PROCEDURE
Applicants are not required to visit any of the MPCB offices at any stage of the application process. The online system offers the functionality of
one-time mobile verification for the applicant & one-time online document verification by the Department as a part of the registration procedure
Then the application is shown as "Document Pending", 4 compulsory documents need to upload online then the status changes to "Payment
Pending". Industry will have to pay the fees online as per fees structure http://www.mpcb.gov.in/consent-under-water-and-air-act#fees. Industry
will have to update the payment details and on approval of application changes to "Payment Approved".
SRO assign the application to Field officer. Once the field officer reviews the application, he/she Push the application through the Integrated
Management information system (IMIS), the application status changes to "In Process". Field officer scrutinize the application, visit the industry (for
establishment and first operate) & put their recommendation / visit report and submit it to Sub Regional Officer.
Now depending upon the category and the Capital Investment of the industry the application is forwarded through IMIS as per delegation of power.
Refer below link: http://www.mpcb.gov.in/consent-under-water-and-air-act The concerned authority will scrutinize the application, if it is fine then
the application is granted in IMIS and then status will be changed to "Approved" on the online portal followed by uploading the signed consent
copy. Otherwise if the application is not fine, then the application is rejected in IMIS and notify the Entrepreneur by marking the application status
as "Rejected". Industry can download the consent copy from online portal.
Then the application is shown as "Document Pending", 4 compulsory documents need to upload online then the status changes to "Payment
Pending". Industry will have to pay the fees online as per fees structure http://www.mpcb.gov.in/consent-under-water-and-air-act#fees. Industry
will have to update the payment details and on approval of application changes to " Payment Approved".
SRO assign the application to Field officer. Once the field officer reviews the application, he/she Push the application through the Internal
Management information system (IMIS), the application status changes to " In Process". Field officer scrutinize the application & put their
recommendation and submit it to Sub Regional Officer.
Now depending upon the category and the Capital Investment of the industry the application is forwarded through IMIS as per delegation of power.
Refer below link: http://www.mpcb.gov.in/consent-under-water-and-air-act.
The concerned authority will scrutinize the application, if it is fine then the application is granted in IMIS and then status will be changed to "
Approved" on the online portal followed by uploading the signed consent copy. Otherwise if the application is not fine, then the application is
rejected in IMIS and notify the Entrepreneur by marking the application status as " Rejected ". Industry can download the consent copy from online
portal.
https://mpcb.gov.in/consentmgt/water-and-air-act/procedure 1/1