L2 Schedule

The document outlines a project schedule with various tasks, their durations, start and finish dates, and completion percentages. Key tasks include design, procurement, construction, and electrical work, with specific milestones and approvals noted. Overall, the project spans from June 2024 to November 2025, with varying levels of planning and completion across tasks.

Uploaded by

vasu_vema
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views4 pages

L2 Schedule

The document outlines a project schedule with various tasks, their durations, start and finish dates, and completion percentages. Key tasks include design, procurement, construction, and electrical work, with specific milestones and approvals noted. Overall, the project spans from June 2024 to November 2025, with varying levels of planning and completion across tasks.

Uploaded by

vasu_vema
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Name Duration Baseline Start Baseline Finish Start Finish % Planning % Complete Half 2, 2024 Half 1, 2025

% Planning % Complete Half 2, 2024 Half 1, 2025 Half 2, 2025


J J A S O N D J F M A M J J A S O N
1 HYD 20 T3 & T4 448.7 days Sat 01-06-24 Sat 01-11-25 Sat 01-06-24 Sat 01-11-25 57% 33%
2 Project Start 0 days Sat 01-06-24 Sat 01-06-24 Sat 01-06-24 Sat 01-06-24 100% 100% 01-06
3 Milestone 342.6 days Thu 03-10-24 Sat 01-11-25 Thu 03-10-24 Sat 01-11-25 99% 99%
4 Statutory approvals 0 days Sat 31-05-25 Sat 31-05-25 Tue 01-07-25 Tue 01-07-25 0% 0% 01-07
5 Design IFC 0 days Thu 03-10-24 Thu 03-10-24 Thu 03-10-24 Thu 03-10-24 100% 100% 03-10
6 Customer IFC 0 days Thu 30-01-25 Thu 30-01-25 Fri 20-12-24 Fri 20-12-24 100% 100% 20-12
7 Design GFC 0 days Fri 13-12-24 Fri 13-12-24 Thu 27-02-25 Thu 27-02-25 100% 0% 27-02
8 Vendors Mobilization 8.3 days Mon 04-11-24 Tue 12-11-24 Mon 04-11-24 Tue 12-11-24 100% 100%
9 Customer Vendor Onboarding 0 days Tue 18-02-25 Tue 18-02-25 Thu 24-04-25 Thu 24-04-25 100% 0% 24-04
10 Long lead items delivery 0 days Fri 27-12-24 Fri 27-12-24 Tue 31-12-24 Tue 31-12-24 100% 100% 31-12
11 Tranche 3 & 4- L3 Finish 0 days Sat 20-09-25 Sat 20-09-25 Fri 19-09-25 Fri 19-09-25 0% 0% 19-09
12 Tranche 3 & 4 Early access 0 days Wed 01-10-25 Wed 01-10-25 Wed 01-10-25 Wed 01-10-25 0% 0% 01-10
13 Tranche 3 & 4- L4 Finish 0 days Wed 15-10-25 Wed 15-10-25 Wed 15-10-25 Wed 15-10-25 0% 0% 15-10
14 Tranche 3 & 4- IST 0 days Mon 20-10-25 Mon 20-10-25 Mon 20-10-25 Mon 20-10-25 0% 0% 20-10
15 Tranche 3 & 4 RFS 0 days Sat 01-11-25 Sat 01-11-25 Sat 01-11-25 Sat 01-11-25 0% 0% 01-11
16 Statutory Approvals 341.8 days Sat 01-06-24 Sat 31-05-25 Sat 01-06-24 Tue 01-07-25 0% 0%
23 Design 233.55 days Sat 01-06-24 Thu 30-01-25 Sat 01-06-24 Thu 27-02-25 100% 99%
24 30% Drawings 30.4 days Sat 01-06-24 Fri 05-07-24 Sat 01-06-24 Fri 05-07-24 100% 100%
29 60% Drawings 30.4 days Thu 27-06-24 Thu 01-08-24 Thu 27-06-24 Thu 01-08-24 100% 100%
34 90% Drawings 30.4 days Wed 24-07-24 Thu 29-08-24 Wed 24-07-24 Thu 29-08-24 100% 100%
39 IFC Drawings 105.9 days Wed 21-08-24 Thu 30-01-25 Wed 21-08-24 Fri 20-12-24 100% 100%
46 Shop Drawing Preparation 77.55 days Mon 04-11-24 Fri 13-12-24 Fri 29-11-24 Thu 27-02-25 100% 91%
51 Procurement 233.05 days Wed 24-07-24 Tue 18-02-25 Wed 24-07-24 Thu 24-04-25 100% 83%
52 Vendor Onboarding 173.45 days Thu 03-10-24 Tue 18-02-25 Thu 03-10-24 Thu 24-04-25 100% 76%
60 LLE Material 91.7 days Wed 24-07-24 Fri 08-11-24 Wed 24-07-24 Fri 08-11-24 100% 100%
61 Ordering 91.7 days Wed 24-07-24 Fri 08-11-24 Wed 24-07-24 Fri 08-11-24 100% 100%
77 Delivery 216.07 days Wed 24-07-24 Fri 17-01-25 Wed 24-07-24 Wed 02-04-25 100% 84%
78 FIM material 216.07 days Wed 24-07-24 Fri 17-01-25 Wed 24-07-24 Wed 02-04-25 100% 84%
94 Construction 303.2 days Wed 24-07-24 Wed 09-07-25 Wed 24-07-24 Wed 09-07-25 53% 22%
95 Data Halls 234.9 days Mon 13-01-25 Wed 09-07-25 Sat 12-10-24 Wed 09-07-25 31% 11%
96 Data Hall 5 & Mechanical Gallery 171.47 days Mon 13-01-25 Mon 19-05-25 Fri 01-11-24 Mon 19-05-25 37% 15%
97 Mechanical Gallery 150.21 days Mon 13-01-25 Tue 01-04-25 Fri 01-11-24 Fri 25-04-25 70% 14%
141 Data Hall 162.87 days Thu 23-01-25 Mon 19-05-25 Mon 11-11-24 Mon 19-05-25 9% 16%
188 Data Hall 6 & Mechanical Gallery 196.77 days Mon 13-01-25 Fri 16-05-25 Sat 12-10-24 Wed 28-05-25 33% 22%
189 Mechanical Gallery 146.01 days Mon 13-01-25 Mon 31-03-25 Fri 01-11-24 Mon 21-04-25 65% 14%
233 Data Hall 196.77 days Sat 25-01-25 Fri 16-05-25 Sat 12-10-24 Wed 28-05-25 8% 26%
280 Data Hall 7 & Mechanical Gallery 233.8 days Thu 23-01-25 Wed 09-07-25 Tue 15-10-24 Wed 09-07-25 30% 5%
281 Mechanical Gallery 160.62 days Thu 23-01-25 Mon 07-04-25 Fri 01-11-24 Wed 07-05-25 63% 7%
325 Data Hall 233.8 days Mon 17-02-25 Wed 09-07-25 Tue 15-10-24 Wed 09-07-25 2% 4%
372 Data Hall 8 & Mechanical Gallery 224.3 days Sat 25-01-25 Sat 05-07-25 Wed 16-10-24 Tue 01-07-25 26% 4%
464 Electrical Rooms 193.7 days Thu 03-10-24 Tue 15-04-25 Thu 03-10-24 Thu 15-05-25 83% 36%
465 Electrical Room BA SKID Room 173.3 days Thu 03-10-24 Thu 06-03-25 Thu 03-10-24 Wed 23-04-25 94% 43%
466 Electrical Room 173.3 days Thu 03-10-24 Thu 06-03-25 Thu 03-10-24 Wed 23-04-25 94% 43%
467 First Fix 137.45 days Thu 03-10-24 Sat 25-01-25 Thu 03-10-24 Mon 10-03-25 100% 63%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 22-02-25
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Duration Baseline Start Baseline Finish Start Finish % Planning % Complete Half 2, 2024 Half 1, 2025 Half 2, 2025
J J A S O N D J F M A M J J A S O N
491 Second Fix 80.1 days Sat 04-01-25 Thu 20-02-25 Mon 06-01-25 Tue 08-04-25 100% 25%
511 Finishing 161.3 days Sat 18-01-25 Thu 06-03-25 Thu 17-10-24 Wed 23-04-25 34% 13%
518 Electrical Room BB SKID Room 167.9 days Wed 09-10-24 Wed 12-03-25 Wed 09-10-24 Wed 23-04-25 91% 44%
519 Electrical Room 167.9 days Wed 09-10-24 Wed 12-03-25 Wed 09-10-24 Wed 23-04-25 91% 44%
520 First Fix 133.2 days Wed 09-10-24 Sat 01-02-25 Wed 09-10-24 Tue 11-03-25 100% 64%
544 Second Fix 77 days Mon 13-01-25 Tue 25-02-25 Tue 07-01-25 Fri 04-04-25 96% 25%
564 Finishing 161.3 days Fri 24-01-25 Wed 12-03-25 Thu 17-10-24 Wed 23-04-25 26% 13%
571 Electrical Room BC SKID Room 168.9 days Fri 11-10-24 Fri 21-03-25 Fri 11-10-24 Sat 26-04-25 87% 42%
572 Electrical Room 168.9 days Fri 11-10-24 Fri 21-03-25 Fri 11-10-24 Sat 26-04-25 87% 42%
573 First Fix 133.9 days Fri 11-10-24 Mon 10-02-25 Fri 11-10-24 Sat 15-03-25 100% 61%
597 Second Fix 83.1 days Wed 22-01-25 Mon 10-03-25 Wed 08-01-25 Tue 15-04-25 82% 23%
617 Finishing 163.4 days Fri 18-10-24 Fri 21-03-25 Fri 18-10-24 Sat 26-04-25 30% 15%
624 Electrical Room BZ SKID Room 177.3 days Sat 05-10-24 Tue 25-03-25 Sat 05-10-24 Wed 30-04-25 85% 42%
625 Electrical Room 177.3 days Sat 05-10-24 Tue 25-03-25 Sat 05-10-24 Wed 30-04-25 85% 42%
626 First Fix 139.3 days Sat 05-10-24 Mon 10-02-25 Sat 05-10-24 Sat 15-03-25 100% 62%
650 Second Fix 84.2 days Wed 22-01-25 Mon 10-03-25 Tue 07-01-25 Tue 15-04-25 82% 23%
670 Finishing 166.4 days Sat 01-02-25 Tue 25-03-25 Fri 18-10-24 Wed 30-04-25 24% 12%
677 Electrical Room BD SKID Room 181.9 days Mon 07-10-24 Wed 02-04-25 Mon 07-10-24 Tue 06-05-25 78% 27%
678 Electrical Room 181.9 days Mon 07-10-24 Wed 02-04-25 Mon 07-10-24 Tue 06-05-25 78% 27%
679 First Fix 144.9 days Mon 07-10-24 Tue 18-02-25 Mon 07-10-24 Sat 22-03-25 100% 34%
703 Second Fix 86.7 days Thu 30-01-25 Sat 15-03-25 Wed 08-01-25 Sat 19-04-25 64% 24%
723 Finishing 170.9 days Sat 19-10-24 Wed 02-04-25 Sat 19-10-24 Tue 06-05-25 25% 13%
730 Electrical Room BE SKID Room 172 days Fri 18-10-24 Wed 02-04-25 Fri 18-10-24 Tue 06-05-25 78% 29%
731 Electrical Room 172 days Fri 18-10-24 Wed 02-04-25 Fri 18-10-24 Tue 06-05-25 78% 29%
732 First Fix 135 days Fri 18-10-24 Tue 18-02-25 Fri 18-10-24 Sat 22-03-25 100% 38%
756 Second Fix 87.8 days Thu 30-01-25 Sat 15-03-25 Tue 07-01-25 Sat 19-04-25 67% 24%
776 Finishing 170.9 days Tue 11-02-25 Wed 02-04-25 Sat 19-10-24 Tue 06-05-25 25% 13%
783 Electrical Room BF SKID Room 178.5 days Mon 21-10-24 Tue 15-04-25 Mon 21-10-24 Thu 15-05-25 68% 25%
784 Electrical Room 178.5 days Mon 21-10-24 Tue 15-04-25 Mon 21-10-24 Thu 15-05-25 68% 25%
785 First Fix 137.5 days Mon 21-10-24 Tue 25-02-25 Mon 21-10-24 Thu 27-03-25 97% 34%
809 Second Fix 94.4 days Fri 07-02-25 Tue 25-03-25 Tue 07-01-25 Mon 28-04-25 45% 22%
829 Finishing 176.3 days Tue 18-02-25 Tue 15-04-25 Wed 23-10-24 Thu 15-05-25 16% 10%
836 Electrical Rooms (Mezzanine Floor) 153.9 days Thu 02-01-25 Thu 10-04-25 Mon 28-10-24 Fri 25-04-25 54% 21%
837 Electrical Room BA Mezzanine & 145.67 days Thu 02-01-25 Mon Mon Wed 82% 30%
Battery Room 10-03-25 28-10-24 16-04-25
838 Electrical Room 145.67 days Thu 02-01-25 Mon 10-03-25 Mon 28-10-24 Wed 16-04-25 83% 30%
839 First Fix 120.41 days Thu 02-01-25 Thu 20-02-25 Mon 11-11-24 Mon 31-03-25 100% 45%
866 Second Fix 75.4 days Tue 21-01-25 Mon 03-03-25 Tue 07-01-25 Thu 03-04-25 70% 10%
884 Finishing 145.67 days Wed 19-02-25 Mon 10-03-25 Mon 28-10-24 Wed 16-04-25 15% 9%
891 Battery Room 104.05 days Thu 02-01-25 Fri 07-03-25 Mon 02-12-24 Wed 02-04-25 82% 31%
892 First Fix 91.8 days Thu 02-01-25 Thu 20-02-25 Mon 02-12-24 Tue 18-03-25 100% 67%
905 Second Fix 67.55 days Fri 17-01-25 Mon 03-03-25 Thu 09-01-25 Thu 27-03-25 74% 11%
918 Finishing 67.25 days Sat 25-01-25 Fri 07-03-25 Wed 15-01-25 Wed 02-04-25 64% 2%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 22-02-25
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Name Duration Baseline Start Baseline Finish Start Finish % Planning % Complete Half 2, 2024 Half 1, 2025 Half 2, 2025
J J A S O N D J F M A M J J A S O N
925 Electrical Room BB Mezzanine & 145.67 days Fri 17-01-25 Fri 21-03-25
Mon Wed 71% 22%
Battery Room 28-10-24 16-04-25
926 Electrical Room 145.67 days Fri 17-01-25 Sat 15-03-25 Mon 28-10-24 Wed 16-04-25 74% 20%
927 First Fix 120.61 days Fri 17-01-25 Fri 28-02-25 Mon 11-11-24 Mon 31-03-25 95% 33%
954 Second Fix 64.6 days Mon 03-02-25 Wed 12-03-25 Tue 21-01-25 Thu 03-04-25 54% 5%
972 Finishing 145.67 days Wed 19-02-25 Sat 15-03-25 Mon 28-10-24 Wed 16-04-25 15% 9%
979 Battery Room 104.05 days Fri 17-01-25 Fri 21-03-25 Mon 02-12-24 Wed 02-04-25 62% 28%
980 First Fix 91.8 days Fri 17-01-25 Thu 06-03-25 Mon 02-12-24 Tue 18-03-25 84% 64%
993 Second Fix 58.95 days Thu 30-01-25 Mon 17-03-25 Tue 21-01-25 Thu 27-03-25 53% 9%
1006 Finishing 28.25 days Fri 07-02-25 Fri 21-03-25 Fri 28-02-25 Wed 02-04-25 36% 0%
1013 Electrical Room BC Mezzanine & 145.67 days Tue 21-01-25 Tue 25-03-25 Mon Wed 68% 24%
Battery Room 28-10-24 16-04-25
1014 Electrical Room 145.67 days Tue 21-01-25 Wed 19-03-25 Mon 28-10-24 Wed 16-04-25 71% 22%
1015 First Fix 120.41 days Tue 21-01-25 Tue 04-03-25 Mon 11-11-24 Mon 31-03-25 92% 35%
1042 Second Fix 74.3 days Thu 06-02-25 Sat 15-03-25 Wed 08-01-25 Thu 03-04-25 52% 4%
1060 Finishing 145.67 days Thu 20-02-25 Wed 19-03-25 Mon 28-10-24 Wed 16-04-25 9% 9%
1067 Battery Room 110.55 days Tue 21-01-25 Tue 25-03-25 Mon 02-12-24 Wed 09-04-25 56% 31%
1068 First Fix 98.3 days Tue 21-01-25 Mon 10-03-25 Mon 02-12-24 Tue 25-03-25 83% 61%
1081 Second Fix 74.05 days Mon 03-02-25 Thu 20-03-25 Thu 09-01-25 Fri 04-04-25 43% 14%
1094 Finishing 73.75 days Tue 11-02-25 Tue 25-03-25 Wed 15-01-25 Wed 09-04-25 36% 4%
1101 Electrical Room BZ Mezzanine & 144.57 days Fri 24-01-25 Thu 27-03-25 Tue 29-10-24 Wed 59% 21%
Battery Room 16-04-25
1102 Electrical Room 144.57 days Fri 24-01-25 Sat 22-03-25 Tue 29-10-24 Wed 16-04-25 62% 18%
1103 First Fix 120.41 days Fri 24-01-25 Fri 07-03-25 Mon 11-11-24 Mon 31-03-25 85% 27%
1130 Second Fix 73.8 days Mon 10-02-25 Wed 19-03-25 Mon 13-01-25 Tue 08-04-25 38% 4%
1148 Finishing 144.57 days Mon 24-02-25 Sat 22-03-25 Tue 29-10-24 Wed 16-04-25 0% 9%
1155 Battery Room 111.05 days Fri 24-01-25 Thu 27-03-25 Mon 02-12-24 Thu 10-04-25 50% 30%
1156 First Fix 98.8 days Fri 24-01-25 Wed 12-03-25 Mon 02-12-24 Wed 26-03-25 83% 59%
1169 Second Fix 70.25 days Thu 06-02-25 Mon 24-03-25 Thu 16-01-25 Fri 04-04-25 30% 14%
1182 Finishing 75.35 days Thu 13-02-25 Thu 27-03-25 Mon 13-01-25 Thu 10-04-25 36% 4%
1189 Electrical Room BD Mezzanine & 145.8 days Tue 28-01-25 Tue 01-04-25 Tue 29-10-24 Thu 17-04-25 45% 19%
Battery Room
1190 Electrical Room 145.8 days Tue 28-01-25 Wed 26-03-25 Tue 29-10-24 Thu 17-04-25 46% 14%
1191 First Fix 122 days Tue 28-01-25 Tue 11-03-25 Mon 11-11-24 Tue 01-04-25 64% 22%
1218 Second Fix 82.2 days Wed 12-02-25 Sat 22-03-25 Wed 08-01-25 Sat 12-04-25 26% 4%
1236 Finishing 145.8 days Thu 27-02-25 Wed 26-03-25 Tue 29-10-24 Thu 17-04-25 0% 9%
1243 Battery Room 111.05 days Tue 28-01-25 Tue 01-04-25 Mon 02-12-24 Thu 10-04-25 43% 30%
1244 First Fix 98.8 days Tue 28-01-25 Mon 17-03-25 Mon 02-12-24 Wed 26-03-25 76% 59%
1257 Second Fix 74.55 days Mon 10-02-25 Thu 27-03-25 Thu 09-01-25 Fri 04-04-25 21% 14%
1270 Finishing 74.25 days Mon 17-02-25 Tue 01-04-25 Wed 15-01-25 Thu 10-04-25 36% 4%
1277 Electrical Room BE Mezzanine & 150.4 days Thu 30-01-25 Fri 04-04-25 Tue 29-10-24 Wed 33% 14%
Battery Room 23-04-25
1278 Electrical Room 150.4 days Thu 30-01-25 Mon 31-03-25 Tue 29-10-24 Wed 23-04-25 33% 9%
1279 First Fix 133.1 days Thu 30-01-25 Sat 15-03-25 Mon 04-11-24 Mon 07-04-25 48% 10%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 22-02-25
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 3
ID Task Name Duration Baseline Start Baseline Finish Start Finish % Planning % Complete Half 2, 2024 Half 1, 2025 Half 2, 2025
J J A S O N D J F M A M J J A S O N
1306 Second Fix 77.1 days Mon 17-02-25 Thu 27-03-25 Tue 21-01-25 Mon 21-04-25 14% 5%
1324 Finishing 150.4 days Tue 04-03-25 Mon 31-03-25 Tue 29-10-24 Wed 23-04-25 0% 9%
1331 Battery Room 111.85 days Thu 30-01-25 Fri 04-04-25 Mon 02-12-24 Fri 11-04-25 35% 28%
1332 First Fix 99.6 days Thu 30-01-25 Thu 20-03-25 Mon 02-12-24 Wed 26-03-25 63% 54%
1345 Second Fix 71.05 days Wed 12-02-25 Mon 31-03-25 Wed 15-01-25 Mon 07-04-25 21% 14%
1358 Finishing 75.05 days Thu 20-02-25 Fri 04-04-25 Wed 15-01-25 Fri 11-04-25 13% 4%
1365 Electrical Room BF Mezzanine & 152.8 days Tue 04-02-25 Thu 10-04-25 Tue 29-10-24 Fri 25-04-25 21% 13%
Battery Room
1366 Electrical Room 152.8 days Tue 04-02-25 Fri 04-04-25 Tue 29-10-24 Fri 25-04-25 19% 8%
1367 First Fix 135.5 days Tue 04-02-25 Thu 20-03-25 Mon 04-11-24 Wed 09-04-25 33% 11%
1394 Second Fix 83.8 days Fri 21-02-25 Tue 01-04-25 Wed 15-01-25 Wed 23-04-25 1% 4%
1412 Finishing 152.8 days Sat 08-03-25 Fri 04-04-25 Tue 29-10-24 Fri 25-04-25 0% 9%
1419 Battery Room 111.85 days Tue 04-02-25 Thu 10-04-25 Mon 02-12-24 Fri 11-04-25 26% 28%
1420 First Fix 99.6 days Tue 04-02-25 Tue 25-03-25 Mon 02-12-24 Wed 26-03-25 52% 54%
1433 Second Fix 71.05 days Mon 17-02-25 Fri 04-04-25 Thu 16-01-25 Mon 07-04-25 15% 14%
1446 Finishing 75.05 days Tue 25-02-25 Thu 10-04-25 Wed 15-01-25 Fri 11-04-25 0% 4%
1453 Diesel Generators and support systems 249.24 days Wed 24-07-24 Wed 07-05-25 Wed 24-07-24 Mon 12-05-25 71% 45%
1454 First Fix 230.24 days Wed 24-07-24 Mon 24-02-25 Wed 24-07-24 Mon 21-04-25 99% 61%
1488 Second Fix 81.4 days Mon 27-01-25 Wed 07-05-25 Mon 06-01-25 Wed 09-04-25 26% 1%
1504 Finishing 69.44 days Fri 11-04-25 Wed 07-05-25 Wed 19-02-25 Mon 12-05-25 0% 14%
1509 Mist System 55 days Sat 15-03-25 Mon 19-05-25 Tue 18-03-25 Wed 21-05-25 0% 0%
1529 Terrace Works 204.1 days Thu 03-10-24 Fri 13-06-25 Thu 03-10-24 Tue 27-05-25 59% 23%
1530 First Fix 162.61 days Thu 03-10-24 Fri 21-02-25 Thu 03-10-24 Thu 10-04-25 99% 41%
1553 Second Fix 105.6 days Fri 14-02-25 Fri 13-06-25 Mon 27-01-25 Tue 27-05-25 4% 0%
1576 External Works 125.4 days Thu 08-05-25 Wed 11-06-25 Mon 28-10-24 Fri 21-03-25 0% 45%
1577 Elec 125.4 days Thu 08-05-25 Wed 11-06-25 Mon 28-10-24 Fri 21-03-25 0% 45%
1585 Commissioning 448.7 days Sat 01-06-24 Sat 01-11-25 Sat 01-06-24 Sat 01-11-25 22% 22%
1586 Cx Script 249.57 days Sat 01-06-24 Thu 09-01-25 Sat 01-06-24 Tue 18-03-25 100% 26%
1605 L1 Commissioning FWT - First of Kind72.7 days Wed 24-07-24 Fri 18-10-24 Wed 24-07-24 Fri 18-10-24 100% 100%
1616 FAT for Long Lead Equipments 78.53 days Wed 24-07-24 Thu 24-10-24 Wed 24-07-24 Thu 24-10-24 100% 100%
1627 Tranche-3 & 4 Cx 266.8 days Thu 03-04-25 Sat 01-11-25 Mon 30-12-24 Sat 01-11-25 0% 4%
1628 Red Tag 187.8 days Thu 03-04-25 Fri 01-08-25 Mon 30-12-24 Fri 01-08-25 0% 18%
1636 L2 Testing and Yellow Tag ( Issue 114.75 days Thu 10-04-25 Wed Fri 11-04-25 Wed 0% 0%
Closure) 20-08-25 20-08-25
1648 Level 3 Cx- Energisation and burn test
89.7 days Thu 15-05-25 Sat 20-09-25 Tue 10-06-25 Fri 19-09-25 0% 0%
1674 Level 4 Cx 22 days Sat 20-09-25 Wed 15-10-25 Sat 20-09-25 Wed 15-10-25 0% 0%
1677 Level 5 Cx and RFS 15 days Wed 15-10-25 Sat 01-11-25 Wed 15-10-25 Sat 01-11-25 0% 0%
1684 Technical Closeout 84 days Sat 21-06-25 Sat 01-11-25 Fri 25-07-25 Sat 01-11-25 0% 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 22-02-25
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 4