Document
Document
Ans-1 - EST (Earliest Start Time):The earliest time an activity can start
without delay. It is determined by the maximum of the earliest finish times of
its immediate predecessors.
- EFT (Earliest Finish Time): The earliest time an activity can finish. It is
calculated as:
\[
\]
Ans - Total Float: The amount of time an activity can be delayed without
delaying the project completion time.
- Most Likely Time (M): The best estimate of the time required to complete
an activity, assuming everything proceeds as normal.
Ans - The Central Limit Theorem states that the distribution of the sum (or
average) of a large number of independent, identically distributed random
variables approaches a normal distribution, regardless of the original
distribution of the variables. This theorem is fundamental in statistics
because it justifies the assumption of normality in many practical situations.
Q5. Explain about Earliest expected Event occurrence time and Latest
allowable Event occurrence time.
Ans - Earliest Expected Event Occurrence Time (TE): The earliest time an
event can occur, considering the completion of preceding activities.
\[
\]
- Latest Allowable Event Occurrence Time (TL):The latest time an event can
occur without delaying the project. It is calculated by backward pass, starting
from the project's end event.
\[
\]
Q6. Explain any two of the following phases of project management in detail.
Ans - Planning: This phase involves defining the project scope, objectives,
and steps to achieve the goals. It includes resource allocation, budget
planning, and risk management.
Q8. Explain about Milestone charts in detail with the help of a neat sketch
and also write its advantages and limitations.
- Advantages:
- Limitations:
Let's address the questions from the second image one by one:
- **EST (Earliest Start Time):** The earliest time an activity can start
without delay. It is determined by the maximum of the earliest finish times of
its immediate predecessors.
- **EFT (Earliest Finish Time):** The earliest time an activity can finish. It is
calculated as:
\[
\]
2. **Enlist different types of float.**
- **Most Likely Time (M):** The best estimate of the time required to
complete an activity, assuming everything proceeds as normal.
- The Central Limit Theorem states that the distribution of the sum (or
average) of a large number of independent, identically distributed random
variables approaches a normal distribution, regardless of the original
distribution of the variables. This theorem is fundamental in statistics
because it justifies the assumption of normality in many practical situations.
\[
\]
- **Latest Allowable Event Occurrence Time (TL):** The latest time an
event can occur without delaying the project. It is calculated by backward
pass, starting from the project's end event.
\[
\]
8. **Explain about Milestone charts in detail with the help of a neat sketch
and also write its advantages and limitations.**
- **Limitations:**
Q9 Let's determine the critical path, project completion time, and all the
floats for each activity from the given table.
- A: 7
- B: 5
- C: 10 (Immediate Predecessor: A)
- D: 5 (Immediate Predecessor: A)
- E: 8 (Immediate Predecessor: B)
- F: 6 (Immediate Predecessor: B)
- G: 5 (Immediate Predecessor: C)
- H: 4 (Immediate Predecessor: C)
- I: 10 (Immediate Predecessor: D)
- J: 8 (Immediate Predecessor: F)
- K: 8 (Immediate Predecessor: F)
- L: 9 (Immediate Predecessors: G, H, I, J)
Step 1: Calculate Earliest Start Time (EST) and Earliest Finish Time (EFT)
1. Activity A:
- EST = 0
2. Activity B:
- EST = 0
3. Activity C:
- EST = EFT of A = 7
4. Activity D:
- EST = EFT of A = 7
5. Activity E:
- EST = EFT of B = 5
6 Activity F:
- EST = EFT of B = 5
7. Activity G:
- EST = EFT of C = 17
- EFT = EST + Duration = 17 + 5 = 22
8. Activity H:
- EST = EFT of C = 17
9. Activity I:
- EST = EFT of D = 12
10. Activity J:
- EST = EFT of F = 11
11. Activity K:
- EST = EFT of F = 11
12. Activity L:
Step 2: Calculate Latest Start Time (LST) and Latest Finish Time (LFT)
(Backward Pass)
1. **Activity L:**
- LFT = LST of L = 22
3. **Activity H:**
- LFT = LST of L = 22
4. **Activity I:**
- LFT = LST of L = 22
5. **Activity J:**
- LFT = LST of L = 22
6. **Activity K:**
- LFT = Min(LST of J) = 14
7. **Activity C:**
8. **Activity D:**
- LFT = LST of I = 12
- LST = LFT - Duration = 12 - 5 = 7
9. **Activity E:**
The critical path is the longest path through the network, which determines
the project duration.
- **Path 1: A → C → G → L**
- Duration: 7 + 10 + 5 + 9 = 31
- **Path 2: A → D → I → L**
- Duration: 7 + 5 + 10 + 9 = 31
Both paths have a total duration of 31, so they are the critical paths.
- A, C, D, G, I, L
- B, E, F, H, J, K
For these calculations, the values for some activities may not be meaningful
because they are not on the critical path.
Summary
2. **Introduction**:
3. **Project Description**:
4. **Market Analysis**:
- Competitive analysis.
5. **Technical Feasibility**:
6. **Financial Analysis**:
7. **Implementation Plan**:
11. **Conclusion**: