MSC Thesis Harmonics in Networks
MSC Thesis Harmonics in Networks
by
Dissertation
Magister Ingeneriae
in
in the
At the
University of Johannesburg
July 2005
3
Acknowledgements
• To our Creator for the privilege; without Him at my side I would not
have been able to complete this dissertation.
• To Chris van Dyk from Power System Dynamics; thanks for your help
on PSCAD Software applications.
Abstract
With the advances in technology and the increase in industrial facilities, the
harmonic content of an electrical network has always been a major concern
among power system engineers. This is especially in an industrial
environment, where the usage of power is very high as there are many large-
scale types of equipment being used. Thus, it would be useful to know the
sources, distortion level, impact on the power system and the equipment of
harmonic currents on the harmonically rich electrical network.
Table of contents
ACKNOWLEDGEMENTS ...............................................................................3
ABSTRACT .....................................................................................................4
LIST OF ABBREVIATIONS...........................................................................10
LIST OF TABLES..........................................................................................12
1 INTRODUCTION ....................................................................................13
1.1 Aim of the study........................................................................................................ 14
2 HARMONIC PROBLEMS.......................................................................23
2.1 Introduction............................................................................................................... 23
2.3.1 Transients.................................................................................................................. 26
6
3.6 Time domain simulation results to show the accuracy of the PSCAD model vs
real measurements................................................................................................... 43
3.7.2 The effect on transmission efficiency if the load is three times the original load
53
4.1.1 Introduction............................................................................................................... 55
4.3.3 Recommended planning levels for harmonic voltage on HV and EHV systems 60
4.11 New power-quality assessment criteria for supply system under unbalanced
and non-sinusoidal conditions .............................................................................. 74
5.3.1 Heating and loss effects caused by harmonic currents on underground cables
81
5.4 Transformers............................................................................................................. 86
5.4.2 Estimation method for power system harmonics effects on power transformers
91
5.4.6 Effects of harmonic currents on the Hart RAO network and motor–generator set
98
7 ANNEXURES .......................................................................................108
Annexure A: PSCAD software............................................................................................ 108
8 LIST OF REFERENCES.......................................................................112
9
List of abbreviations
AC Alternating Current
CSIR Council for Scientific and Industrial Research
DC Direct Current
EHV Extra High Voltage
SAC Satellite Application Centre
UPS Uninterruptible Power Supply
PF Power Factor
RMS Root Mean Square
IEEE Institute of Electrical and Electronic Engineering
SMPS Switch Mode Power Supply
IHD Individual Harmonic Distortion
PSCAD Power System Computer-aided Design
Hart RAO Hartbeeshoek Radio Astronomy Observatory
HDF Harmonic Distortion Factor
HV High Voltage
VSD Variable Speed Drives
IGY International Geophysical Year
USA United States of America
RF Radio Frequency
LV Low Voltage
MV Medium Voltage
11
List of figures
List of tables
1 INTRODUCTION
With the growing concern about the level of harmonic current and voltage
distortion present in electrical networks, a number of regional standards have
been introduced in countries throughout the world. These standards are
imposed on electrical items, electricity customers and electricity utilities. There
are many standards available, for example, the IEEE 519-1992 USA “IEEE
Recommended Practices and Requirements for Harmonic Control in Electrical
Power Systems” and The NRS 048 (South Africa).
The main objectives of this study are to investigate the harmonic impact on a
power system and its equipment and the power quality of harmonic currents at
the Satellite Application Centre (SAC) power network when considering future
load growth or expansion; to determine the harmonic content or harmonic
voltage distortion levels at SAC; to see whether network voltage distortion is
exceeding the standard limits; to determine the detrimental effects of the
harmonic currents on power system equipments when considering future
expansion or load growth on the SAC network; to develop a model that could
be used to simulate SAC’s power network; and to identify general concerns
when considering expansion in the network.
“The Satellite Applications Centre, as we know it today, had its origin at the
dawn of the space age in December 1957 when the CSIR agreed to install
and operate a 108 MHz “MINITRACK” interferometer satellite tracking system
in South Africa. This system was to be part of a world-wide tracking network of
similar systems, designed by the United States Naval Laboratories (NRL) to
track artificial earth satellites that were to be launched by the United States
with Project Vanguard, as their contribution to the International Geophysical
Year (IGY) in 1958” [2].
The station was handed over to the Council for Scientific and Industrial
Research (CSIR) in 1975 and was converted to a radio astronomy
observatory. In 1988 the observatory became a National Facility operated by
the Foundation for Research Development (FRD). In 1999 the FRD was
restructured as the National Research Foundation (NRF)” [3].
16
The harmonic problems for the Satellite Application Centre (SAC) are
investigated in this dissertation. The Satellite Application Centre has its own
power distribution and conversion system. Eskom’s transformer supply to
SAC and Hart RAO is 11 kV 1MVA, 50 Hz. This source is then converted to
115 V (three-phase, 208 V), 60 Hz or 220 V (three-phase, 380 V), 60 Hz,
because the generation station was built by America in 1957. In case of a
power failure, SAC has two 500kVA diesel generators that are able to supply
the full load within 17 seconds of the detected supply failure. The grid is
monitored 24 hours a day. Deviation that exceeds 15% results in the diesel
generator assuming the supply of power until stability is reached in the grid for
a minimum of 25 minutes. At this point, the power supply automatically reverts
to the grid. In the event of a major grid failure, SAC has approximately 40 000
litres of diesel fuel on site. This supply is sufficient for about 10 days.
The power to SAC and Hart RAO is 11kV, 50Hz. This is then transformed
down to 400V by 11kV to 400V delta-wye transformer. The two networks are
coupled to the same bus on the ESKOM side. But each network has its own
converter or motor-generator set. An underground cable of 16 mm2, 11kV
paper lead drain cable 3km long brings this power to the SAC main building,
where it is transformed down to 208/400V by 500kVA 11kV to 208/400V delta-
wye transformer. Hart RAO is 300m away from the generator house, with an
underground feeder. The underground cable was used in these networks to
avoid interference with sensitive equipment used at Hart RAO and SAC. SAC
is responsible for the management and maintenance of the generation station.
Two uninterruptible power supply systems (UPS) of 120kVA each and other
critical electronic equipment in the facility are the main source of harmonics on
the system. The presence of unbalanced loads creates unbalanced currents
components that cause voltage drops across the source impedance, hence
generating harmonic powers flowing backwards from the load to the network.
Due to current and possible future load growth on the electrical network at
SAC, there could be some major catastrophic impact on a power system
when the load keeps on increasing with a system with a high harmonic level.
The major concerns facing the power system engineers at SAC that need to
be assessed are as follows:
There are two reasons to undertake a system harmonic study: firstly, to study
the impact of the harmonic source and, secondly, to examine a harmonic
problem on an existing system. The harmonic contents or distortion level of
SAC need to be assessed. An approach to this is to benchmark the SAC
harmonics against utility standards for the purpose of checking the network
compliance.
SAC is a large satellite station, so the load at SAC needs to be increased (i.e.
installation of new antenna on the network). There are several things that
could have a major impact on a power system’s behaviour; thus, there is a
need to investigate the concerns before any major change can be made to the
existing loads.
non-linear load conditions? Yes, it could damage the cable because the
harmonic currents generate heat in the cable, which could shorten the life of
the cable, so the cable needs to de-rated to a certain percentage in order to
compensate for future load growth.
Secondly, the rating method for transformers and underground cables needs
to be developed. The transformer capability when supplying non-sinusoidal
loads needs to be evaluated by using a suitable rating system that could
accommodate harmonic frequencies. Non-linear load causes accelerated loss
of insulation life in transformer windings because of the heating effects of high
frequency harmonics. When significant harmonic currents are present in a
system, additional I2R losses occur in the phase or line conductors and the
neutral conductor. The primary effect of power system harmonics on
transformers is the additional heat that is generated by the losses caused by
the harmonic content of the load current. The lifespan of a transformer will be
reduced if it operates above the rated temperatures. Initially, the transformer
may be operated at the reduced loading, but in future, the loading could be
increased without considering the intended de-rating.
This means that the load condition can change rapidly. So an accurate model
is required for harmonic studies, to analyse possible future expansion and to
simulate other power quality disturbances. Because the load could increase
due to the installation of new antennas and other power electronic loads,
there is a need to check power network compliance with the standards. If the
distortion level is beyond the allowable limit, steps need to be taken to remedy
the situation so that adverse effects and added costs are avoided.
The single-phase model of the system could be attractive as it is one third the
size of the three phase model and the results could be more compact and
easier to interpret. Still, it should be employed only when it is clear that it
21
would be sufficient for the study being undertaken. For this study, a three-
phase model will be used because the system is unbalanced.
2 HARMONIC PROBLEMS
2.1 Introduction
Harmonics is a more important issue for the industry, commerce and the
home consumer now than it was a few decades ago. Modern consumers and
commercial equipment are not designed to cope with the increasing levels of
power distortion or pollution. The discussion of the harmonic will starts off with
definition of harmonics, the discussion of the theory of harmonics, causes and
other power quality disturbances.
f h = 60 Hz × h 2-1
where h is the harmonic order. In the power system, these harmonics interact
with the fundamental frequency waveform and each other to produce a
distorted waveform as shown in Figure 2-1
where,
ao: dc component
f: fundamental frequency
The fourier series can also be used to deconstruct a waveform into the
fundamental and harmonic components. This is the principle behind
performing a harmonic analysis on a power system. A waveform is recorded
and the magnitudes of the harmonics in the wave are calculated.
With the advent of power electronic devices in rectifiers, motor drives and
power supplies, the increasing levels of harmonics have become quite a
concern for power system engineers. Non-linear loads cause harmonic
distortion in a power system where the current is not proportional to the
applied voltage. A common example of this is in variable speed drives, where
the diode rectifier module within the variable speed drive (VSD) is responsible
for injecting harmonic currents into the system [6].
Research has shown that non-linear loads inject harmonic currents into the
system. Therefore, the harmonic-producing loads can be treated as current
sources. However, these harmonic currents that pass through the system
cause a voltage drop for each harmonic. This results in voltage distortion at
the load bus as well as current distortion.
The most notable effects that harmonics have on a power system are impact
on the quality of the AC voltage waveform (i.e., it will become distorted), thus
causing problems with other sensitive loads connected to the same supply [7].
2.3.1 Transients
A transient is a disturbance in an AC wave, characterised by a discontinuity of
the waveform. These may be of either polarity and are additive or subtractive
from the nominal waveform. Transients can be classified into impulsive and
oscillatory transients. Impulsive transients are instantaneous voltage
deviations, which are often impervious to the RMS voltage due to their short
duration shown in Figure 2-2. These types of transients are often due to
lightning striking a power system. Oscillatory transients have positive and
negative polarity and are distinctive by their fast rise time and oscillatory
behaviour that decays over time are shown in Figure 2-3. Oscillatory
transients are most commonly a result of the load [8].
Short duration voltage variations are a deviation from the nominal voltage
supply in the form of a ‘rise’, ‘dip’ or ‘supply void’. They can be classified in [9]
as sags, swells and interruptions. A sag is a decrease between 0.1pu and
0.9pu in the RMS voltage or current at the power frequency with durations
from 10msec (0.5 cycles) to one minute. A voltage sag can result from a large
load being placed on the power system, such as starting up a large motor as
shown in Figure 2-4 [9].
A swell is an increase between 1.1pu and 1.8pu in the RMS voltage or current
at the power frequency with durations from 10msec (0.5 cycles) to one minute
[10]. The causes of swells can be the consequence of removing a large load
from a power system as shown in Figure 2-5.
When the supply voltage or load current decreases to less than 0.1pu for a
period not exceeding one minute, the disturbance can be classified as an
interruption [11]. An interruption can be a consequence of a power system
fault, which requires some finite time for the circuit breakers to re-close
causing a supply interruption as shown in Figure 2-6.
encountered for a longer period than the short duration variations. The long
durations are classified as undervoltages, overvoltages and sustained
interruptions.
Declared voltage
R.M.S. voltage
Dip
threshold
Dip
magnitude
(% of declared)
Duration (ms)
The positive sequence set of three vectors are all equal in magnitude and 120
degrees away from each other, as shown in Figure 2-10. While the negative
sequence set of three vectors in figure 2-10 are all equal in magnitude and
120 degrees away from each other, their phase order is reversed of the
positive sequence phase order, and the zero sequence set of three vectors
are all equal in magnitude and phase.
Vneg
UB = × 100 2-3
V pos
where,
The compatibility level for unbalance on three phase networks is 2%, but if
there is a large number of single-phase or two-phase loads, the assessed
unbalance increases to 3% [11].
• Harmonic
• Inter-harmonic
• Notching
• Noise
• Flicker
32
h max
∑
2
Mh
h =2
THD
M1
2-4
I a = I a ∠0° = I a
1 1 1
I b = I a ∠240° = a 2 I a
1 1 1
2-5
I c = I a ∠120° = aI a
1 1 1
1+ a + a2 = 0 2-7
the order of the phasors is abc. This is designated the positive phase
sequence. When the order is acb, as shown in Figure 2-10, it is designated
the negative phase sequence. The negative phase sequence quantities are
represented as:
I a = I a ∠ 0° = I a
2 2 2
I b = I a ∠240° = a I a
2 2 2
2-8
I c = I a ∠120° = a I a
2 2 2 2
The last set of balanced phasors, the zero phase sequence, are found to be in
phase with each other. Zero phase sequence currents, as shown in Figure 10-
2, would be designated as:
34
Ia = Ib = Ic
0 0 0
2-9
The superscripts 1, 2 and 0 are used to represent positive, negative and zero-
sequence quantities respectively. However, 0, + and – can also be used
instead of 1, 2 and 0. Three-phase unbalanced phasors of a three-phase
system can be resolved into three balanced system of phasors.
Given the three-phase unbalanced currents Ia, Ib and Ic. we seek to find
symmetrical components of the currents such that:
Ia = Ia + Ia + Ia
0 1 2
Ib = Ib + Ib + Ib
0 1 2
2-10
Ic = Ic + Ic + Ic
0 1 2
Ia = Ia + Ia + Ia
0 1 2
I b = I a + a 2 I a + aI a
0 1 2
2-11
I c = I a + aI a + a 2 I a
0 1 2
or
1 ⎤⎡I a ⎤
0
⎡ I a ⎤ ⎡1 1
⎢ I ⎥ = ⎢1 a 2 ⎢ 1⎥
⎢ b⎥ ⎢ a ⎥⎥ ⎢ I a ⎥ 2-12
⎢⎣ I c ⎥⎦ ⎢⎣1 a a 2 ⎥⎦ ⎢⎢ I a 2 ⎥⎥
⎣ ⎦
⎡1 1 1⎤
A = ⎢⎢1 a 2 a ⎥⎥ 2-14
⎢⎣1 a a 2 ⎥⎦
35
012 −1 abc
Aa =A I 2-15
⎡1 1 1⎤
a 2 ⎥⎥
−1 1⎢
A = ⎢1 a 2-16
3
⎢⎣1 a 2 a ⎥⎦
−1 1 *
A = A 2-17
3
−1
Substituting for A in equation 2-15 then:
⎡I a 0 ⎤ ⎡1 1 1 ⎤ ⎡I a ⎤
⎢ 1⎥ 1⎢
⎢ I a ⎥ = ⎢1 a a 2 ⎥⎥ ⎢⎢ I b ⎥⎥ 2-18
⎢ 2 ⎥ 3 ⎢1 a 2 a ⎥⎦ ⎢⎣ I c ⎥⎦
⎣⎢ I a ⎦⎥ ⎣
1
I a = (I a + I b + I c )
0
3
1
I a = ( I a + aI b + a 2 I c )
1
2-19
3
1
I a = ( I a + a 2 I b + aI c )
2
It can be seen from equation 2-19 that the zero–sequence current is equal to
one-third of the sum of the phase currents. When the phase currents add up
to zero, as in a three-phase system with an ungrounded neutral, the zero-
sequence current cannot exist. But if the neutral of the system is grounded,
zero-sequence current flows between the neutral and the ground. Similarly
expressions for voltages can be derived. The unbalanced phase voltages in
terms of symmetrical component voltages are:
36
Va = Va + Va + Va
0 1 2
Vb = Va + a 2Va + aVa
0 1 2
2-20
Vc = Va + aVa + a 2Va
0 1 2
In matrix form:
= AVa
abc 012
Va 2-21
1
Va = (Va + Vb + Vc )
0
3
1
Va = (Va + aVb + a 2Vc )
1
2-22
3
1
Va = (Va + a 2Vb + aVc )
2
In matrix form:
012 −1 abc
Va =A V 2-23
Unbalanced conditions can be resolved into positive, negative and zero
sequence components. The positive sequence component is similar to the
normal balanced load. The equations in this chapter will be used to assess the
concern regarding the current and voltage unbalance factor at SAC in chapter
4.
2.4 Summary
As the use of power electronic devices increases, there will be a need to
understand the effects of harmonics and the application of all the mitigation
methods. Harmonics is not a transient phenomenon, and its presence can
easily be measured and identified. In some cases, harmonics can be
tolerated, but in other cases it should be minimised or eliminated.
3.1 Introduction
SAC requires a power system simulation tool to simulate the power network
before attempting expansion on the network so that possible future expansion
does not cause problems such as cable and transformer failure due to
overloading. Well–accepted component models will be used to simulate SAC
power network.
39
the scan, harmonic penetration and harmonic load flow. On the other hand,
the time domain analysis methods are based on the calculation of the time
evolution of the system magnitudes that are generally done through simulation
of the operation. This chapter is dedicated to the time domain analysis of the
system under study.
As discussed in chapter 1, Eskom supply power to SAC and Hart RAO But
each network has its own converter or motor-generator set.
41
Moreover, the time domain simulation allows the simultaneous existence of all
the electrical phenomena existing in the actual system operations like the
transients produced by the switching of the power electronic devices that
constitute the energy converters. In addition to a proper modelling of the
different systems components, some other consideration should be made in
order to obtain accurate results from a time domain simulation of the system
behaviour. These considerations include the proper calculation of the
initialisation process and magnitude of the different variables.
There are several items related to a study, which have to be set properly in
order to obtain results that match the reality. These items are generally:
Once the results are obtained from the computer simulation, it is also
important to compare the values against the measurements in the real field. In
the case of this study, the values and waveforms obtained will be matched
with field measurements. Although these studies were intended for different
purposes, the results and waveforms they provide allow for a comparison to
show the accuracy of the software.
43
The comparison of the wave shapes was difficult to do, because of the phase
rotation. The SAC network uses colour codes blue, red and yellow, and the
PSCAD software uses A, B and C. It was difficult to match the phases, so
waveforms with a similar shape/pattern from model and field measurements
were chosen. The measuring equipment measured single phase. The phase
rotation can be measured by determining the phase angle between the
measured waveforms. It can be positive or negative phase rotation, taking VA
as the reference phase. The positive phase rotation (abc) is when VA leads VB
by 120 º and VB leads VC by 120 º. The negative phase rotation (acb) is when
VA leads VC by 120 º and VC leads VB by 120 º.
The line currents of the model and field measurements are shown in Figure
3-4.
45
Figure 3-4: Line currents of model and field measurements taken at the
SAC generator
Figure 3-5 shows that the magnitude of the 5th harmonic current is very high
for both model and field measurements. This will be evaluated in the next
chapter with reference to the NRS 048 standard.
46
The IEEE power definitions discussed in chapter 4 were used to analyse the
real measurements to ensure some uncertainty on the measured results and
the results, were similar. The PSCAD software has a power component (P
and Q) in the master library. The real/reactive power meter measures
instantaneous real power by multiplying the instantaneous voltage and current
of each phase and then adding them together. The reactive power is
calculated on the assumption that all three phases are balanced. The software
does not specify whether the calculated power is fundamental and harmonic
power.
Figure 3-6 shows the point where current and voltage simulation results were
taken from, just before the step-up transformer. The cable impedance is
ignored because the length is short ( ± 6m).
Figure 3-7: Line currents and line-to-line voltages of simulation 1 at the SAC
generator respectively
The voltages are balanced and 120 º away from each other, but the currents
are unbalanced as shown in Figure 3-7. The line-to-line voltage is a pure
sinusoidal waveform, which means that any load connected to the same
source with the SAC that generates the harmonic current cannot be affected
by this harmonic, because the current waveform at the source depends on the
line-to-line voltage of the generator.
The Hart RAO network cannot be affected, because two networks have two
separate motor-generator set, which means that there is mechanical coupling
between the two networks and the ESKOM supply. One of the major concerns
is whether the load can be increased. This concern will be evaluated by
increasing the load on the model and calculating the transmission efficiency of
the model.
48
Figure 3-8: SAC network model simulation 2 after increasing the load
The line-to-line voltages and line currents of simulation run 2 at the SAC
generator after increasing the load are shown in Figure 3-9.
Figure 3-9: Line-to-line voltages and line currents at the Sac generator after
increasing the load respectively
It shows that when the load power increases, the distortion level of the current
waveform at the generator increases, but the voltage waveform is still purelly
sinusoidal.
49
The line-to-ground voltages and line currents of simulation 3 at the SAC load
208 V E bus supplying two UPS of 120 KVA each are shown below in Figure
3-11.
The line-to-neutral voltages are 120V and 120 degrees away from each other
and well balanced, as shown in Figure 3-11. Figure 3-11 shows the non-linear
current characteristics of the UPS. These power electronic loads draw power
only during portions of the applied voltage waveform.
50
Pout
η= × 100 3-1
Pin
There is a difference between the real and model transmission efficiency. The
difference might be that there are transmission losses on the real system, and
losses on the transformers and the underground cable. The PSCAD software
uses a default value for losses in the transformer, which could differ from the
actual losses on the transformer. The other possibility for this difference could
be the way in which PSCAD calculates active and reactive power and the
IEEE definitions used to calculate power in the real system.
From two simulation for cases where the transformer is treated as ideal and
non-ideal the losses was about 2%
Figure 3-12: Line-to-line voltage at the generator with two times the original
load
Figure 3-12 shows that the voltage waveforms are 120 degrees away from
each other, pure sinusoidal, and balanced, which means that doubling the
load has no effect on the line-to-line voltage. The transformer model in Figure
3-10 as an ideal transformer is used to determine the transmission efficiency
when the original load is doubled. Power into the step-up transformer and out
of the step-down transformer was calculated by the PSCAD software to
determine the transmission efficiency, and the results are provided in Table
3-4.
52
Table 3-4: Transmission efficiency using the ideal transformer double the
original load
The transmission efficiency is 65.9 % which means that doubling the original
load has an effect on the transmission efficiency of the system. It shows that if
the non-linear loads on the system increase, the losses on the cable will also
increase, which could cause overheating in the transformers and the cables in
the network. The transformer model in Figure 3-10 used as non-ideal
transformer to determine the transmission efficiency when the original load is
doubled. Power into the step-up transformer and out of the step-down
transformer was calculated by the PSCAD software to determine the
transmission efficiency, and the results are provided in Table 3-5.
The transmission efficiency is 64.6% which means that doubling the original
load has an effect on the transmission efficiency of the system. It shows that if
the non-linear loads on the system increase, the losses on the cable will also
increase, which could cause overheating in the transformers and the cables in
the network.
53
Figure 3-13: Line-to-line voltage at generator, three times the original load
The voltage waveforms in Figure 3-13 are still the same as the voltage on the
original load 120 degrees away from each other, pure sinusoidal and
balanced.
Table 3-6: Transmission efficiency using the ideal transformer, three times
the original load
Tripling the original load has a major impact on the transmission efficiency of
the model. It shows that increasing non-linear loads in the network could
cause serious problems.
3.8 Summary
It is difficult to match the exact conditions of the field measurements in the
simulation due to the unknown load powers, the unknown power losses on the
underground cable and transformers, the unbalanced currents in the network
and the variable nature of the load. The transmission efficiency of the model is
reliable, but it was shown in this chapter that as the load increases, the
transmission efficiency decreases, which means that a significant amount of
heating is generated on the transformer cores and cables on the network.
Increasing the non-linear loads in the power network has a catastrophic
impact on the current waveforms and transmission efficiency of the system.
It has been shown that as the size of the non-linear loads increases, the
current waveform distortion increases, and the transmission efficiency
decreases. Thus, additional heat is generated by the losses caused by the
harmonic content of the load current. The lifespan of a transformer and cables
the will be reduced if they operate above the rated temperatures.
4.1.1 Introduction
The work of the IEEE Working Group on non-sinusoidal situations presents a
set of practical definitions for distortion power in terms of the total,
fundamental and harmonic constituents [15]. These definitions will be
analysed numerically in the measurements to ensure adequate uncertainty of
the measurements that are made. Accurate measurements of electrical power
are becoming more important, as electrical power becomes a more essential
and valuable commodity. Many factors make this measurement more difficult
and error prone. Power is becoming dirtier and more distorted, and
measurements beyond straight power and energy are becoming
commonplace.
It is true that the different definitions suit different applications better than
others and that the diversity is sometimes advantageous. It would, however,
be a great advantage if a single theory could be found that would be equally
suitable for all types of analyses under all circumstances “[16].
56
∑U U ∑U
∗ 2
U= n n = n 4-1
n n
∑I ∑I
2
I= n In∗ = n 4-2
n n
And
∑U
2
UH = n 4-5
n ≠1
and
∑I
2
IH = n 4-6
n ≠1
From equation 4-5 and 4-6, the apparent power S can be calculated,
S = ∑|Un|2|In|2 4-7
n
N = S2-P2 4-8
In turn:
S12 = (U1I1)2
and
The term (U1IH) is named the current distortion power, (UHI1) the voltage
distortion power and (UHIH) the harmonic apparent power. The last term could,
in turn, be broken down into the total harmonic active power PH and the total
harmonic non-active power NH.
⎛SN⎞2 2 2 2
⎜ S ⎟ = (ITHD) + (UTHD) + (UTHD⋅ITHD) 4-15
⎝ 1⎠
The three right-hand terms of (4-15) represent the current THD, the voltage
THD and the product of the previous two respectively.
58
This section discusses the NRS 048 on harmonic apportioning with reference
to the voltage and current limits that are set. A comparative evaluation of the
said standard will be done and the aim is to asses the harmonic content of the
SAC electrical network, to determine whether the harmonic level of the system
is not exceeding standards limits. Efforts are being made to regulate the levels
of harmonics injected into the power system through the introduction of
standard guidelines and recommended practices.
3. to ensure that the power system does not interfere with the
operating of other systems such as telephone networks.
5 6 3 5 2 2
7 5 9 1,5 4 1
11 3,5 15 0,3 6 0,5
13 3 21 0,2 8 0,5
17 2 >21 0,2 10 0,5
19 1,5 12 0,2
23 1,5 >12 0,2
25 1,5
>25 0,2 + 1,3 × 25/h
Total harmonic distortion (THD) ≤ 8 %
NOTE — For each harmonic, the harmonic voltage distortion compatibility level is given as a percentage of the
magnitude of the declared (fundamental frequency) voltage
60
1 2 3 4 5 6
Odd harmonics non-multiple of 3 Odd harmonics multiple of 3 Even harmonics
Order Harmonic voltage Order Harmonic voltage Order Harmonic voltage
HV-EHV HV-EHV HV-EHV
H % H % H %
5 2 3 2 2 1,5
7 2 9 1 4 1
11 1,5 15 0,3 6 0,5
13 1,5 21 0,2 8 0,4
17 1 >21 0,2 10 0,4
19 1 12 0,2
23 0,7 >12 0,2
25 0,7
>25 0,2 +
0,5 × 25/h
Total harmonic distortion (THD) ≤ 3 % in HV networks
Part 2 of the NRS 048 describes the voltage quality parameters that affect the
normal operation of the electricity-dependent processes of customers. The
minimum standards in this part of the NRS 048 are intended to be applied as
a measure of the power quality at the point of supply to the end customers of
electricity utilities.
IEEE standard 519 imposes limits on the harmonics that a customer may
contribute to a network, and the harmonics that a utility may produce,
measured at the point of coupling to a customer. This ensures that individual
customers do not overly distort the electricity supply for other customers. The
electricity utility has also an obligation to supply clean power to all its
customers.
NRS 048 and IEEE 519-1992 determine the prescribed voltage current
distortion limits. IEEE 519 –1992 set limits for the harmonic of not only the
current caused by the operation of the load of individual customers, but also
the supply voltage. The NRS 048 sets harmonic limits for the supply voltage,
but does not provide current harmonic limits for the operating loads, as in
IEEE 519-1992. NRS 048 sets harmonic voltage limits only and leaves the
harmonic producers responsible for reducing their respective harmonic
currents so that the system voltage limits are not violated.
The aim of these measurements is to discuss NRS 048 and the IEEE
standards on harmonic apportioning with reference to the voltage limits that
are set as well as the apportioning procedure that is followed. An evaluation of
the said standards will be done using the current and voltage measured data
to check network compliance.
SAC and Hart RAO receive supply from ESKOM, as shown in Figure 4-1 and
discussed and shown in chapter 3. The two networks are coupled to the same
bus on the ESKOM side, but each network has its own converter mechanism.
63
The simplified model of the SAC is shown in Figure 4-2. The reason that the
SAC was the only network investigated in the dissertation was the signs of
harmonic problems had occurred on the previous measurements taken. Hart
RAO does not experience harmonic problems.
4.7 Measurement 1
Measurement 1 was taken on the secondary side of 11KV/400V 1MVA step-
down transformer, which is the ESKOM supply to SAC and Hart RAO, just
before the motor-generator set.
The line-to-neutral voltage and the line current measured in the ESKOM side
are shown in the waveforms in figure 4-3
64
Figure 4-3: The line-to-neutral voltage and the line current measured on the
ESKOM side
Order (h) Harmonic voltage (%) Order (h) Harmonic voltage (%) Order (h) Harmonic voltage (%)
It shows that the individual harmonic does not exceed the limit of the specific
harmonic by NRS 048, but the THD voltage for all harmonics is also below the
maximum limit of NRS 048. The maximum voltage distortion prescribed by
NRS 048 part 4 is 8%. With reference to NRS 048, the voltage distortion is
4.37 % below the allowable limit. This shows that the supply from ESKOM to
SAC and Hart RAO is acceptable.
66
4.8 Measurement 2
Measurement 2 was taken at the SAC generator, on the primary side of the
400V/11KV, 1MVA step-up transformer as shown in Figure 4-4.
The line-to-neutral voltage and the line current measured at the SAC
generator are shown in Figure 4-5 .
Figure 4-5: The line-to-neutral voltage and line current at the primary side of
the step-up transformer
67
It shows clearly that the type of load connected shows its impact on the
waveforms measured at the generator, by distorting the current waveform at
the source. It appears that SAC, which is generating harmonics, could
automatically be penalised by a higher apparent electricity consumption,
which might as well cause the supply some additional losses. It would be to
SAC’s own benefit to reduce the harmonic level to the largest possible extent
if they were coupled to the grid to avoid penalties.
The overall power factor of 0.8 in Table 4-5, compared to the fundamental
power factor of 0.93, is brought about by the relatively high level of harmonic
distortion. At a low power factor of operation for a given voltage and power
level, the current drawn by the equipment will be large, thus requiring an
increased volt-ampere rating of the utility equipment such as transformers,
68
transmission lines and generators. Note that the voltage the THD has
increased. In measurement 1, the THD of the voltage is 1.64% and now it is
9.09%, which is unacceptable. A diverse range of problems could be expected
as a result of this, ranging from the overheating of transformers and cables, to
odd phenomena such as the overheating of lightning circuit breakers. This
could affect sensitive equipment and the load in the system.
Order (h) Harmonic voltage Order (h) Harmonic voltage Order (h) Harmonic
(%) (%) voltage (%)
SAC NRS SAC NRS SAC NRS
Table 4-6 shows that the individual harmonic does not exceed the limit of the
specific harmonics by NRS 048, but the THD voltage for all the harmonics is
above the allowable maximum limit of NRS 048. The maximum voltage
distortion prescribed by NRS 048 part 4 is 8% and by the IEEE it is 5% THD,
but an individual THD of 3% is prescribed for 69KV systems and below.
Table 4-6 shows that the 5th harmonic is 5.04%, which is not acceptable. With
reference to NRS 048 part 4, the voltage distortion is 3.3% above the
allowable limit, which is not acceptable.
69
Order Harmonic voltage (%) Order (h) Harmonic voltage (%) Order Harmonic voltage (%)
(h) (h)
Table 4-7 shows that the individual harmonic does not exceed the limit of the
specific harmonics by NRS 048, but the THD voltage for all harmonics is
above the allowable the maximum limit of NRS 048. The maximum voltage
distortion prescribed by NRS 048 part 4 is 8 % and by the IEEE it is 5 % THD,
but an individual THD of 3% is prescribed for 69KV systems and below. Table
4-7 shows that the 5th harmonic is 5.04%, which is not acceptable. With
reference to NRS 048 part 4, the voltage distortion is 3.62 % above the
allowable limit, which is not acceptable.
Table 4-8: Comparison of NRS 048 and measurements at the SAC generator
RED PHASE
Order (h) Harmonic voltage (%) Order (h) Harmonic voltage (%) Order (h) Harmonic voltage
(%)
SAC NRS SAC NRS SAC NRS
Table 4-8 shows that the individual harmonic does not exceed the limit of the
specific harmonic by NRS 048, but the THD voltage for all the harmonics is
above the allowable maximum limit of NRS 048. The maximum voltage
distortion prescribed by NRS 048 part 4 is 8 % and by the IEEE it is 5 % THD,
and the individual THD of 3% is prescribed for 69KV systems and below.
Table 4-8 shows that the 5th harmonic is 4.64% and the 3rd harmonic is 2.9 %,
which is not acceptable. With reference to NRS 048 part 4, the voltage
distortion is 3.51 % above the allowable limit, which is not acceptable.
4.9 Measurement 3
Measurement 3 was taken on the secondary side of the 11KV/380/208V,
500kVA step-down transformer shown in Figure 4-6.
The line-line voltage and line current at the primary side of the step-down
transformer are shown in Figure 4-7.
71
Figure 4-7: The line-neutral voltage and line current at the SAC load on the
secondary side of the step-down transformer
Figure 4-7 shows the non-linear current characteristics of the UPS. These
power electronic loads draw power only during portions of the applied voltage
waveform. The voltage waveforms are not purely sinusoidal, as shown in
Figure 4-7. This is one of the observable effects that harmonics have on a
power system and impact on the quality of the AC voltage waveform
becoming distorted.
The voltage THD is 9.41%, which is unacceptable. This high voltage distortion
can clearly be seen on the voltage waveform in Figure 4-7. The power factor
is low. This is brought about by the relatively high level of harmonic distortion.
This will affect nearby sensitive loads.
Table 4-10: Comparison of NRS 048 and the SAC at the LOAD side
UPS RED PHASE
Order (h) Harmonic voltage (%) Order (h) Harmonic voltage Order (h) Harmonic voltage
(%) (%)
Table 4-10 shows that the individual harmonic does not exceed the limit of the
specific harmonic by NRS 048, except the 5th harmonic which is quite high,
and, the THD voltage for all the harmonics is above the allowable maximum
limit of NRS 048. The maximum voltage distortion prescribed by NRS 048 part
4 is 8 % and by the IEEE it is 5 % THD and the individual THD of 3% is
prescribed for 69KV systems and below.
Table 4-10 shows that the 5th harmonic is 9.32%, which is not acceptable.
With reference to NRS 048 part 4, the voltage total harmonic distortion is
4.25% above the allowable limit, which is not acceptable.
Table 4-11: Current and voltage on the three-phase at the SAC generator
Fundamental phase currents (A) Fundamental Line-to-neutral Voltage (V)
Red 217.56 ∠ -20°A Red 278.07 ∠ 0°V Reference
Blue 195 ∠ 100°A Blue 277 ∠ 120°V
White 132.9 ∠ 220°A White 277.5 ∠ 240°V
Vneg
UB = × 100 4-16
V pos
where,
0.353
UB = = 0.105% 4-17
335.235
74
The results show that the compatibility for unbalance on the SAC network is
allowable because it is less than 2%. According to NRS 048, if the network
has significant number of single-phase loads, the assessed unbalance factor
may increase to 3% [11]. The SAC network has a predominance of single-
phase loads, but the unbalance factor is still low. With reference to the IEEE,
the voltage unbalance is not a problem at the SAC, because the unbalance
factor is below the 2% benchmark for the system to be balanced.
Current unbalance
The parameters R and L of the ideal and balanced load have been estimated
on one phase according to the following procedure in [18]. The same method
can also be used for the other two phases.
If Z 1 A is the impedance of the phase with the R-L series circuit at the
fundamental frequency, it results in:
V1 A
Z1A = 4-18
I1A
∠Z1 A = θ1 A − φ1 A = ϕ 4-19
where V1 A and I1 A are the fundamental root mean square (rms) values of the
phase A voltage and current, and θ1 A and φ1 A are the phase angles of the
same quantities, then:
R A = Z 1 A ⋅ cos ϕ1 A
4-20
X 1 A= Z 1 A ⋅ sin ϕ1 A 4-21
X 1A
LA = 4-22
2 ⋅π ⋅ f0
where X 1 A represents the ideal R-L series reactance at the fundamental
frequency, f 0 , RA and LA are the expected parameters. The values of the
X kA = 2 ⋅ π ⋅ k ⋅ f 0 L A k = 1,2,…,n. 4-23
Z kA = R 2 A + X 2 kA 4-24
⎛ X kA ⎞
ϕ kA = arctg ⎜⎜ ⎟⎟ k = 1,2,…,n 4-25
⎝ A ⎠
R
where n represents the order of the last significant voltage harmonic
component.
76
The current that the ideal linear load on phase A should drain could expressed
as
n
2 ⋅ VkA
ilA (t ) = ∑ ⋅ sin( 2 ⋅ π ⋅ k ⋅ f 0 t + (θ kA − ϕ kA )) 4-26
k =1 Z1A
This is the calculated current [18].
The difference between the measured real current and the calculated current
can be defined as the non-linear current:
I nlA
⋅ 100% 4-28
IA
where I nlA and I A are RMS values
l
I nlA = ∑I
k =1
2
knlA 4-29
m
IA = ∑I
k =1
2
kA 4-30
and I knlA and I kA are the corresponding RMS values of the harmonic
regarding the network conditions. The aim of this study is to verify that the
current non-linear index as proved in [18] is a constant non-zero value when a
non-linear load is tested.
Units
Description Red phase Blue phase White phase
%
THD I 26.29 33.23 31.9
Non-linear index %
47.57 47.98 47.87
Table 4-13 shows that the non-linear current index is more invariant than the
current THD. It shows that the non-linear current index is almost the same on
all three phases measured, but the current THD varies. The current THD has
a smaller value on the phase with less distortion. In this way the evaluation of
harmonic distortion generated by the load is hardly influenced by the network
conditions. Moreover, it can be pointed out that the current non-linear index
has approximately the same value on the three phases, which means that the
same types of loads are connected. This could express the load’s ability to
affect distortion at the source.
78
Figure 4-8: Daily trend of current non-linear index and current THD [18]
For this study it is not possible to show that the current non-linear is invariant
than the current THD, because daily trends of current measurement data are
not available. Figure 4-8 shows the daily trend of the total harmonic of the
current THD and the non-linear current index where the current THD varies
while the non-linear current index is almost invariant.
4.12 Summary
Individual harmonic does not exceed the limit of the harmonics specified by
NRS 048, except the 5th harmonic, which is high in all the measurements. But
the voltage THD in the system exceeds the maximum limit of NRS 048 by
± 3.6 %. SAC did not meet these requirements from the analyses in this
chapter.
The harmonic content study of SAC conducted in this chapter shows that the
system has a significant amount of harmonics. There is a need to establish a
mechanism or tool that could be used to manage the equipment operating
under this non-sinusoidal condition. The method of de-rating transformers and
cables operating under this condition will be discussed in the next chapter.
Harmonic data will be used to illustrate these de-rating methods. The de-
rating methods will work as the tool to control the power system equipment as
the non-liner loads increase in a harmonically rich network.
80
5.1 Introduction
Methods of evaluating the performance of power system equipments
operating on harmonic load environments need to be developed. Because the
harmonic level of the network is high, and there is a possibility of expanding
these high distortion level network due to operations in the facility. There is
need to de-rate equipments such as transformers and cables. Transformers
and cables can operate at low loading, but as the network expands, the load
increases without intended de-rating. The design tool to cater for the changes
on the network needs to be developed and managed properly to avoid loss of
production due to cable or transformer failure. So before any expansion on the
existing system harmonic, studies need to be performed to analyse the
equipment capability under a harmonically loaded environment.
The flow of a normal 60-Hz current in a cable produce losses, and current
distortion introduces additional losses in the conductor. Also, the effective
resistance of the cable increases with the frequency due to skin effect, where
unequal flux linkages across the cross-section of the cable cause the AC
current to flow on the outer periphery of the conductor. Because of both the
fundamental and the harmonic currents that can flow in a conductor, it is
important to make sure that a cable is rated for the proper current flow.
Resistance of a conductor varies with frequency.
The effect of harmonic currents in the neutral conductor can be evaluated with
the same method as for the phase conductors. But the harmonic current
magnitudes could be different in the neutral conductors due to the fact that the
zero-sequence current is not cancelled, and the positive and negative
sequence harmonic currents are cancelled. Thus, the neutral becomes an
additional heat-generating conductor.
82
The skin depth is dependent on the frequency and the properties of the
conductor.
1
δ = 5-1
π ⋅ f ⋅ μ ⋅σ
where μ and σ are conductor permeability and conductivity. Copper as a
conductor with a frequency of 60 Hz, has a skin depth of:
1
δ =
(4 ⋅ π × 10 )⋅ 60 ⋅ π ⋅ (0.999991) ⋅ (5.8 × 10 )
−7 7
≈ 8mm
This means that if the conductor has a diameter of more than 16mm, most of
current flows in the outer rim, 8mm from the surface of the conductor. As the
frequency increases, so the skin depth decreases. For example, a seventh
harmonic that is operating at 420 Hz in a copper conductor has a skin depth of
3.2mm. For a third harmonic, which is operating at 300 Hz, the skin depth is
3.8mm.
Harmonic current signature is defined as the sequence {IB, α1, α3, α5, α7,…},
where IB is the base RMS value (which can be selected arbitrarily), and αi is
the per unit value of the ith harmonic with respect to the base IB [19].
The method and the equations in [19] will be used in this study to compute the
cable de-rating factor and the ohmic losses on the underground cable at SAC.
each harmonic frequency on each phase. Then add the ohmic losses for each
phase to obtain the total ohmic losses of the cable.
= 222.19kW/m
Given a harmonic signature {IB, α1, α3, α5, α7…}, the de-rating factor, k is
defined as the number k such that an identical cable carrying an undistorted
current of I1 = α1IB/k has the same losses as the cable carrying a current with
the given harmonic signature [19].
IB
k = α1 × 5-3
I1
where α1: the fundamental harmonic signature
2
α n ⋅I B
∑
2 2
P loss IB ⋅ r ac ( n ) ⋅ α n ⋅ r ac ( 1)
2
( n⋅ ε⋅ N ) k
5-3
α 1 2 ⋅ I B 2 ⋅ rac (1)
k= 5-4
Ploss
Using the value of Ploss = 222.19kW/km, IB = 225.35 A, and rac (1) = 1.3761
ohms/km the de-rating factor can be calculated.
α 1 2 ⋅ I B 2 ⋅ rac (1)
k= = 0.561
Ploss
k = 0.561 is the required de-rating factor of the cable using the resulting ohmic
losses calculated by using an extended Neher-McGrath Model for 60 Hz
losses. The underground cable capability with the given non-sinusoidal load
current harmonics composition is approximately 56% of its sinusoidal load
current capability. It shown in chapter 3 that as size of non-linear loads
increase the transmission efficiency decreases, which means that there are
additional I2R losses and this affect the ampacity of the underground cable.
This effect shortens the useful life of the cable.
5.4 Transformers
The primary effect of power system harmonics on transformers is the
additional heat that is generated by the losses caused by the harmonic
content of the load current. The lifespan of a transformer will be reduced if it
operates above the rated temperatures. Other problems include possible
resonance between the transformer inductances and system capacitances,
mechanical insulation stresses (winding and lamination) due to temperature
cycling, and possible small core vibrations.
The primary loss components are I2R losses, the winding eddy-current and
stay losses from electromagnetic flux in areas such as windings, the core and
tanks. The losses due to I2R components will be due to conductor heating and
the skin effect. Losses from the winding eddy-current will increase with the
square of the load current and the square of the frequency. Other stray losses
will also increase with frequency although at a power slightly less than two.
The losses in the iron core are basically due to hysteresis and eddy current
effects in the magnetic core. The eddy current losses, as in the case of the
windings, depend on the square of the frequency. The hysteresis loss
dependence with the frequency is not related in a simple direct way like the
eddy current losses. An important effect particularly relevant to power
transformers is the circulation of the triplex zero-sequence current in the delta
windings. The extra circulation currents could overrate the windings unless
they are taken into account in the design.
They increase the RMS current flowing in the transformer windings, which
results in additional I2R losses. The winding eddy current losses also
increase. An eddy current loss can cause an excessive winding loss from the
high-frequency heating effects. This results in a higher winding temperature
rise, which could shorten the transformer life expectancy. Transformers that
supply non-linear loads must be de-rated to handle the harmonics. The de-
rating factor is based on the percentage of the harmonic currents in the load
and the rated winding eddy current losses.
a) Method 1
This k-factor is equal to the sum of the square of the harmonic frequency
currents multiplied by the square of the harmonic frequency numbers [21]:
2 2 2 2 2 2 2 2
k := I1 ⋅ ( 1) + I2 ⋅ ( 2) + I3 ⋅ ( 3) + ....... + In ⋅ ( n )
5-5
Where:
I1 is the ratio between the fundamental current and the total RMS current,
I2 is the ratio between the second harmonic current and the total RMS current,
and
I3 is the ratio between the third harmonic current and the total RMS current.
b) Method 2
To determine the de-rating factor for the transformer, take the peak and RMS
current measurements for the three-phase conductors. If the phases are not
balanced, average the three measurements and plug that value into the
following formula:
(1.414) ⋅ RMSPhaseCurrent
= 5-7
RMSPeakPhaseCurrent
This formula generates a value between 0 and 1.0, typically between 0.5 and
0.9. If the phase currents are purely sinusoidal (undistorted), the
instantaneous peaks are 1.414 times the RMS value and the de-rating factor
is 1.0. If this is the case, no de-rating is required. However, with harmonics
present, the transformer rating is the product of the nameplate kVA rating
times the Harmonic De-rating Factor (HDF).
I = 158.516 A
140.75
I1 = = 0.888
158.516
3.63
I3 = = 0.0229
158.516
70.13
I5 = = 0.442
158.516
19.63
I7 = = 0.1238
158.516
k = 6.428
k ≈6
This study will also be used to clarify method 2 for de-rating transformers.
90
The 11kV/400/208V step-down transformer rated at 500 kVA will be used for
method 2. The currents measured on the secondary side of the step-down
transformer are given in Table 5-5.
HDF =
(1.414)(174.26) × 100 = 87%
283.85
The results indicate that with the level of harmonics present the transformer
should be de-rated to 87% of its rating to prevent overheating. The
transformer capability with the given non-sinusoidal conditions composition is
approximately 87% of its sinusoidal conditions capability.
Thus,
a) Crest factor
The crest factor is a measure of the RMS value. A perfect sine wave has a
crest factor of 1.414. The mathematical definition of the crest factor is the
92
peak magnitude of the current waveform divided by the true RMS value of the
current:
Peak
Crest factor = 5-10
RMS
The logic of this equation is that any deviation from 1.414 represents a
distorted waveform. As will be shown later, this method is limited because
harmonic frequencies are not considered.
b) % THD
The %THD is the ratio of the RMS value of the harmonics to the RMS of the
fundamental. In equation form:
∑I
2
h
h≡2
%THD = 5-11
I1
a) K-factor method
The k-factor calculation considers the important effect that frequency has on
transformer losses. The k-factor is defined as the sum of the squares of the
harmonic currents times the harmonic numbers squared [21]-[22]. In the form
of an equation, it is:
∞
∑ (I h) ⋅ h
2 2
K
h =1 5-12
It is difficult to implement the k-factor for both existing and new loads. To
calculate the k-factor on an existing system, a harmonic analysis must be
done to determine the harmonic behaviour of the system. It is difficult to obtain
an accurate harmonic study because the load is generally in a constant state
of transition. The analysis should be extended to show the maximum peaks
and valleys of the harmonic currents over time. If the analysis is complete, the
transformer can now be designed for the worst-case harmonic obtained. A
simple expansion of the k-factor calculation provides conservative results
when calculating the k-factor for differing multiple loads.
The equation used to find the values of equivalent harmonic current, IEH, from
the three harmonic indices in [22] is:
(1 − K )
(K − h2)
I EH
5-13
The 7th harmonic current index has the most useful relationship with the k-
factor in the development of the weighted sum approach to supply non-linear
loads with a single transformer [22].
1− K
I EH = × 100 5-14
K − 49
After establishing the k-factor of the load, the equivalent harmonic current
(EHC) can now be determined and combined with other loads as a weighted
sum. Then the multiple harmonic generating loads can be combined and
applied to a transformer.
2. Determine the equivalent harmonic current (EHC), IEH for each of the three
types of loads. This represents the equivalent magnitude of the 7th
harmonic to generate the same amount of heat as a specific k-rated load.
I EH (K − 30) =
(1 − 30) × 100 = 123.544 HA 5-15
(30 − 49)
I EH (K − 15) =
(1 − 15) × 100 = 64.168 HA 5-16
(15 − 49)
3. Calculate the weighted sum of the kVA-equivalent harmonic current factor
for the various types of loads and add them together. This is determined
by multiplying the nameplate of the load kVA by the equivalent harmonic
current determined above for the type of load. The results of these values
are:
96
Suppose two UPS’s have the kVA rating of 120 kVA, and a k-rating of (k-
30) each and another 260kVA and k-rating of (k-15) are for different office
equipment and power electronic equipment:
This shows that 92.67 % of the fundamental current as the 7th harmonic
produces the same heat as the combination of non-linear loads outlined
above. The results are then substituted in equation (5-13) along with the
fundamental current, and the multiple non-linear load composite k-factor is
determined to be:
The next higher standard size k-factor transformer should be specified for the
set-up at SAC to avoid a shortened transformer life. The transformer with k-
45, 500kVA is required. K-factor ratings range between 1 and 50. The higher
the k-factor, the more heat from harmonic currents the transformer is able to
handle. A standard transformer that is designed for linear loads is said to have
a k-factor of 1, whereas a transformer with a k-factor of 50 is designed for the
harshest harmonic current environment possible. Transformers rated with k-
factors of 40 and 50 are extremely rare, very expensive and generally are not
97
The weighted sum method for determining the resultant system load k-rating
is the most practical approach available to specify a transformer supplying
different non-linear and linear loads. This simple expansion of the IEEE
recommendation for specifying transformer supplying non-sinusoidal loads is
easy to implement. It will prevent the cost of over-designing the entire power
network. The use of de-rated standard transformers instead of k-factor
transformers carries some disadvantages because transformers can operate
at the reduced loading. But in the future, the loading could be increased
without considering the intended de-rating.
98
There should be a sinusoidal voltage present in all the busses throughout the
power network with a single frequency of 60Hz. But non-linear loads can
cause changes to the ideal sinusoidal voltage waveform observed at the
generator or the source. Harmonic voltage drops over the system impedances
result from the harmonic currents flowing through the frequency-dependent
impedances, causing a non-sinusoidal voltage at the bus. The voltage drop
99
Can this distorted wave feed to other loads, as for this study, Hart RAO
network, independent of whether they are linear or non-linear? The harmonic
current “propagates” through the network. Non-linear loads at SAC are
injecting harmonic currents that can travel to other locations in the power
network and eventually back into the power source. This was observed on the
wave shapes in chapter 4.
There are some concerns about harmonic currents: first, can the harmonic
currents generated by non-linear loads at SAC feed to the Hart RAO network,
which are connected to the same bus on the ESKOM supply? Secondly, with
reference to the distortion level at SAC, how long will the system operate
before major equipment failure occurs?
From the measurements taken, it is clear that Hart RAO waveforms are clean
with no distortion in the voltage and current waveforms. The Hart RAO power
network cannot be affected by harmonics generated by the SAC load because
the two networks (Hart RAO and SAC) have two separate motor-generator
sets, which means that there is a mechanical coupling between the two
networks and the ESKOM supply. Thus, harmonics generated by SAC loads
cannot affect ESKOM and Hart RAO.
The temperature rise is not uniform throughout the motor and hot spot appear
near the conductors within the iron core portions. If the harmonics are time
varying, the motor can tolerate higher peak distortion levels without increasing
the hot spot temperature. This is possible because the motor thermal time
constant is much longer than the period of the harmonic variation.
This effect is so severe that the single-phase load equal to the normal three-
phase rated currents can quickly heat the brass rotor slot wedges to a
softening point. They can then be extruded under centrifugal force until they
101
stand above the rotor surface, when it is possible that they could strike the
stator iron [24]. Concentration of heating occurs on portions of the coil binding
rings and here surface fusion has been known to occur. Heating depends on
the reaction field and on the load current. A machine can be assigned a
continuous negative sequence rating [24].
The currents will quickly cause rotor overheating and serious damage if the
generator is permitted to continue operating with such an unbalance.
Unbalanced currents can also cause severe vibration, but the overheating is
the most serious problem.
The neutral is normally sized the same as the phase conductors. Therefore,
the neutral conductor could be overloaded. This problem occurs often in
industries where a three-phase distribution system feeds large single-phase
electronic office equipment loads.
102
The effect of this low frequency common mode noise voltage is somewhat
debatable, typically calling for less than 0.5 RMS, neutral-to-ground at the
source regardless of the frequency. But as we move away from the source,
this neutral-to-ground voltage increases depending on the load and the
distance between the sources. This can measure 2 to 3 V [25]. The neutral
conductor can be sized to twice the phase conductor capacity to solve the
problem.
5.5 Summary
The harmful effects of harmonic voltages and currents on transformers, cables
and motor generator set performances often go unnoticed until an actual
failure occurs. In some instances, transformers that have operated
satisfactorily for long periods have failed in a relatively short time when plant
loads were changed or a facility's electrical system was reconfigured.
6.1 Conclusions
There is agreement between the model and real measurements. It was
difficult to match the model results with exact conditions of the field
measurements for several reasons:
NRS 048 and the IEEE follow different approaches to determine the
prescribed voltage and current distortion limits. The IEEE sets limits for the
harmonics of not only the current caused by the operation of the loads, but
also the supply voltage. NRS 048 sets harmonics limits for the supply voltage,
but does not provide current harmonic limits for the operation of loads as the
IEEE. NRS 048 sets harmonic voltage limits only and leaves the harmonic
producers responsible for reducing their respective harmonic currents so that
the system voltage limits are not violated. Signs of harmonics are occurring in
the system. The analysed field measurements in chapter 4 show that the
overall total harmonic voltage distortion is high in the SAC network, with
reference to NRS 048 and IEEE 519 standards. It shows that the individual
harmonic does not exceed the limit of the specific harmonics specified by
NRS 048 except the 5th harmonic, which is high in every point measured on
105
Unbalance voltage is not a problem in the SAC network, because the voltage
unbalance factor is below 2% stated by the IEEE and NRS 048. The only
problem in the SAC network is unbalanced and distorted currents, and their
effects on the power system.
The new index discussed in chapter 4 can be used to evaluate the distortion
on the network. Because this current non-linear index is independent of the
load entity and can be used to express the capability of the non-linear load to
affect harmonic diction at the source. This index can provide information about
the harmonic distortion level and be compared to the current total harmonic
distortion to indicate its accuracy and behaviour.
It is evident that the power system engineer must be concerned about the
application of the complete range of power system devices when applied in
the harmonically loaded environment. This subject is by no means complete
and a great deal of work remains to be done. It is possible to use basic
application guidelines and limitations. The response of various types of
equipment to distorted waveforms is by no means uniform and some
components are of more concern than others. Capacitors, dry type
transformers and electronic equipment rate require the highest degree of
attention. The effects of distorted waveform on cables, motors and oil-filled
transformers cannot be ignored. Transformers supplying non-linear loads at
SAC require de-rating to avoid overheating.
Regarding the methods of calculating the heating due to harmonics, only the
expanded k-factor method was acceptable for specifying the non-sinusoidal
condition. This method takes harmonic frequency into account. The estimation
method for power system harmonics effects on power transformers was
discussed in chapter 5 for dry-type or k-rating types of transformers, but oil-
filled transformers are used at SAC. It will be costly for SAC to redesign and
replace the oil-cooling type of transformers. For an accurate estimation of the
additional heat non-sinusoidal loads inflicted on transformers, harmonic
106
The set of equations for calculating total ohmic losses in the cable with
distorted current are presented in chapter 5. These equations can be used to
compute the required de-rating factor for the cable system because of the
presence of harmonics. The calculations can be performed with a handheld
calculator. Example of these calculations are included in chapter 5 of this
document.
It would be beneficial for SAC to minimise the harmonic level on the network
to avoid equipment failure and a major loss of production. As the number of
non-linear loads increases, the level of distortion will also increase. But it is
difficult to notice the effects of a harmonic current on equipment until
equipment failure occurs.
7 ANNEXURES
PSCAD is a powerful user friendly and accurate power simulator for all types
of power distribution systems. It is graphically interfaced that allows the user
to systemically construct any circuit, run simulation, analyse results, run-time
control and reporting. This software includes a library where most of the
components could be easily accessed for power system analysis. Own
modeling of system and components using the built-in graphical components
workshop, could also be created when the master library could not support the
simulation. Although PSCAD is improved to interface well with the other
Microsoft windows operating systems, it requires a fortran compiler to execute
the simulation. Together with the compiler, PSCAD has proved to be effective,
accurate and fast simulation software for studying transient behavior of
electrical networks.
( )
arg IC = deg ( )
arg VC = deg
1
Va = (Va + Vb + Vc )
0
a := −0.5 + 0.866i
1
Ia = (Ia + Ib + Ic )
0
3
2 3
a = 1
Va = (Va + aVb + a 2Vc )
1
1
I a = ( I a + aI b + a 2 I c )
1
3
3 1
Va = (Va + a 2Vb + aVc )
2
1
I a = ( I a + a 2 I b + aI c )
2
3
(
Izero := IA + IB + IC ⋅
1
3
) 3
(
Vzero := VA + VB + VC ⋅
1
)
3
Izero =
Vzero =
(
arg Izero = ) (
arg Vzero = deg)
(
arg Ipos = ) ( )
arg Vpos = deg
Ineg = Vneg =
(
arg Ineg = deg ) ( )
arg Vneg = deg
UNI = % UN = %
111
8 LIST OF REFERENCES
[3] //http://www.hart.radio.astronomy.observatory/.htm
[6] J. Arrilaga, D.A. Bradley, P.S. Bodger, Power System Harmonics, John
Wiley & Sons, New York, Brisbane 1985.
[8] R.C. Dugan, M.F. McGranaghan and H.W. Beaty, Electrical Power
Systems Quality, McGraw-Hill, USA, 1996.
[10] C.J. Melhorn, T.D. Davis and G.E. Beam, “Voltage Sags: Their Impact
on the Utility and Industrial Customers”, IEEE Transactions on Industry
Applications”, Vol. 34, No. 3, May/June 1998, pp. 549-558.
[14] Wilsun Xu, “Status and Future Direction of Power System Harmonic
Analysis”.
[18] Antonio Dell’ Aquila, Maria Marinelli, Vito Giuseppe Monopoli, Pericle
Zanchetta, “New Power-Quality Assessment Criteria for Supply System
Under Unbalanced and Non-sinusoidal Conditions”, IEEE Transactions
on Power Deliver, vol.19, no.3, July 2004, pp 1284 – 1290.