Tutorials 1
Tutorials 1
Activity
Activity Duration range
PERT Dur. Variance
S.D. at 68%
Activity O ML P (Mean)
confidence
O+(4xML) + P {(P-O)/6}2
(P-O)/6 level
6
20.83
30 6.250 20.83 +/- 2.50
A 15 20 2.50
15+80+30 2.50 x 2.50) 18.33 to 23.33
6
20.00+/- 3.33
B 10 20 30 20.0 3.33 11.088
16.67 to 23.33
5.034
25.346
(Sq. Rt of 60.99 +/-5.034
For Path (Total
60.99 25.346
Level Activity
which is 55.965 to
A+B+C Variance for
Variances 66.024
A+B+C)
of A+B+C
Standard Deviation
Q1.1 Find the PERT duration and standard deviation for the three activities
Q1.2 Find the PERT duration and standard deviation for the path A, B and C
Q1.3 Calculate a duration range to complete each activity and the complete project at about 68%
confidence factor.
Class Exercises Answers
Q. EV1 A project has 4 activities – A, B, C and D. At review point this was the position in man-
hours.
A 160 90 150
B 200 50 140
C 100 60 50
D 300 75 225
------- -------
760 565
EV1.1 What is the earned value for each activity and the project at review point?
EV1.2 What is the overall % complete of the project?
EV1.3 What is the current cost efficiency?
EV1.4 What are the man-hours the project is likely to take to be completed based on the
current cost efficiency.
EV for B = 100
EV for C = 60
EV for D = 225
1.2 Overall % complete of the project is: 69.6% (EV / BAC) = (529/760) = 69.6%
1.3 Current cost efficiency of the project is: 93.6% (EV/AC) = 529/565 = 0.936
1.4 Expected man-hours (EAC) based on current performance = 812 Man-hours (BAC/CPI)
Class Exercises Answers
Earned Value – 2
Q. Estimate likely time for completion of project if efficiency becomes 100% from month 5.
Ans. = Current month + Backlog months + Remaining months
( for backlog months compare BCWS with BCWP)
=4+2+8
= 14 months at 100% efficiency
Class Exercises Answers
Earned Value – 3
Resource histogram
Act. A 2 2 2 2 2 2
Act. B 4 4 4 4
Act. C 6 6 6 6 6
Weeks 1 2 3 4 5 6 7 8 9 10
Wkly 8 8 8 8 8 2 4 4 4 4
Resources
Cum. 8 1 2 32 40 42 4 50 54 58
Resources 6 4 6
Class Exercises Answers
Earned Value 4
Month PV in Rs AC in Rs EV
1 100 100 50
2 200 250 150
3 300 400 201
4 400 550 300
6 Forecast the expected cost of the project based on the current performance.
Expected cost of project as per current performance is Rs 1833.
BAC / CPI = 1000/54.5
7 Forecast the expected cost of the project if the efficiency becomes 50% from 5th month.
Expected cost of project if efficiency is 50% from month 5 is Rs. 1950
AC + BAC-EV = 550+ (700 /.5) = 1950
.5
8 Forecast the expected cost of project if efficiency becomes 100% from 5th month.
Expected cost of project if efficiency is 100% from month 5 is Rs. 1250
AC + BAC-EV = 550 + 700 = 1250
1
9 Forecast the time when the project can be expected to be completed assuming 100%
efficiency from month 5 onwards.
Project can be expected to be completed in 13 months.
(current month + backlog months + remaining months) = 4 + 1 + 8 = 13 months
Class Exercises Answers
NPV - 1
------------------------------------------------------------------------------------------------------------------------------------
Year Discount Cash Flow A PV A Cash Flow B PV B
Factor (Rev.-Exp.) (Cash Flow x DCF) (Rev.- Exp.) (Cash Flow x DCF)
(Rs) (Rs) (Rs) (Rs)
------------------------------------------------------------------------------------------------------------------------------------
1 .90 3000 2700 3000 2700
Note: (A higher NPV is better. If NPV negative then one should not go ahead with project.)
Class Exercises Answers
NPV – 2
-------------------------------------------------------------------------------------------------
Year Discount Cash Flow in Rs PV Rs
Factor (Anticipated annual return) (Cash Flow x Discount Factor)
or cash flow
-------------------------------------------------------------------------------------------------
1 .909 2000 1818
2 .826 2000 1652
3 .751 2000 1502
4 .683 2000 1366
--------- -------
6338
Less Initial investment - 7500
--------
NPV = - 1162
or
--------------------------------------
IRR-1
Ans.
Contractor’s Fee =
210,000 - 250,000 (Target cost minus Actual cost)
-40,000 x 20% = -8000 (20% of extra cost)
25,000 - 8000 = 17,000 (Target fee less share of cost overrun)
Contractor fee = 20,000/- (Minimum Fee assured is 20,000)
Final Price of contract = Actual cost + Contractor’s fee
= 250,000 + 20,000 = 2,70,000/-
Contractor Fee
= 10,000 x .25 (share ratio of cost savings -Target cost less Actual cost)
= 2,500 + 10,000 (cost saving share + Target fee)
= 12,500
Final Price
= 90,000 + 12,500 (Actual cost + contractor Fee)
= 1,02,500
---------------------------------------------------------------------------
FPIF Example 2
Target Cost 1,50,000
Target Fee 10,000
Target Price 1,60,000
Share Ratio 80/20
Ceiling Price 1,75,000
Actual Cost 1,70,000
Contractor’s Fee
[(150,000 – 170,000) (.20) = -4000 Fee reduction
= 10,000 - 4000 (10,000 less 4000) Target fee after adjusting for 20% excess
cost
= 6000 – 1000 = 5000 (Reduced due to ceiling)
Final Price
170,000 + 5000
= 1,75,000 (Limited to ceiling)