Best Practice - Subsurface Utility Engineering (SUE) : Scope
Best Practice - Subsurface Utility Engineering (SUE) : Scope
Scope
This Best Practice is meant to help industry stakeholders and the public understand the concept of
Subsurface Utility Engineering (SUE) by defining it, citing relevant sources and portions of the Excavation
Requirements Statute and discussing practical application/intention of the Law.
Best Practices are recommendations of the Underground Damage Prevention Safety Commission (Safety
Commission).
SUE: Background
SUE is considered an effective practice by many organizations, including the American Society of Civil
Engineers (ASCE), American Council of Engineering Companies of Colorado (ACEC), American Public Works
Association (APWA), Federal Aviation Administration (FAA) and Department of Transportation (DOT). SUE is
used to better understand underground infrastructure during the planning and designing phases of projects to:
• Allow better execution during the construction phase
• Reduce risks of underground utilities
• Observe significant cost savings on projects
Without SUE, some projects may experience delays and extra costs resulting from:
• Unnecessary utility locations based on incorrect location information
• Unexpected utilities found during construction
• Redesign of utility or structural project components
• Utilities located at unexpected depths
• Utility damage
• Unanticipated utility relocation construction
The intent is to design around utilities in the interest of public safety. The recommendation is to
include SUE in the design phase. SUE combines civil engineering, surveying and geophysics to meet
damage prevention goals.
The Safety Commission interprets the intent of the language in the Law to be a “floor” not a ceiling – meaning
at a minimum, certain projects (those that meet the criteria as a SUE-required project per the Law) require
SUE. More stringent requirements may be required by the project owner. Furthermore, other projects that do
not meet SUE requirements per the Law may involve interaction with underground utilities, and performing a
SUE investigation still serves as a damage prevention tool. If a SUE investigation is not required or performed,
engineers should include utility information in design plans.
SUE Defined
“A branch of engineering practice that involves managing certain risks associated with utility
mapping at appropriate quality levels, utility coordination, utility relocation design and
coordination, utility condition assessment, communication of utility data to concerned parties,
utility relocation cost estimates, implementation of utility accommodation policies, and utility
design.”
For the purposes of this Best Practice, the Safety Commission is utilizing the definition from CI/ASCE 38-02
Section 3.0 (Definitions).
(6.8) “Subsurface utility engineering-required project” means a project that meets all of the
following conditions:
(a) The project involved a construction contract with a public entity, as that term is
defined in section 24-91-102;
(b) The project involves primarily horizontal construction and does not involve primarily
the construction of buildings;
(A) Has an anticipated excavation footprint that exceeds two feet in depth and
that is a contiguous one thousand square feet; or
(II) For purposes of this subsection (6.8) (c), the term “two feet in depth” does not
include rotomilling, and the contiguous one thousand square feet does not
include fencing and signing projects.
(d) The project requires the design services of a licensed professional engineer.
Practical Application
When is SUE required?
Per the Statute, SUE projects must meet all four of these requirements under subsection 6.8, summarized
as follows:
1. Has a construction contract with a public entity
2. Involves primarily horizontal construction
3. The project:
a. Has an anticipated excavation footprint that exceeds two feet in depth and that is a contiguous
one thousand square feet; or
b. Involves utility boring
4. Requires the services of a licensed professional engineer.
• For purposes of subsection 6.8(c), the term “two feet in depth” does not include rotomilling, and the
contiguous one thousand square feet does not include fencing and signing projects.
• The intent of the Law is to understand the types of underground utilities and their location. Having utility
information during the design phase is intended to help the design and construction process go
smoothly and ensure damage prevention.
For projects started prior to August 8, 2018, can a project be ‘grandfathered’ from SUE?
Projects must be evaluated individually, as they range from small to large and may have been in different
phases of planning and execution when the Law passed on August 8, 2018. The intent of SUE is to design the
project around utilities to protect underground infrastructure and public safety. Therefore, the Safety
Commission does not endorse grandfathering based solely on the August 8, 2018, effective date of the Law.
UDP Safety Commission Best Practice SUE Page 3 of 6
Excavation Requirements Statute §9-1.5-103(2.4)
At the project owner’s expense, a licensed professional engineer designing for a subsurface
utility engineering-required project shall:
(a) Notify the notification association with a subsurface utility engineering notification;
(b) Either:
(I) Meet or exceed the ASCE 38 standard for defining the underground facility location in
the stamped plans for all underground facilities within the proposed excavation areas;
or
(II) Document the reasons why any underground facilities depicted in the stamped plans
do not meet or exceed ASCE 38 utility quality level B or its successor utility quality
level;
(c) Attempt to achieve ASCE 38 utility quality level B or its successor utility quality level on all
utilities within the proposed excavation area unless a reasonable rationale by a licensed
professional engineer is given for not doing so; and
(d) Document the reasons why any underground facilities depicted in the stamped plans do
not meet or exceed ASCE 38 utility quality level A or its successor utility quality level for
underground facilities at the point of a potential conflict with the installation of a gravity-fed
system.
Practical Application
What is ASCE 38 and the quality levels referenced in § 9-1.5-103 (2.4)?
ASCE 38 Standard is a consensus standard by ASCE that references quality levels. Quality levels may be
thought of as degrees of risk. There are four recognized levels, ranging from Quality Level D (lowest level) to
Quality Level A (highest level).
• Similar to school grades, ASCE 38 advises levels of quality (i.e., diligence or uncertainty); it takes more
effort to achieve Quality Level A than Quality Level D (as an example).
• Quality levels are applied individually to specific segments of utilities.
• While the Law requires an attempt to achieve Quality Level B, contracts may request a higher level.
(a) Provide underground facility location records that give the available information on the
location, not to include depth, of underground facilities within the project limits;
(b) Provide a mark on the ground that gives the approximate location, not to include depth, of
its underground facilities within the project limits; or
(c) Provide the available information as to the approximate location, not to include depth, of
its underground facilities within the project limits.
Practical Application
What is meant by ‘Other Request for information’ and what are the similarities/differences between this and
requesting a SUE notification/ticket?
• “Other request for information” is an Engineering notification.
• Engineering notifications (also known as “tickets”) are for design projects that do not meet SUE-
required project criteria; it is an option to obtain location information on underground utilities from
owners/operators.
• From the utility owner/operator standpoint, the response is the same: both require utility owners to
provide records, marks on the ground or other available information as to the approximate location of
utilities within ten business days. CO 811 will issue a notification to all owners/operators with
underground infrastructure in the area.
• The Safety Commission interprets the intent of the language in the Law to be a “floor” not a ceiling –
meaning at a minimum certain projects (those that meet the criteria as a SUE-required project) are
using SUE. Where other projects may involve interaction with underground utilities, and performing
SUE works as a damage prevention tool or allows the project to be designed around existing
infrastructure, it is a recommendation for engineers to request information and owners/operators to
provide this information.
• Under the Law, the owner/operator has three options: records, marks on the ground, or provide other
available information, and all three of these options are valid forms of positive response. In recognition
of the intent for the information request, most engineers prefer receiving records if available and the
owner/operator is willing to provide them.
• The goal of damage prevention is shared by all parties involved in the SUE process. When information
about utility locations are shared by utility owners/operators, the engineers are able to avoid and design
around utilities.