customers it delay
0
-
2 -0
-
2 =
-
-
control
C 10 -
2 -
3
=
55 -
2 -
3 =
0 3) allow business to give accurate
delivery date
-
inform cust
E 14 -
8 -
2 =
4/14
-
8 -
2
=
4
F 14 -
4 -
5 =
5 14 -
4
- 5
=
5
4
. x ESSAY GUIDE <S
-
Lft =
-right to left
-subtract
-take the lowest value
Calculating critical path
- class discussion
Calculating float times for non – critical
activities
Total float
-is the amount of time an activity can be delayed
without delaying the whole project duration
- LFT – DURATION - EST
Free float
-is the amount of time an activity can be delayed
without delaying the start of the following activity
-EST(next activity)-DURATION-EST(these activity)
ADVANTAGES
• Using a network diagram to calculate the total project
duration allows businesses to give accurate delivery dates.
• Calculating an EST for each activity allows the operations
manager to order special equipment or materials needed
for that task at the correct time.
• Knowing the critical path is important. If there is a delay on
a critical activity, as there is no float time, this will put back
the timing of the whole project. This could lead to expensive
damage claims from customers.
• The additional resources for speeding up a critical activity
could come from the non-critical ones.
• The sequential and logical structure of the diagram lends
itself well to computer applications and nearly all business
applications of network analysis are now run on computer.
• The need to put all activities into sequence in order to
structure the diagram each project carefully by putting
activities in the correct order.
• Network analysis gives design and engineering departments
an advantage by showing them the tasks that can be
undertaken simultaneously in developing a new product.
eg GBH can be done tot > save time
-
.
DISADVANTAGES
• Network analysis will only be helpful if the data used to
construct diagrams is reliable.
• Construction of network alone will not guarantee the
smooth completion of a project. factors) >
- eg . Covid >
-
Mainly focus on time and not cost > When profit is the main objective
•
-
workers/workers
eg . not
enough
sick >
-
no extra workers
G
>
·