Project_Management_Course
Project_Management_Course
Arij Sayhi
• Projects are responsible for the latest and most improved products, services, and organizational processes.
• Projects provide a philosophy and strategy for the management of change.
• Project management involves crossing functional and organizational boundaries.
• Traditional management functions of planning, organizing, motivation, directing, and controlling apply to project manage-
ment.
• Principal outcomes of a project are the satisfaction of customer requirements within the constraints of technical, cost, and
schedule objectives.
• Projects are terminated upon successful completion of performance objectives.
• One in six I T projects has an average cost overrun of 200 percent and a schedule overrun of 70 percent
• More than a third of the 110 billion Dollars in costs spent on the post-war reconstruction projects in Afghanistan, total
110 billion Dollars was lost due to fraud, waste and abuse.
1
1.5 Why Are Projects Important?
• Shortened product life cycles
1.6.1 Conceptualization
Development of the initial goal and technical specifications of the project. Key stakeholders are identified and signed on at this
phase.
1.6.2 Planning
all detailed specifications, schedules, schematics, and plans are developed.
1.6.3 Execution
The actual “work” of the project is performed.
1.6.4 Termination
The project is transferred to the customer, the resources are reassigned, and the project is closed.
Figure 1: Change During Project Life Figure 2: Project Life Cycles and
Cycle Their Effects
2
Figure 4: Four Dimensions of Project Success Im-
portance
Figure 3: Quadruple Constraint of
Project Success
Figure 5: Spider Web Diagram for Measuring Figure 6: Spider Web Diagram with Embedded Or-
Project Maturity ganizational Evaluation
3
Project Management Maturity—A Generic Model
4
Project Management Employability Skills Project Manager Responsibilities
5
2 Project Selection and Portfolio Management
2.1 Project Selection
Screening models help managers pick winners from a pool of projects. Screening models are numeric or nonnumeric and
should have:
• Realism
• Capability
• Flexibility
• Ease of use
• Cost effectiveness
• Comparability
2.2.4 Additional
Patent protection , Impact on company’s image , Strategic fit
All models only partially reflect reality and have both objective and subjective factors imbedded.
6
2.3.3 Analytic hierarchy process
The AHP is a four step process:
Profile Model
7
Table 1: Comparison of Payback for Projects A and B
Discount sum of cash flows by the company’s required rate of return to get a more accurate payback period.
8
This table has been calculated using a discount rate of 15 Percent
The project does meet our 15 Percent requirement and should be considered further.
• review
• realignment
• reprioritization of a firm’s projects
9
2.5.2 Developing a Proactive Portfolio
The project portfolio matrix classifies projects into four types according to commercial potential and technical feasibility:
• Time-paced transition
• Unpromising projects
• Scarce resources
10
3 Leadership and the Project Manager
Leadership is “The ability to inspire confidence and support among the people who are needed to achieve orga-
nizational goals.”
• Joint accountability
• Absolute honesty
Project managers:
• acquire project resources
• Requirements understated
• Insufficient funds
• Distrust between managers
11
3.4 Purpose of Meetings
• 1.Define project and team players.
3.5 Communicate
It is critical for a project manager to maintain strong contact with all stakeholders.
Project meetings feature task-oriented and group maintenance behaviors.
[Continued]
Task and Group Maintenance Behaviors
• Technically competent
• Decisive
• A good communicator
• A good motivator
12
3.8 Leadership and Emotional Intelligence
Emotional intelligence refers to leaders’ ability to understand that effective leadership is part of the emotional and relational
transaction between subordinates and themselves.
Five elements characterize emotional intelligence:
• Self-awareness
• Self-regulation
• Motivation
• Empathy
• Social skills
Champions can be: creative originator , entrepreneur , “godfather” or sponsor , project manager
• Information gathering
• Constraints
• Alternative analysis
• Project objectives
• Business case
A document issued by the project initiator or sponsor formally sanctioning existence of the project and authorizes the project
manager to begin applying organizational resources to project activities
It is created once project sponsors have done their “homework” to verify that:
15
4.2.1 Work Breakdown Structure (WBS)
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the
project objectives and create the project deliverables. Each deliverable is decomposed, or broken down, into specific “bite-sized”
pieces representing work to be completed.
WBS Hierarchy
• One owner
• Miniature projects
• Milestones
• Fits organization
• Trackable
• work definition
• owner assignment of work packages
• budget assignment to departments
• Valid consideration
• Contracted terms
Contracts range from: Lump-sum or Turnkeys and Cost plus
• Document control
• Acquisition control
• Specification control
18
4.5.4 Project Changes
Occur for one of several reasons:
• Client requests
4.7 Sustainability
Sustainable development involves efforts to promote harmony among human beings and between humanity and nature.
Sustainability involves efforts to promote the triple bottom line of social sustainability, environmental sustainability, and
economic sustainability.
• Waste elimination
19
5 Project Scheduling: Networks, Duration
Estimation, and Critical Path
5.1 Project Scheduling
Project scheduling requires us to follow some carefully laid-out steps, in order, for the schedule to take shape. P M B o K
states, “an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.”
Project planning, as it relates to the scheduling process, has been defined by the PMBooK as:The identification of the
project objectives and the ordered activity necessary to complete the project including the identification of
resource types and quantities required to carry out each activity or task.
• Predecessors : Those activities that must be completed prior to initiation of a later activity in the network.
• Successors : Activities that cannot be started until previous activities have been completed. These activities follow
predecessor tasks.
• Early start (ES) date: The earliest possible date the uncompleted portions of an activity can start.
• Late start (LS) date: The latest possible date that an activity may begin without delaying a specified milestone.
• Forward pass: Network calculations to determine earliest start/earliest finish for an activity through working forward
through each activity in network.
• Backward pass: Network calculations to determine late start/late finish for uncompleted tasks through working backward
through each activity in network.
• Merge activity: An activity with two or more immediate predecessors.
• Burst activity: An activity with two or more immediate successors.
• Float: The amount of time an activity may be delayed from its early start without delaying the finish of the project.
• Critical path: The path through project network with the longest duration.
• Critical Path Method: A network analysis technique used to determine the amount of schedule flexibility on logical
network paths in project schedule network and to determine minimum project duration.
• Resource-limited schedule: Start and finish dates reflect expected resource availability.
20
5.5 AOA Versus AON
21
5.9 Duration Estimation Methods
• Experience
• Expert opinion
• Mathematical derivation—Beta distribution
– Most likely (m)
– Most pessimistic (b)
– Most optimistic (a)
• Two assumptions used to convert m, a, and b into time estimates (TE) and variances (S 2 ) are :
• Critical path the longest path from end to end which determines the shortest project length
22
Options for Reducing the Critical Path
• Eliminate tasks on the critical path.
• Replan serial paths to be in parallel.
• Overlap sequential tasks.
23
6 Project Scheduling: Lagging, Crashing, and
Activity Networks
6.1 Lags in Precedence Relationships
The logical relationship between the start and finish of one activity and the start and finish of another activity.
Four logical relationships between tasks: Finish to Start , Finish to Finish , Start to Start , Start to Finish
24
6.1.4 Start to Finish Lag
6.3 Crashing
The process of accelerating a project
25
6.3.1 Crash Process
• Determine activity fixed and variable costs
• Networks pose special dangers because contractors may create their own networks.
• Positive bias exists in PER T networks.
26