Assignment 2014 CEP
Assignment 2014 CEP
1) Think of a construction project you participated in or observed. Write down the steps
involved in its planning and the steps involved in its scheduling (without much
specificity).
Step 1: Explain the project plan to key stakeholders and discuss its key components
Step 2: Define roles and responsibilities
Step 3: Hold a kickoff meeting
Step 4: Develop a Scope Statement
Step 5: Analyze project quality and risks
2) Prepare a bar chart for building in ground swimming pool. If you do not know the steps
involved, ask a practitioners or search for the information.
There are multiple possible answers.
After Design of Swimming Pool, we should select site location
A- Excavation of Earth
B- Construction of Swimming Pool Base
C- Steel Cage Reinforcement
D- Pump and Filter System for Swimming Pool
E- Concrete in Swimming Pool Construction
F- Waterproofing the Concrete Pool
G- Construction of Coping
Assignment 2
1) You are given the following information about a project consisting of six activities:
1-2-5-6 14 months
Hence, Critical Path is 1-2-5-6 with the duration of 14 months. Now, duration of activity D can be
increased by 2 months at most. So, maximum duration of activity D without delaying completion of
project is 6 months.
2) For the following schedule, draw the network diagram, perform the CPM calculation,
mark the critical path, and complete the table
3) Based on the activities given below. Using PERT three estimate approach
Time Required
Optimistic Most Likely Pessimistic Immediate
Task Estimate Estimate Estimate Predecessors
A 3 weeks 4 weeks 5 weeks
B 2 weeks 2 weeks 2 weeks A
C 3 weeks 5 weeks 6 weeks B
D 1 weeks 3 weeks 5 weeks A
E 2 weeks 3 weeks 5 weeks B,D
(a) Find the estimate of the mean and variance of the duration of each activity.
(b) Find the mean critical path.
(c) Find the approximate probability of completing the project within 11 weeks.
Since probability of project completion on 11 weeks is more than 50%; Ato Abera ,
president of AK con Construction Company, should submit a bid contract to earn
250,000 birr profit.
4) List out and discuss insurance clauses of the harmonized FIDIC 2006 and PPA 2011
Condition of contract for works of Civil Engineering construction?
5) Discuss the cause of accidents in construction project and the method of preventing
accidents in the construction projects?
6) Give the definition for the following terms that are used frequently in safety concept.
Injury
Hazed
Risk
Hazardous materials
Pollutant
Pollution
Environmental impact assessment (EIA)