Boq - 2 Storey - Using Aac Block
Boq - 2 Storey - Using Aac Block
1 GENERAL REQUIREMENTS
1.1 . Mobilization / Demobilization 25,000.00
1.2 Land Survey 12,500.00
1.3 . Temporary Facilities with office 45,000.00
1.4 . Power & Light Consumption 21,000.00
1.5 . Water Consumption 14,000.00
1.6 . Site supervision, safety and security services 85,000.00
1.7 . Design and Production of Plan -
1.8 . As-Built Drawings 25,000.00
1.9 . Government Permits
1.9.1 . Building Permit
1.9.2 . Occupancy Permit
1.9.3 Board-up Fence 30,000.00
SUB-TOTAL 257,500.00
TOTAL GENERAL REQUIREMENTS COST ESTIMATE 257,500.00
3 CIVIL/STRUCTURAL WORKS
3.1 Concrete Works
1 . Column Footing 89,775.00
2 . Tie Beam 19,323.00
3 . Wall Footing 1,881.00
4 . Door/Window Opening Lintel Beam 8,748.00
5 . Column 80,370.00
6 . Grade Slab 101,703.60
7 . Second Floor Beams 47,880.00
8 . Second Floor Slab 65,466.00
9 . Roof Beam 20,341.80
10 . Stair 18,000.00
12 . Septic Vault 14,121.00
13 . Catch Basin 5,400.00
14 . Integral Waterproofing (Comfort Rooms) 7,200.00
SUB-TOTAL 480,209.40
3.2 Rebars
1 . Column Footing 24,192.96
2 . Tie Beam 25,825.63
3 . Wall Footing 1,209.45
4 . Door/Window Opening Lintel Beam 6,570.24
5 . Column 59,829.09
6 . Grade Slab 31,949.30
7 . Second Floor Beams 74,097.49
8 . Second Floor Slab 90,113.79
9 . Roof Beam 28,222.09
10 . Wall rebars -
11 . Stair 5,729.82
12 . Septic Vault 9,000.00
13 . Catch Basin 5,000.00
14 . G.I. Wire #16 32,250.00
SUB-TOTAL 393,989.85
Page 2 of 9
ITEM DESCRIPTION AMOUNT
418,427.66
3.3 Formworks and Scalfoldings
1 . Column Footing 12,096.00
2 . Tie Beam 35,485.93
3 . Wall Footing 1,584.00
4 . Door/Window Opening Lintel Beam 99,695.00
5 . Column 139,792.80
6 . Grade Slab 9,864.00
7 . Second Floor Beams 84,202.79
8 . Second Floor Slab 85,649.12
9 . Roof Beam 84,199.10
10 . Stair 5,440.00
11 . Septic Vault 3,061.50
12 . Catch Basin 6,750.00
SUB-TOTAL 567,820.24
4 ARCHITECTURAL WORKS
4.1 Doors
D1 - Solid Wood Panel Door on 50x150mm mm wood
1. 17,500.00
jamb (Painted Finish)
D2 - Double Swing Flush Door on 50x150mm wood
2. 105,000.00
jamb (Painted Finish)
D3 - Double Swing Flush Door on 50x150mm wood
3. 70,000.00
jamb (Painted Finish)
D4 - Double Swing Flush Door on 50x150mm wood
4. 35,000.00
jamb (Painted Finish)
D5 - Sliding Glass Door w/ Analok alum. Frame with
5 21,550.00
1/4" thk clear class
D6 - Sliding Glass Door w/ Analok alum. Frame with
6. 20,350.00
1/4" thk clear class
7 . Finishing Hardware
a . Lockset, Hinges, Hardwares etc. 75,000.00
SUB-TOTAL 344,400.00
Page 4 of 9
ITEM DESCRIPTION AMOUNT
Page 5 of 9
ITEM DESCRIPTION AMOUNT
4.7 Carpentry
A. . Kitchen Cabinet & Bedroom Closets
1 . 3/4 plywood
2 . 2" Black Screw
3 . Fin nail
4 . Stickwell
250,000.00
5 . Triming
6 . Hanging Rod
7 . Mirror
8 . Track/ Roller Guide 0.60 x 2.10 & concealed Hinges
SUB-TOTAL 250,000.00
Page 6 of 9
ITEM DESCRIPTION AMOUNT
4.8 Steelworks
B. . STAIR RAILINGS WITH 2.5" Ø STAINLESS HANDRAIL
1 2 x 3 Aluminum Handrail painted in wood design 8,979.60
2 . 12 mm thk tempered glass 54,476.24
3 . Consumables 15,000.00
SUB-TOTAL 78,455.84
TOTAL ARCHITECTURAL COST ESTIMATE 1,859,056.59
5 ELECTRICAL WORKS
5.1 Lighting and Power Materials
1 . PVC Pipe 40mm Ø 3,402.00
2 . PVC Pipe 25mm Ø 11,149.20
3 . PVC Pipe 20mm Ø 16,524.00
4 . Junction Box 4,950.00
5 . Utility Box 3,150.00
6 . Square Box 4 x 11/6 Metal 185.40
11 . Entrance Cup w/ connector 40mm Ø 154.13
12 . Entrance Cup w/ connector 25mm Ø 82.58
13 . Wire #3.5mm.sq. Phelp Dodge 140,332.50
14 . Wire #5.5mm.sq. Phelp Dodge 62,640.00
15 . Wire #30mm.sq. Phelp Dodge 22,435.20
16 . Coaxial Canle RG-60 2,295.00
17 . Panel Board 22 Branches Bolt-On 17,488.80
18 . G.E. Center Main 125AT 18,900.00
20 . G.E. Circuit Breaker 20AT 12,892.50
21 . G.E. Circuit Breaker 30AT 34,380.00
22 . NEMA 3R w/ 30AT Breaker G.E. 2,147.40
23 . Two-Gang Outlet Duplex (Panasonic) 50,118.75
24 . One Gang Switch 2,520.00
25 . Two Gang Switch 3,465.00
26 . Three Gang Switch 2,025.00
27 . 3-Way Switch 4,914.00
28 . Range Outlet (Assume 1 Range only) 1.80
29 . Assummed A.C.U. Outlet (Bedroom, Living and dining) 945.00
30 . Consumables, Testing & Comissioning 29,600.00
SUB-TOTAL 446,698.27
Page 7 of 9
ITEM DESCRIPTION AMOUNT
6 PLUMBING WORKS
6.1 Plumbing Fixtures
1 . Water Closet (kholer PN: 13811T-S-O) 182,500.00
2 . Vessel Lavatory (Kohler PN: K198971) 112,500.00
3 . Lavatory Faucet (kohler 74013t-4-cp) 35,500.00
4 . Shower Assembly (Kohler pn:7194t-4-cp) 123,000.00
5 . Accessories & Fittings 32,000.00
6 . Bidet (kohler PN: 77364k-cp) 20,500.00
7 . Tissue Holder 7,000.00
8 . Kitchen Sink (Franke pn: bcx 621bbrhd) 36,300.00
9 . Kitchen Faucet (Kohler pn: k-26259t-4-cp) 63,630.00
10 . Hose Bibb 1/2 x 3/4 2,400.00
10 . Water Heater (Kohler pn: 5241k-4-e2-cp) 65,200.00
SUB-TOTAL 680,530.00
6.2 Waterline
1 . Water Line rough -in as per given specification 95,000.00
SUB-TOTAL 95,000.00
6.3 Stormdrain
1 . Storm Drain rough -in as per given specification 65,000.00
SUB-TOTAL 65,000.00
6.4 Sewer line
1 . Sewer line rough-in as per given specification 85,750.00
6.4.7 Floor Drain Stainless 5,250.00
6.4.9 . Consumables 15,000.00
SUB-TOTAL 106,000.00
Page 8 of 9
ITEM DESCRIPTION AMOUNT
Submitted by:
Page 9 of 9