Optimal Solutions For A 33 KV Loop Supplied by Infinite Source
Optimal Solutions For A 33 KV Loop Supplied by Infinite Source
Corresponding Author:
Ethmane Isselem Arbih Mahmoud
Research Team in Electrical Energy and Control, Mohammed V University
Mohammadia School of Engineers
Avenue Ibn Sina, Rabat, Morocco
Email: [email protected]
1. INTRODUCTION
Effective power system management involves more than ensuring that the power transits remain
below transmission capacity. Several technical parameters must also be monitored, including voltage levels.
The voltage must be maintained within a permissible range at all points in the grid under all anticipated
production and consumption scenarios. In this context, we also propose analyzing the feasibility of an infinite
source generation system to meet the domestic demand of the 33 kV network. The goal is to achieve and
maintain a voltage profile within the range of 0.95 to 1.05 per unit (pu). To achieve this, we modeled the power
grid based on its transit capacities and analyzed the simulation results using PSSE and MATLAB.
This modelling is also conducted to ensure the voltage profile remains within the limits established
by the grid operator. Another objective is to propose a methodology for managing and controlling transit power
and voltage to optimize system efficiency under varying conditions. In this context, a reactive energy
compensation system is proposed [1]-[11]. To achieve the predetermined objectives, we undertake the
following steps:
First, we provide a schematic diagram of the 33 kV loop network, including its various parameters for
the year 2022 [12]-[16]. This is followed by calculating the power system admittance matrix and analyzing the
load flow results. In the second step, we provide the forecasted demand for the years 2025 to 2040 [17], [18].
In the third step, a numerical model using the gauss-seidel (GS) method is implemented and run in the
MATLAB environment and PSS/E simulator. The simulation results will be analyzed and discussed to address
any identified issues. In the fourth step, we implement the proposed solutions to optimize the power flow and
voltage profiles of the studied network. A conclusion is then drawn based on the proposed work. It is important
to note at the end of this introduction that increasing transformer capacity aims to establish a stable electrical
energy network capable of delivering the required power to consumers, even during disturbances [19]-[23].
2. METHOD
Figure 1 illustrates the single-line diagram of the 33 kV loop network. The line data, injected powers
at the buses, and load information are provided in Tables 1 and 2, respectively. The electrical network
comprises four transmission lines, four transformer substations fed by an infinite source, and four loads
connected to buses 1, 2, 3, and 4 as shown in Figure 1. The active and reactive powers generated are expressed
in MW and MVAR. The voltage at each bus (i) is given in per unit. Each load bus is characterized by its active
power P and reactive power Q, with (P, Q) specified and(V) to be calculated. In this context, bus 3 is proposed
to be the slack bus. Additionally, it should be noted that a bus numbered (i) is connected to (k) other buses, as
depicted in Figure 1.
SP2 SP1
2 M'Bout Selibabi 1
SL2 SL1
SP3 SP4
3 4
Kaedi Gouray
SL3 SL4
Table 3 shows the projected system demand from 2025 to 2040 using extrapolation. This forecast is
crucial for strategic planning and resource allocation. It helps anticipate future needs and prepare accordingly.
Table 4 presents the simulation results for the admittance matrix involving buses 1, 2, 3, and 4. This data
highlights the interactions and performance of these buses within the system. Analyzing these results is crucial
for understanding system dynamics.
Optimal solutions for a 33 KV loop supplied by infinite source (Ethmane Isselem Arbih Mahmoud)
206 ISSN: 2088-8694
Table 3. Projected demand of the system between 2022 and 2040 years
2025 - 2030 2030- 2035 2035-2040
Country
PD (Mw) QD (Mvar) PD (Mw) QD (Mvar) PD (Mw) QD (Mvar)
Sélibabi 10.33 7.524 11.537 8.653 13.268 9.951
M’Bout 4.751 4.345 5.464 4.997 6.284 5.746
Kaédi 11.385 8.538 13.09 9.819 15.056 11.292
Gouray 4.109 3.42 4.726 3.93 5.435 4.523
Pi − jQ i = Vi∗ Ii (2)
Pi,inj − j𝑄𝑖,𝑖𝑛𝑗 = Vi∗ ∑nk=1 𝑉𝑖𝑘 𝑉𝑘 = Vi∗ [𝑌𝑖1 𝑉1 + 𝑌𝑖2 𝑉2 + ⋯ + 𝑌𝑖𝑖 𝑉𝑖 + ⋯ + 𝑌𝑖𝑛 𝑉𝑛 ] (3)
Calculation of current flowing between bus(i) and bus (k) is defined by (5).
Hence, the voltage and the conjugate complex power at bus(i) is calculated by (6) and (7) respectively.
Vi = |Vi |∠δi , Vk = |Vk |∠δk , Yii = |Yii |∠θii , Yik = |Yik |∠θik (6)
The injected powers at bus (i) are defined by (8) and (9).
Int J Pow Elec & Dri Syst, Vol. 16, No. 1, March 2025: 204-211
Int J Pow Elec & Dri Syst ISSN: 2088-8694 207
Since the voltage at the buses must be maintained within certain specified statutory limits, the voltage bound
constraint limit at bus (i) is defined by (10).
Where Vi (min) and Vi (max) are minimum and maximum voltage values at bus i. The reactive power supply
constraint at bus (i) is specified by (11).
With Qgi(min) et Qgi(max) are minimum and maximum reactive power values generated at bus(i).
Where, Qc- is a reactive power in MVAr, U - is a bus bar voltage, C - is a capacitance in μF, ω - is a pulse, F
is a network frequency. Given that C= 20 μF, U=33 KV, F=50 Hz, we calculate the reactive power required to
maintain the system within voltage constraints (0.95 and 1.05pu) substituting these values into (10) then
applying in (13).
𝑄𝐶 = 3 ∗ 314 ∗ 332 106 ∗ 20 ∗ 10−6 = 20.51 𝑀𝑉𝐴𝑅 𝑤𝑖𝑡ℎ 𝜔 = 314 𝑟𝑎𝑑/𝑠 (13)
The injected reactive power at Selibabi bus bar (1) is Qc=20.51 MVAR. This represents a bank of capacitors
shunt connected at bus (1).
Optimal solutions for a 33 KV loop supplied by infinite source (Ethmane Isselem Arbih Mahmoud)
208 ISSN: 2088-8694
Table 5. Simulation results at 2040 year Table 6. Simulation results after injected reactive
with using PSS/E power at bus 1
Name of bus N° Type Vpu ϕ° Bus N° Type Vpu ϕ°
Selibabi 1 PQ 0.9 -1.55 Selibabi 1 PQ 1 -5.15
M’Bout 2 PQ 0.93 -0.89 M’Bout 2 PQ 0.985 -2.69
Kaedi 3 Slack 1 0 Kaedi 3 Slack 1 0
Gouray 4 PQ 0.91 -1.37 Gouray 4 PQ 0.99 -4.33
Table 7 presents the simulation results for total active and reactive power before and after the insertion
of the reactive power compensation system at Selibabi bus (1). A reduction in total power losses is observed.
This improvement highlights the effectiveness of the compensation system. Figure 4 shows a reduction in total
active power loss from 1.8 MW to 1.5 MW. This indicates an improvement in active power transmission
through the lines. The results highlight the effectiveness of the reactive power compensation system in
enhancing voltage levels at buses and reducing active power losses.
Figure 5 shows a reduction in total reactive power loss from 2.5 MVAR to 2 MVAR. That indicates
a decrease in reactive power loss through the transmission lines. These results demonstrate the effectiveness
of the reactive power compensation system in enhancing voltage levels at buses and reducing reactive power
losses in the power system.
Figure 4. Total active power losses Figure 5. Total reactive power losses
Int J Pow Elec & Dri Syst, Vol. 16, No. 1, March 2025: 204-211
Int J Pow Elec & Dri Syst ISSN: 2088-8694 209
rating of transformer T2 (MVA2) and its percentage impedance (%Z2); iii) The total demand power (MVA);
and iv) With these parameters, the load can be appropriately distributed between the two transformers.
Load sharing by T1 as in (14).
𝑀𝑉𝐴1
𝑍1
𝑇1 = 𝑀𝑉𝐴1 𝑀𝑉𝐴2 ∗ 𝑀𝑉𝐴 (14)
+
𝑍1 𝑍2
To determine the power values shared between connected transformers in parallel at bus 3 (Kaedi) in
the year 2040, you can use (14) and (15). These equations will allow you to calculate the distribution of power
between the transformers based on their ratings and impedances. Noting that one of the transformers is already
existing in the system with a rating of T1=10 MVA, the load shared by the second transformer (T2) can be
determined as the following:
˗ The total load demand (MVA) minus the power rating of the existing transformer (MVA1) gives the load
that needs to be handled by the second transformer (MVA2).
˗ Mathematically: MVA2 = total load demand (MVA) − MVA1
˗ Where: MVA1 is the power rating of the existing transformer (10 MVA). MVA2 is the power rating
required for the second transformer. To carry out this analysis, we will examine two cases:
˗ Simulation Case: Use PSSE software to determine the total load demand of the system.
˗ Analytical Case: Calculate the shared load between transformers T1 and T2 using (14) and (15), as detailed
in Table 8.
˗ This approach allows for a comparison between the simulated load demand and the theoretical calculations
for load distribution.
˗ Based on Table 8, we can determine and fix the shared load between the two transformers, with T1=10
MVA and T2 = 31 MVA. Operating the transformers in parallel is more economical compared to replacing
them, as this approach allows for scaling with load increases.
Table 8. Simulations and calculation results of load shared at Kaedi bus (3)
Total load Load of Load shared by Impedances of T1 Calculation results in Simulations results
Bus (T) existing (T1) (T2) and T2 MVA in MVA
(MVA) (MVA1) (MVA2) %Z1 %Z2 T1 T2 T1 T2
Kaedi 41 10 31 8 10 15.25 25.62 20.5 20.5
Year 2040 < 2030 > 2030 - - - - - -
4. CONCLUSION
In this paper, we examined the state of a 33 KV loop for two distinct periods: First Period: The state
of the network parameters (voltages, powers) for the year 2022. During this period, the system is stable, and
all parameters are within the required standards. In the second period, we projected the demand forecast from
2025 to 2040. The results indicated that the system would exceed stability constraints. To address the increasing
demand, we proposed injecting reactive power using a capacitor bank at the Selibabi bus (1). This intervention
allows the system to remain within the voltage stability margin (0.95 to 1.05 per unit) and reduces power
mismatches. As a result, the system achieves stability in both voltage and power at each busbar.
In the second case, where the existing transformers become overloaded, it is more economical to
operate the transformers in parallel. This approach allows for accommodating load increases by adding
transformers in parallel rather than replacing them. As a result, the system becomes stable in both voltage and
power. Furthermore, when the load decreases, one of the two transformers can be deactivated to prevent low-
efficiency operation at reduced loads.
ACKNOWLEDGEMENTS
The authors would like to thank the Rosso Higher Institute of Technological Education,
Electromechanical Engineering Department, in Mauritania, Laboratory of Research Applied to Renewable
Energies, Nouakchott, University, Mauritania. We also extend our gratitude to the reviewers and editor-in-
chief for their valuable remarks, which have significantly improved the quality of this paper.
Optimal solutions for a 33 KV loop supplied by infinite source (Ethmane Isselem Arbih Mahmoud)
210 ISSN: 2088-8694
REFERENCES
[1] T. S. Tran, T. H. Dang, and A. T. Tran, “Optimal Control of Switched Capacitor Banks in Vietnam Distribution Network Using
Integer Genetic Algorithm,” Indonesian Journal of Electrical Engineering and Informatics, vol. 11, no. 2, pp. 553–561, 2023, doi:
10.52549/ijeei.v11i2.4518.
[2] M. Myintzu, K. M. Lin, and K. Z. Oo, “Optimal capacitor allocation for minimizing cost of energy loss in active distribution network
with different load levels,” International Journal of Applied Power Engineering (IJAPE), vol. 12, no. 1, pp. 71–82, 2023, doi:
10.11591/ijape.v12.i1.pp71-82.
[3] A. Rezaei, A. Balal, and Y. P. Jafarabadi, “Using machine learning prediction to design an optimized renewable energy system for
a remote area in Italy,” International Journal of Applied Power Engineering (IJAPE), vol. 12, no. 3, pp. 331–340, 2023, doi:
10.11591/ijape.v12.i3.pp331-340.
[4] M. Mahmoud and A. Faza, “Reliability improvement of power systems using shunt reactive compensation and distributed
generation,” International Journal of Applied Power Engineering (IJAPE), vol. 12, no. 3, pp. 277–292, 2023, doi:
10.11591/ijape.v12.i3.pp277-292.
[5] P. R. Kumari, K. Rajasri, T. Diwakara, S. Reddy, and A. Sudhakar, “Power factor improvement using silicon based switching
devices for changing load parameters,” International Journal of Applied Power Engineering (IJAPE), vol. 12, no. 4, pp. 367–372,
2023, doi: 10.11591/ijape.v12.i4.pp367-372.
[6] I. A. E. Mahmoud, A. Yahfdhou, M. Maaroufi, I. Youm, A. K. Mahmoud and H. Menou, “An Optimized STATCOM for Higher
Quality of the Power System,” in 2018 International Symposium on Advanced Electrical and Communication Technologies
(ISAECT), Rabat, Morocco, Dec. 2018, pp. 1-5, doi: 10.1109/ISAECT.2018.8618814.
[7] A. D. Hermawan et al., “Effect of the placement capacitor bank on electrical power quality in the ILST fan drive system,” International
Journal of Power Electronics and Drive Systems, vol. 15, no. 3, pp. 1435–1445, 2024, doi: 10.11591/ijpeds.v15.i3.pp1435-1445.
[8] M. A. Al-Tak, M. F. Ain, O. S. Al-Yozbaky, and M. K. M. Jamil, “Impact of grading capacitor on transient recovery voltage due
to shunt reactor de-energization for different values of current chopping,” International Journal of Power Electronics and Drive
Systems, vol. 15, no. 2, pp. 1300–1307, 2024, doi: 10.11591/ijpeds.v15.i2.pp1300-1307.
[9] F. G. Merconchini, L. V. Seidedos, J. C. Oliva, J. R. N. Alvarez, and D. Checa-Cervantes, “Study of electric power quality indicators
by simulating a hybrid generation system,” International Journal of Power Electronics and Drive Systems, vol. 14, no. 2, pp. 1044–
1054, 2023, doi: 10.11591/ijpeds.v14.i2.pp1044-1054.
[10] M. H. Ali, A. M. A. Soliman, and S. K. Elsayed, “Optimal power flow using archimedes optimizer algorithm,” International Journal
of Power Electronics and Drive Systems, vol. 13, no. 3, pp. 1390–1405, 2022, doi: 10.11591/ijpeds.v13.i3.pp1390-1405.
[11] O. Y. Her, M. S. A. Mahmud, M. S. Z. Abidin, R. Ayop, and S. Buyamin, “Artificial neural network based short term electrical
load forecasting,” International Journal of Power Electronics and Drive Systems, vol. 13, no. 1, pp. 586–593, 2022, doi:
10.11591/ijpeds.v13.i1.pp586-593.
[12] N. Agouzoul, A. Oukennou, F. Elmariami, J. Boukherouaa, and R. Gadal, “Power efficiency improvement in reactive power
dispatch under load uncertainty,” International Journal of Electrical and Computer Engineering, vol. 14, no. 4, pp. 3616–3627,
2024, doi: 10.11591/ijece.v14i4.pp3616-3627.
[13] M. T. Sarker, M. J. Alam, G. Ramasamy, and M. N. Uddin, “Energy demand forecasting of remote areas using linear regression
and inverse matrix analysis,” International Journal of Electrical and Computer Engineering, vol. 14, no. 1, pp. 129–139, 2024, doi:
10.11591/ijece.v14i1.pp129-139.
[14] Y. W. Liu, S. H. Rau, C. J. Wu, and W. J. Lee, “Improvement of Power Quality by Using Advanced Reactive Power Compensation,”
IEEE Transactions on Industry Applications, vol. 54, no. 1, pp. 18–24, 2018, doi: 10.1109/TIA.2017.2740840.
[15] K. A. Makinde, D. O. Akinyele, and A. O. Amole, “Voltage rise problem in distribution networks with distributed generation: A
review of technologies, impact and mitigation approaches,” Indonesian Journal of Electrical Engineering and Informatics, vol. 9,
no. 3, pp. 575–600, 2021, doi: 10.52549/.V9I3.2971.
[16] N. S. I. Razali, T. S. Gunawan, S. H. Yusoff, M. H. Habaebi, S. L. Ibrahim, and S. N. M. Sapihie, “Voltage Instability and Voltage
Regulating Distribution Transformer Assessment Under Renewable Energy Penetration For Low Voltage Distribution System,”
Indonesian Journal of Electrical Engineering and Informatics, vol. 11, no. 3, pp. 673–684, 2023, doi: 10.52549/ijeei.v11i3.4857.
[17] I. A. Ethmane, M. Maaroufi, A. K. Mahmoud, and A. Yahfdhou, “Optimization for electric power load forecast,” International
Journal of Electrical and Computer Engineering, vol. 8, no. 5, pp. 3453–3462, 2018, doi: 10.11591/ijece.v8i5.pp3453-3462.
[18] E. Almeshaiei and H. Soltan, “A methodology for Electric Power Load Forecasting,” Alexandria Engineering Journal, vol. 50, no.
2, pp. 137–144, 2011, doi: 10.1016/j.aej.2011.01.015.
[19] O. N. Igbogidi and A. A. Dahunsi, “Enhancement of Power Supply with Paralleling of Transformers Using Same Parameters
Approach,” International Research Journal of Engineering and Technology (IRJET), vol. 07, no. 11 | Nov 2020, pp. 397–404, 2020.
[20] Z. Cabrane, M. Ouassaid, and M. Maaroufi, “Battery and supercapacitor for photovoltaic energy storage: a fuzzy logic
management,” IET Renewable Power Generation, vol. 11, no. 8, pp. 1157–1165, Jun. 2017, doi: 10.1049/iet-rpg.2016.0455.
[21] B. B. Kucukkaya and N. Pamuk, “Theoretical and practical analysis of parallel operating conditions of two transformers with
different relative short circuit voltages,” Sigma Journal of Engineering and Natural Sciences, vol. 42, no. 3, pp. 701–713, 2024,
doi: 10.14744/sigma.2023.00025.
[22] D. Trebolle and B. Valecillos, “Optimal Operation of Paralleled Power Transformers,” Renewable Energy and Power Quality
Journal, vol. 1, no. 6, pp. 623–627, 2008, doi: 10.24084/repqj06.392.
[23] Z. W. Aung, “Analysis of Three Phase Transformer Parallel Operation and Circulating Current Phase,” International Journal of
Trend in Scientific Research and Development (IJTSRD), vol. 3, no. 5, pp. 1147–1150, 2019.
[24] M. I. Kuznetsov, D. A. Dadenkov, S. A. Dadenkov, and D. S. Dudarev, “Parallel operation of three-phase power transformers with
different short-circuit voltages,” Russian Electrical Engineering, vol. 88, no. 6, pp. 388–393, 2017, doi: 10.3103/,
https://link.springer.com.
[25] A. V. Romodin and M. I. Kuznetsov, “Transformation of reactive power in a three-circuit transformer with capacitive
compensation,” Russian Electrical Engineering, vol. 84, no. 11, pp. 595–598, 2013, doi: 10.3103/ https://link.springer.com.
[26] L. Lilien, “Course on the Transport and Distribution of Electrical Energy,” Department of Electrical Engineering and Computer Science,
Institute of Electricity Mont Fore, University of Liège, 2013.
[27] J. L. Lilien, “Alimentation de faibles charges directement des lignes à haute tension,” Ph.D dissertation, Department of Electrical
Engineering and Computer Science, University of Liège, 2002.
[28] O. Mammeri, “Différentes méthodes de calcul de la puissance réactive dans un nœud a charge non linéaire en présence d’un système
de compensation de l’énergie,” M.S. thesis, Département d'Électrotechnique, Université Batna, 2012.
Int J Pow Elec & Dri Syst, Vol. 16, No. 1, March 2025: 204-211
Int J Pow Elec & Dri Syst ISSN: 2088-8694 211
[29] I. Zoubga, “Etude et dimensionnement de la liaison électrique interurbaine Pa-Dédougou : Tronçon 33KV Safane- Wona,” Ph.D
dissertation, Departement of Génie Électrique, Institut International d’Ouagadougou, 2013.
[30] M. Badis, “Modélisation, analyse et commande des grands systèmes électriques interconnectés,” Ph.D dissertation, Department of
Electronique-Electrotechnique-Automatique, Ecole normale supérieure de Cachan, 2010.
[31] I. B. Anichebe, A. O. Ekwue, and E. S. Obe, “Time-series trendline and curve-fitting-based approach to short-term electricity
demand forecasting,” International Journal of Applied Power Engineering (IJAPE), vol. 13, no. 1, pp. 81–90, 2024, doi:
10.11591/ijape.v13.i1.pp.81-90.
BIOGRAPHIES OF AUTHORS
Ahmed Abbou received the B.E. degree from ENSET in Rabat, the M.E. degree
from Mohammed V University in Rabat and the Ph.D. degree from Mohammed V University in
Rabat, in 2000, 2005 and 2009, respectively, all in Electrical Engineering. Since 2009, he has
been working at Mohammadia School of Engineers, Mohammed V University in Rabat,
Department of Electric Power Engineering, where he is a full professor of Power Electronics and
Electric Drives. He published numerous papers in scientific international journals and
conferences proceedings. His current research interests include induction machine control
systems, self-excited induction generator, power electronics, sensorless drives for AC machines,
Electric Vehicles charge, drone control and renewable energy conversion. He can be contacted
at email: [email protected].
Abdel Kader Mahmoud was born in Aleg, Mauritania in 1960. He received his
master degree of sciences in Power Stations in 1988 and his Ph.D. degree in Electrical Engineering
from the Technical University of Tashkent in Uzbekistan, in 1991. Then he received his second
doctorate degree in Renewable Energy from the University of Cheikh anta Diop (UCAD), Dakar,
Senegal, in 2008. Currently he is in charge of the Applied Research Laboratory of Renewable
Energy (LRAER). He is the author and co-author of more than 30 scientific papers. Their current
project is 'Comparison between the different numerical models and determination of parameters
characteristics physical materials. He can be contacted at email: [email protected].
Optimal solutions for a 33 KV loop supplied by infinite source (Ethmane Isselem Arbih Mahmoud)