Lecture8 MMZ SE 2018
Lecture8 MMZ SE 2018
2018
Mona M. Zaki
Lecture #8
15th April 2018
Today
• Velocity
• Burn down charts
• Examples and discussion
• Lab submission
• Practical exam documentation submission
50
40
30
Hours
20
10
0
Mon Tue Wed Thu Fri
15/04/2018 Dr Mona M. Zaki, Computer Science 15
i. The number of stories
The number of items/stories on the Y axis. Problems?
It leads to micromanagement
60
50
40
Hours remaining
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Days in Sprint
Burndown Example 5
Work being performed, but not fast enough
Sprint 1 Burndown
49
48
47
46
Hours remaining
45
44
43
42
41
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Days in Sprint
Burndown Example 6
Work being performed, but too fast!
Sprint 1 Burndown
60
50
40
Hours remaining
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Days in Sprint
Think!
What does a Burndown chart show?
1. Total Estimate
It is the sum of efforts in hours of all the user-stories,
basically it’s the total number of works in hours to
which the team is committed to
2. Amount of work Remaining or Effort Remaining
- This is what burn down shows and this is how this
graph get its name, in literal meaning it is the “effort
burndown chart”
- The Team will burndown some effort each day so that
on last day of sprint or release there is no work effort
remains
What does a Burndown chart show?
3. Working Days
- That is the reason you see a very straight line from the
top of Y-axis to X-axis, which is the last day of your
sprint
What does a Burndown chart show?
5. Real Effort
- Effort remaining line varies from team to team and day
to day