0% found this document useful (0 votes)
1 views

Tutorials 1

The document contains various class exercises and answers related to project management concepts such as PERT analysis, earned value management, and net present value calculations. It includes calculations for project durations, variances, earned value, cost efficiency, and forecasts for project completion. Additionally, it discusses contract types like Cost Plus Incentive Fee and Fixed Price Incentive Fee with examples.

Uploaded by

Narendra Saxena
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1 views

Tutorials 1

The document contains various class exercises and answers related to project management concepts such as PERT analysis, earned value management, and net present value calculations. It includes calculations for project durations, variances, earned value, cost efficiency, and forecasts for project completion. Additionally, it discusses contract types like Cost Plus Incentive Fee and Fixed Price Incentive Fee with examples.

Uploaded by

Narendra Saxena
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Class Exercises Answers

Activity
Activity Duration range
PERT Dur. Variance
S.D. at 68%
Activity O ML P (Mean)
confidence
O+(4xML) + P {(P-O)/6}2
(P-O)/6 level
6
20.83
30 6.250 20.83 +/- 2.50
A 15 20 2.50
15+80+30 2.50 x 2.50) 18.33 to 23.33
6

20.00+/- 3.33
B 10 20 30 20.0 3.33 11.088
16.67 to 23.33

20.16 +/- 2.83


C 12 20 29 20.16 2.83 8.008
17.33 to 22.99

5.034
25.346
(Sq. Rt of 60.99 +/-5.034
For Path (Total
60.99 25.346
Level Activity
which is 55.965 to
A+B+C Variance for
Variances 66.024
A+B+C)
of A+B+C
Standard Deviation

Q A path has 3 activities A, B and C.

Activity Optimistic Most Likely Pessimistic


A 15 20 30
B 10 20 30
C 12 20 29

Q1.1 Find the PERT duration and standard deviation for the three activities
Q1.2 Find the PERT duration and standard deviation for the path A, B and C
Q1.3 Calculate a duration range to complete each activity and the complete project at about 68%
confidence factor.
Class Exercises Answers

Q. EV1 A project has 4 activities – A, B, C and D. At review point this was the position in man-
hours.

Activity Budgeted % Complete Actual


Man-hours of activity Man-hours

A 160 90 150
B 200 50 140
C 100 60 50
D 300 75 225
------- -------
760 565

EV1.1 What is the earned value for each activity and the project at review point?
EV1.2 What is the overall % complete of the project?
EV1.3 What is the current cost efficiency?
EV1.4 What are the man-hours the project is likely to take to be completed based on the
current cost efficiency.

1.1 EV for A = 144 (BCWS x % complete)

EV for B = 100

EV for C = 60

EV for D = 225

EV for the project = 529 Man-hours

1.2 Overall % complete of the project is: 69.6% (EV / BAC) = (529/760) = 69.6%

1.3 Current cost efficiency of the project is: 93.6% (EV/AC) = 529/565 = 0.936

1.4 Expected man-hours (EAC) based on current performance = 812 Man-hours (BAC/CPI)
Class Exercises Answers

Earned Value – 2

Q The Project budget is Rs. 1,00,000 and is planned to be completed in 12 months.

Month PV (BCWS) EV (BCWP) Actual Cost (ACWP)


1 7000 2000 2500
2 14000 6000 9000
3 22000 10000 15000
4 30000 14000 21000

Q. What is the schedule variance at month 4?


Ans. Schedule variance = EV – PV (BCWP – BCWS)
= 14000 – 30000
= -16000

Cost variance = EV – AC (BCWP – ACWP)


= 14000 – 21000
= -7000

Q. Cost of completion at end of 4th month is?


Ans. EAC = BAC / CPI
= 100,000 (14000/21000)
= 100,000 / .666
= Rs.1,50,000

Q. Estimate likely time of completion of project if efficiency remains same.


Ans. = Planned time to complete / SPI
= 12 months / (BCWP/BCWS)
= 12 (14,000/30,000)
= 12 / .4666
= 25.71 months

Q. Estimate likely time for completion of project if efficiency becomes 100% from month 5.
Ans. = Current month + Backlog months + Remaining months
( for backlog months compare BCWS with BCWP)
=4+2+8
= 14 months at 100% efficiency
Class Exercises Answers

Earned Value – 3

Activit Res. Duration Depend. Budget Week 4 Week 8


y
M/wk PV % Actual % Actual
Comp AC Comp
A 2 6 - 12 80 12 100 17
B 4 4 A 16 0 0 40 8
C 6 5 - 30 60 20 100 35

EV3.1 Find the total EV at week 4 and week 8.

EV at week 4 = 27.6 A = 9.6 (12x.8) Budget x % Complete


B=0
C = 18 (30x.6)

EV at week 8 = 48.4 A = 12x100% = 12 Budget x % Complete


B = 16x40% = 6.4
C = 30x100% = 30

EV3.2 What is the % complete at week 4 and week 8.


% complete at Week 4 = 47.5% EV/BAC = 27.6/58 = 47.5%
Week 8 = 83.4% 48.4/58 = 83.4%

EV3.3 What is the efficiency at week 4 and week 8.


Efficiency at Week 4 = 86% EV/AC = 27.7/32 x 100 = 86.25%
Week 8 = 81% EV/AC = 48.4/60 x 100 = 80.66%

EV3.4 Draw a Resource histogram

Resource histogram

Act. A 2 2 2 2 2 2
Act. B 4 4 4 4
Act. C 6 6 6 6 6

Weeks 1 2 3 4 5 6 7 8 9 10
Wkly 8 8 8 8 8 2 4 4 4 4
Resources
Cum. 8 1 2 32 40 42 4 50 54 58
Resources 6 4 6
Class Exercises Answers

Earned Value 4

Following are details of a project that is planned to be completed in 12 months at a total


cost of Rs.1000. The project is being reviewed at the end of month 4.

Month PV in Rs AC in Rs EV
1 100 100 50
2 200 250 150
3 300 400 201
4 400 550 300

1 Calculate the schedule variance at month 4.


Schedule Variance = EV - PV = 300 - 400 = -Rs. 100

2 Calculate the cost variance at month 4.


Cost Variance = EV - AC = 300 - 550 = -Rs. 250

3 What is the cost efficiency of the project?


Efficiency is 54.5% (CPI i.e. EV/AC)

4 What is the status of the project?


The project is over budget by Rs. 250 and behind schedule by 25%

5 Forecast the time when the project can be expected to be completed


based on the current performance.
Forecasted completion date = OD/SPI = 12 / .75 = 16 months

6 Forecast the expected cost of the project based on the current performance.
Expected cost of project as per current performance is Rs 1833.
BAC / CPI = 1000/54.5

7 Forecast the expected cost of the project if the efficiency becomes 50% from 5th month.
Expected cost of project if efficiency is 50% from month 5 is Rs. 1950
AC + BAC-EV = 550+ (700 /.5) = 1950
.5
8 Forecast the expected cost of project if efficiency becomes 100% from 5th month.
Expected cost of project if efficiency is 100% from month 5 is Rs. 1250
AC + BAC-EV = 550 + 700 = 1250
1
9 Forecast the time when the project can be expected to be completed assuming 100%
efficiency from month 5 onwards.
Project can be expected to be completed in 13 months.
(current month + backlog months + remaining months) = 4 + 1 + 8 = 13 months
Class Exercises Answers

NPV - 1

------------------------------------------------------------------------------------------------------------------------------------
Year Discount Cash Flow A PV A Cash Flow B PV B
Factor (Rev.-Exp.) (Cash Flow x DCF) (Rev.- Exp.) (Cash Flow x DCF)
(Rs) (Rs) (Rs) (Rs)
------------------------------------------------------------------------------------------------------------------------------------
1 .90 3000 2700 3000 2700

2 .80 5000 4000 10000 8000

3 .70 10000 7000 15000 10500

4 .60 10000 6000 20000 12000

5 .50 10000 5000 10000 5000


---------- ---------
24,700 38,200
---------- ----------

Less Initial investment 20,000 40,000

NPV for option A = 24,700 - 20,000 = Rs. 4,700

NPV for option B = 38,200 - 40,000 = Rs. -1,800

Option A is the better option.


The NPV of option B is negative so one should go for option A.

Note: (A higher NPV is better. If NPV negative then one should not go ahead with project.)
Class Exercises Answers

NPV – 2

-------------------------------------------------------------------------------------------------
Year Discount Cash Flow in Rs PV Rs
Factor (Anticipated annual return) (Cash Flow x Discount Factor)
or cash flow
-------------------------------------------------------------------------------------------------
1 .909 2000 1818
2 .826 2000 1652
3 .751 2000 1502
4 .683 2000 1366
--------- -------
6338
Less Initial investment - 7500
--------
NPV = - 1162

or

NPV = (2000/1.101 + 2000/1.102 + 2000/1.103 + 2000/1.104 ) - 7500


= 2000/1.10 + 2000/(1.10x1.10) + 2000/(1.10x1.10x1.10) +
2000/(1.10x1.10x1.10x1.10)
= (2000/1.10 + 2000/1.21 + 2000/1.331 + 2000/1.464) - 7500
= (1818 + 1652 + 1502 + 1366) - 7500
= 6338 - 7500 (initial investment) NPV = -1162

Ans. 2.2 Project is not viable as the NPV is negative.

--------------------------------------

IRR-1
Ans.

Year Cash Flow Discount Factor Present Value


@ 8%
0 (149,500) 1.0 (149,500)
1 39,995 .926 37,035
2 40,000 .857 34,280
3 40,000 .794 31,760
4 40,000 .735 29,400
5 25,000 .681 17,025
Net Present Value 0

IRR for the project is 8%

Cost Plus Incentive Fee (CPIF)


Class Exercises Answers

Contract details are:


Target Cost 2,10,000
Target Fee 25,000
Target Price 2,35,000
Share Ratio 80/20 (Buyer/Seller)
Minimum Fee 20,000
Actual Cost 2,00,000
Contractor’s Fee =
210,000 - 200,000 (Target Cost minus Actual cost)
10,000 x 20% = 2000 (20% of cost saving)
25,000 + 2000 = 27,000
Final Price of contract = Actual cost + Contractor’s fee
= 2,00,000 + 27,000 = 2,27,000/-
-------------------------------------------
CPIF Example 2
Contract details are:
Target Cost 2,10,000
Target Fee 25,000
Target Price 2,35,000
Share Ratio 80/20 (Buyer/Seller)
Minimum Fee 20,000
Actual Cost 2,50,000

Contractor’s Fee =
210,000 - 250,000 (Target cost minus Actual cost)
-40,000 x 20% = -8000 (20% of extra cost)
25,000 - 8000 = 17,000 (Target fee less share of cost overrun)
Contractor fee = 20,000/- (Minimum Fee assured is 20,000)
Final Price of contract = Actual cost + Contractor’s fee
= 250,000 + 20,000 = 2,70,000/-

Fixed Price Incentive Fee (FPIF) contract


Example 1
Target Cost 1,00,000
Class Exercises Answers

Target Fee 10,000


Target Price 1,10,000
Share Ratio 75/25
Price Ceiling 20,000 (Max. payout)
Actual Cost 90,000

Contractor Fee
= 10,000 x .25 (share ratio of cost savings -Target cost less Actual cost)
= 2,500 + 10,000 (cost saving share + Target fee)
= 12,500
Final Price
= 90,000 + 12,500 (Actual cost + contractor Fee)
= 1,02,500
---------------------------------------------------------------------------
FPIF Example 2
Target Cost 1,50,000
Target Fee 10,000
Target Price 1,60,000
Share Ratio 80/20
Ceiling Price 1,75,000
Actual Cost 1,70,000
Contractor’s Fee
[(150,000 – 170,000) (.20) = -4000 Fee reduction
= 10,000 - 4000 (10,000 less 4000) Target fee after adjusting for 20% excess
cost
= 6000 – 1000 = 5000 (Reduced due to ceiling)
Final Price
170,000 + 5000
= 1,75,000 (Limited to ceiling)

You might also like