Test Plan - WebShop
Test Plan - WebShop
Scope/Out of Scope
Assumptions
Schedules:
Deliverables
Environments
Tools
Exit Criteria
Overview:
As part of the project, ‘Webshop’ is the web application with the URL
https://demowebshop.tricentis.com/
This document serves as high level test planning document with details on the scope of the
project, test schedule and resource requirements, test deliverables, risk and management.
Scope:
The scope of the project includes testing the following features of
‘https://demowebshop.tricentis.com/
’ web application.
Inclusions:
• Register
• Forgot Password
• Search
• Category Pages
• Menu Options
• Product Compare
• Add to Cart
• Wish List
• Shopping Cart
• Home Page
• Checkout Page
• My Account Page
• Contact Us Page
• Footer Options
Exclusions(Out of Scope):
• Test Automation
Assumptions:
•Production like data required and be available in the system prior to start of Functional Testing
•During Functional testing, testing team will use preloaded data which is available on the system
at the time of execution.
Schedules:
Following is the test schedule planned for the project –
Deliverables :
Target
Deliverables Description Completion Date
Tools:
The following are the list of Tools we will be using in this Project
Defect Management:
•Any deviation from expected behaviour by the application will be noted. If it can’t be reported
as a defect, it’d be reported as an observation/issue or posed as a question.
• Every day, at the end of the test execution, defects encountered will be sent along with the
observations.
Note:
• Test scenarios and Test cases will be documented in an excel document and will be updated
on JIRA tool.
Risk and Risk Management:
The following are the list of risks possible and the ways to mitigate them:
Exit Criteria:
100% Test Scripts executed (OR as decided with customer)
All remaining defects are either cancelled or low severity or documented as Change Requests
for a future release