Module Four
Module Four
1
Risk Management Process
2
Risk Management Process Management Elements
SCOPE
• program to achieve Organisational
Objectives
• Governance, policy and processes
CONTEXT
• Organisational operating environment
• Organizational operations and
management
• Impact on stakeholders Scope, Context, Criteria
CRITERIA
• Determination of risk acceptance and
tolerance
Risk Assessment
Risk Treatment
Recording & Reporting
• Records Policy
• Records management system Recording & Reporting
• Access to documentation
• Reporting Channels
Risk Management Assessment and Treatment Process Elements
RISK TREATMENT
Specific selection criteria
• Physical Controls Risk Treatment
• Personal Controls
• Information Management Controls
• Work History and performance Recording and Reporting
• Cyber Controls
• Review and Improvement Processes
Identify Sources of Risk
Personnel/human behavior.
Management activities and controls.
Economic circumstances.
Natural events.
Political circumstances.
Technology/technical issues.
Commercial and legal relationships.
The activity itself.
6
Risk Identification
A risk that is not identified at this stage will not be included in further
analysis
7
Example
8
Risk Analysis
9
Risk Evaluation
10
Risk Criteria
11
Example :Level of Risk
Magnitude of a risk or combination of risks, expressed in terms of
the combination of consequences and their likelihood
Risk levels with relation to the project objectives are evaluated using
the risk matrices
Risk level of events that may have a positive impact on the project's
cost or time schedule is evaluated using the "Cost decrease" or
"Advance" risk matrices, respectively.
12
Example : Risk Matrices
13
Risk Assessment Matrix
14
Example :Risk Matrices
15
Example: Definition of Consequence
classes in the Risk Matrices
you should modify a appropriate for your project scale, and maybe
add some arguments to why the values are chosen as they are:
Negligible : Event will have negligible impact on the objective.
Project cost: about ±$10k, or less
Time schedule: about ±1 week, or less
Serious : Event will have a sizeable impact on the objective.
Project cost: about ±$100k
Time schedule: about ±1 month
Major : Event will have a large impact on the objective.
Project cost: about ±$1m, or more
Time schedule: about ±6 months, or more
16
The colors of the Matrix fields indicate
Risk level:
High risk
Medium risk
Low risk
17
Example: Evaluation of Risk levels
If the risk level is low, risk treatment is not required. Risk may be
accepted without further justification.
18
Risk Treatment
19
Risk Treatment
20
Monitor & Review
Monitoring
Continual checking, supervising, critically observing or determining
the status in order to identify change from the performance level
requires or expected
Can be applied to a risk management framework, risk management
process, risk or control
Reviewing
Activity undertaken to determine suitability, adequacy and
effectiveness of subject matter to achieve established objectives
Can be applied to a risk management framework, risk management
process, risk or control
21