Window Delay Analysis - Final
Window Delay Analysis - Final
01 JUN 2023
31 MAY 2025
31 MAY 2025
31 MAY 2025
Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25
25 AUG 2024
Client Sent an Approved CMP
with Land Use Via Email
18 JUN 2025
17 OCT 2024
Contractor submit Re- Design Report
for Phase 2 Under EI No.07
26 AUG 2025
04 NOV 2024
Client Sent an Approval (Re- Design Report for
Phase 2 Under EI No. 07)
25 NOV 2024
Approved Shop Drawings- MV Network as per
New Design and New CMP
03 DEC 2024
Approved Shop Drawings- LV Network as per
New Design and New CMP
07 DEC 2024
Approved Shop Drawings- Storm Water
Network Plan & Profile CMP EI- 07