S. 202501basic DesignSpecification
S. 202501basic DesignSpecification
Basic Design
1/2/2025
2 / 46
Index
Chapter 1 - General 4
1.1 Project Name and Undertaking Unit
1.2 Design Basis and Scope
1.3 Main design principles
1.4 Construction scale and product plan
1.5 Production Technology 5
1.6 Main technical and economic indicators
6
Chapter 2 Construction Conditions 8
2.1 Geographical location and transportation conditions of the enterprise
2.2 Raw material and fuel resources
2.3 Power supply and water supply
2.4 Meteorological conditions and earthquakes
3 / 46
Chapter 1 - General
1, The overall design principles of this project are "mature technology, reliable production,
saving investment, improving efficiency, and emphasizing environmental protection".
2, When choosing a production process plan, based on careful investigation and research,
make a good comparison of the plan, and try to use mature and reliable new processes and
technologies as much as possible, achieving both advanced technology, economic rationality,
and practical reliability.
3, Electrical and automation control should consider advanced technology, mature and reliable
equipment and instruments, and their simplicity and applicability.
4 / 46
4, Meet local environmental protection requirements and actively implement the principle of
energy conservation and consumption reduction.
Mg9999 99.99 0.002 0.002 0.0003 0.0003 0.002 0.002 0.0005 0.001 0.002 0.003 ---
Mg9998 99.98 0.002 0.003 0.0005 0.0005 0.004 0.002 0.01 0.001 0.004 0.004 ---
Mg9995A 99.95 0.003 0.006 0.001 0.002 0.008 0.006 --- 0.005 0.005 0.005 0.005
Mg9995B 99.95 0.005 0.015 0.001 0.002 0.015 0.015 --- 0.005 0.005 0.01 0.01
Mg9990 99.90 0.04 0.03 0.001 0.004 0.02 0.03 --- --- --- --- 0.01
Cb, Hg, As, Cr6+ Elements, the client may not perform routine analysis, but their content should be
monitored. Requirements W(Cb+Hg+As+Cr6*)≤0.03%
Based on the raw material analysis report provided by the client, combined with the
production experience of domestic metal magnesium production enterprises in China, this
project adopts the silicon thermal production process. Taking into account the characteristics
of the silicon thermal production process and the actual situation of the factory, the
production line of this project is divided into five parts:
1.5.1 Dolime calcination production system
This project adopts a preheating calcination production system for dolime calcination,
consisting of a six push head preheater, Φ 3× 50m rotary kiln, 3.8 × 3.8 Vertical cooler
composition, with a production capacity of 260-280t dolime per day and a heat consumption
of 1400kcal/kg dolime. The fuel uses natural gas.
1.5.2 Grinding and pressing ball system
5 / 46
The batching of the grinding and pressing ball system is measured using a static weighing scale,
and one grinding machine is used for grinding Φ 2.4 × An 8m ball mill with an hourly output of
18-20 t/h. 3x10tph briquette machines (two in use and one backup) are used for briquette.
1.5.3 Reduction System
The reduction system of this project adopts a vertical tank reduction process using natural gas
as fuel. The reduction system is equipped with 2x144 vertical tank thermal storage reduction
furnaces and a mechanical vacuum system. Reduction furnace usage Φ 630 ×4000mm
reduction tank with a designed magnesium to material ratio of approximately 6.5, with
reduction time of 16-20 hours, and a single tank output of 120kg.
The living facilities include office buildings, dormitories, canteens, and necessary living aids for
bathrooms. The civil design and construction of this project are entirely the responsibility of
the client.
6 / 46
1.6 Main technical and economic indicators
7 / 46
Chapter 2 Construction Conditions
2.2.1 Dolomite
As the dolomite used in the Pidgeon process for magnesium smelting, it should not only
meet the process requirements in terms of chemical composition, but more importantly, in
terms of mineral structure, it should meet the requirements of the smelting process, because
the chemical composition and mineral structure of dolomite have a significant impact on the
various processing of this process.
The chemical composition of dolomite theoretically contains 21.8% MgO, 30.4% CaO, CO2
47.68%, CaO/MgO=1.394 (mass ratio), CaO/MgO=1.0 (molar ratio). The chemical composition
of dolomite used for magnesium smelting by the silicothermic method (Pidgeon method) in
China should meet the following requirements:
The general requirement is that the wear resistance index R1 of dolomite is less than 10%, and
the ash ratio R2 is less than 1.5% . The particle size of raw materials is required to be 20-40mm,
and impurities such as mud and sand should be avoided as much as possible.
The mineral structure requires small grains, polycrystalline, lattice like, and network like
structures, without any specific shape. Its color is light gray, and the ore has high mechanical
strength, hard texture, and is not easy to break. When broken, the powder ratio is small. When
8 / 46
burned at high temperatures, its thermal intensity is high and its thermal cracking is small.
2.2.2 Ferrosilicon
Oman has sufficient local supply of ferrosilicon, and this project is also preparing to build a
ferrosilicon plant, which can meet the needs of this project. The main components of
ferrosilicon should meet the requirements of containing 25% Fe and 75% Si, with a particle size
less than 15mm.
2.2.3 Fluorite
Fluorite, as a co solvent in the reduction process, is added during the briquetting process,
accounting for about 1-3% of the total amount and can be purchased nearby.
This project requires a large amount of electricity, and client is responsible for connecting the
dual circuit power supply from the higher-level step-down station. A main step-down station
and workshop substation are set up in the factory area, with a production voltage level of
11/6.6kV and 0.4kV.
The production and daily water use of this project shall be the responsibility of The Client to
divert water or drill wells at the construction site as the water source for this project.
The factory is equipped with facilities such as reservoirs, circulating water tanks, and water
treatment systems, and the water supply capacity of the water source should meet the needs
of the factory.
9 / 46
▲ Water quality requirements for metal magnesium production lines
Standard code Water quality(mg/L) Remark
GBJ29—90 item Based on CaO Based on CaCO3 Drainage
temperature ℃
Calcium ≤140 ≤250 45
carbonate 168 330 40
hardness 196 350 35
280 500 30
10 / 46
Chapter 3 General Layout
Sohar, Oman
1. Implement the current national standards and requirements for fire prevention, explosion
prevention, safety and health, and environmental protection.
2. Make full use of the site, arrange the overall plan reasonably and compactly, and ensure
smooth traffic organization within the factory.
3. The process flow is smooth and simple, with a reasonable flow direction.
4. Based on natural conditions such as wind direction and terrain, arrange according to local
conditions to ensure that most buildings have a good orientation.
5. Reasonably arrange roads to facilitate transportation within the factory, clearly define
functional areas, and facilitate communication between inside and outside the factory.
Based on the surrounding environment of the factory and the area occupied by the factory,
plan the total production scale of metallic magnesium for the project, with an annual output
of 14280 tons, and reserve a construction site for the second phase.
The main construction content includes: calcination dolime production system; Grinding and
briquetting system; reduction system; The refining workshop, tank making and maintenance
workshop, as well as water, electricity, office, and living service facilities that are compatible
with the project.
The overall layout is based on the transportation route connection conditions of the factory
site, the terrain, topography, engineering geology, and meteorological conditions of the
factory area. It considers the reasonable and smooth process flow, compact connection
between various processes, as well as the ability of living and welfare facilities and mechanical
11 / 46
and electrical maintenance, reducing engineering investment, and considering the
convenience of power supply Gas supply and water supply line design in the factory area.
Based on the above principles and combined with the actual situation, propose the functional
zoning of this design, and strive for a neat appearance and smooth process in the layout of the
production line; The main roads in the factory area run through the factory area, providing
convenient transportation.
According to local meteorological data (annual dominant winds, etc.) and the owner's
requirements, the transportation conditions outside the factory are separated by roads in
each functional area. The overall layout is as follows:
1. office and living service facilities are arranged in the southern part of the entire factory
area, and the designed land area can meet the development requirements of the two
phases of the factory.
2. On the west side of the construction site, a dolomite storage yard, a calcination
production line, a grinding and briquetting workshop, a reduction workshop,
4. The westernmost side is reserved for the use of land for the second phase of the
project.
5. The central control, distribution room, and laboratory are located in the middle of the
two phases of the project.
6. In the middle of the construction site, from north to south, machine repair, reduction
tank workshop, main pressure reduction station, air compressor station (equipped with
air compressor and nitrogen generator), refining workshop, and magnesium ingot
warehouse are set up. And reserve the construction site for the pilot plant.
7. The eastern part of the construction site is a silicon iron production line as required by
the owner, which is not within the scope of this project.
Due to the relatively flat construction site, the vertical layout design plan of the construction
site is as follows:
The workshop of this project adopts a unified elevation of ± 0.00, and the ground rainwater
drainage is done through open ditches along the road from north to south.
According to the process flow and logistics, this project sets up a raw material entrance gate
12 / 46
on the northwest side of the factory area, and an electronic car scale is set up at the entrance
of the gate for the transportation of raw materials into the factory for measurement; A
finished product and waste residue factory gate is set up on the southwest side of the factory
area for transportation of finished products and waste residue.
In the middle of the south side of the factory, a gate is set up to handle the flow of people and
external communication channels.
After the project is put into operation, the entry of various raw materials and spare parts, as
well as the delivery of finished products and waste residue, will be mainly carried out by truck
transportation, which will be jointly undertaken by the company's transportation team and
external transportation vehicles from society.
The design of roads in the factory area is based on the principles of smooth material
transportation, convenient workshop connections, and compliance with fire safety
regulations.
According to the transportation characteristics of raw materials and finished products, the
circular roads or main roads in the factory lead to major production workshops and raw
materials, as well as the gathering points of finished products. The roads in the factory area
are all paved with concrete, and the main roads are urban lanes.
The internal transportation of production mainly involves the secondary transportation of raw
materials and fuels, stacking and storage, as well as the transportation of other materials for
production services. The Client will provide supporting loaders and forklifts as needed.
The greening of the factory area is set up by The Client in accordance with local regulations,
and this design is not discussed in detail.
13 / 46
Chapter 4 Production Process
Note:
1. Using magnesium metal as the calculation benchmark;
2. The production line operates for 330 days annually (with an annual operating rate of 90%);
3. The calorific value of natural gas is calculated at 8500Kcal/m ³ calculate
4. The total amount of dolomite is calculated based on 5% of the particle size being
unqualified
14 / 46
Dolomite
elevator cooler
Finished Mg stockyard
While ensuring reliable equipment operation, product quality, and environmental protection
standards, priority is given to the selection of imported technology and local manufactured
high-efficiency energy-saving equipment.
The calcination production system uses dolomite as raw material and produces magnesium
oxide through calcination. The calcination of dolomite is actually the heating and
decomposition of dolomite. Dolomite is a composite of CaCO3 and MgCO3. The basic reaction
of dolomite calcination, which is the heating decomposition reaction of carbonate, is an
extremely important process in the entire production process of metallic magnesium.
This project adopts a preheating calcination production system for dolime calcination,
consisting of a six push head preheater, Φ 3× 50m rotary kiln, 3.8 × 3.8 Vertical cooler
composition, with a production capacity of 260-280t calcined dolime per day and a heat
consumption of 1400kcal/kg calcined dolime. The fuel uses natural gas.
After sieving, the dolomite with a particle size of 20-40mm is transported from the mine to the
factory area and stacked in the material yard. The dolomite passes through the hopper and is
fed into the belt conveyor by a vibrating feeder under the hopper. The belt conveyor is then
fed into the screening frame. A vibrating screen is installed at the top of the frame to screen
out particles smaller than 20mm generated during transportation and stacking. The dolomite
with a particle size of 20-40mm is sent to the kiln tail preheater through a belt conveyor.
Dolomite feeding, the dust generated during the screening process is treated by two pulse bag
dust collectors. The dust collected by the bag dust collectors and particles smaller than 15mm
after screening enter the screening material bin.
16 / 46
4.2.1.2 Calcination of dolomite
The materials are introduced into the preheater body through the feeding chute from the top
silo of the preheater. At the same time, the high-temperature flue gas introduced by the
rotary kiln exchanges heat with the materials, preheating them to around 900 ℃ to partially
decompose the dolomite. Then, 6 hydraulic push rods are sequentially pushed the material
into the tail of the rotary kiln, and after 1250℃~1300℃ high-temperature calcination in the
rotary kiln; they are unloaded into the vertical cooler.
Cold air is blown in by the fan, and cool the material to an ambient temperature
below+100-150 ℃. The air blown in by the vertical cooler enters the rotary kiln as secondary
air to participate in combustion, because the secondary air passing through the vertical cooler
is preheated to around 600 ℃, which can effectively increase the firing temperature inside the
kiln and reduce fuel consumption.
The cooled lime is discharged by a closed electric vibrator at the bottom of the vertical cooler,
and then transported to the finished lime conveying and storage system through a chain
conveyor. A pulse bag filter is installed on one side of the kiln hood and cooler to remove dust
from the cooler and discharge point.
The main function of the vertical preheater is to deliver the dolomite material sent from the
upper part to the preheater body, and at the same time, use the waste gas (850-1000 ℃)
discharged after calcination in the rotary kiln to evenly preheat the material in the preheater
to -900 ℃, and then push it into the rotary kiln by hydraulic push rod for calcination.
This calcination process not only greatly shortens the calcination time of dolomite in the kiln,
but also achieves high activity of calcination. The structure of a vertical preheater, in addition
to electrical control, mainly consists of four parts:
1. The first is the upper feeding system, which mainly includes the upper material bin,
feeding pipe, feeding method and structure to ensure complete sealing when feeding
into the preheater body. This way, cold air from the outside cannot enter the
preheater, and the feeding can be achieved continuously or intermittently through a
rod valve.
2. The second is the main body of the preheater, which is the most important part to
ensure that the materials are preheated to around 900 ℃. It is composed of the
preheater cylinder, material distribution arch, suspension device, and refractory brick
lining. The structure of this section is mostly made of metal components, and some
materials are selected as heat-resistant steel according to needs. The heat-resistant
steel can work at high temperatures of 1000-1100 ℃. In addition, the design of the
refractory brick lining structure is novel, which can ensure that the material is
17 / 46
uniformly preheated in the preheater and reaches the preheating temperature.
3. The third is the hydraulic push rod device, which mainly includes push rods, frames,
and connecting rods. The push rods are made of heat-resistant steel castings and can
withstand high temperatures. With the help of electronic control and hydraulic
systems, the 6 hydraulic push rods can achieve automatic control program sequential
feeding.
4. The fourth is the framework, which mainly includes columns, ring beams, etc., and its
main function is to support the upper structure of the preheater.
Dolomite is uniformly preheated to around 900 ℃ in the preheater by the kiln tail gas at
850-1000 ℃. The exhaust gas is collected through the six exhaust holes on the upper part of
the preheater and enters the kiln tail gas treatment system.
The partially decomposed dolomite is pushed into the feeding chamber by the hydraulic push
rod on the preheater. The feeding chamber mainly includes a chute, the main body of the
feeding chamber, the feeding vessel, etc. Its main function is to guide the preheated material
into the rotary kiln for calcination.
After calcination, the calcined dolime material enters the single barrel cooling machine for
cooling through the kiln discharge device, cooling the calcination temperature from about
1150 ℃ to below the ambient temperature of 100-150 ℃.
The high-temperature flue gas generated by the combustion of the rotary kiln undergoes heat
exchange with dolomite in the preheater, and the temperature drops below 260 ℃. After
passing through a cyclone dust collector, the flue gas temperature further decreases, and then
enters a bag filter.
After dust removal, it is discharged into the atmosphere through a high-temperature fan, and
the dust concentration discharged into the atmosphere is less than 50mg/Nm3, which meets
local emission standards.
The kiln tail dust collector adopts the advanced long bag low-pressure pulse dust collector in
China, which has the advantages of large processing capacity, high dust removal efficiency,
and wide range of use. The dust collector type of this project has a processing air volume of
130.000 m3/h, a filtering area of 2.880 square meters. There is a steel chimney behind each
dust collector.
Due to the temperature of dolomite reaching~900 ℃ in the preheater, magnesium oxide and
calcium oxide have been generated on the surface, which can fully react with sulfur dioxide in
18 / 46
the flue gas, and the desulfurization efficiency can reach over 90%.
The reduction reaction of metallic magnesium belongs to solid-phase reaction, which takes
place on the surface between the reducing agent and the calcined particles. The quality of the
contact between the materials determines the reduction reaction rate of magnesium oxide.
Therefore, after the calcination, reducing agent ferrosilicon, and mineralizing agent fluorite
are mixed and ground finely, they indirectly contact each other well through briquetting,
which is conducive to the progress of the reduction reaction process.
Due to the absorption of moisture in the air during storage, the reduction reaction rate of
magnesium oxide is reduced. Therefore, the selection of the grinding system must be designed
according to its characteristics. In this project, one grinding system is used ф 2.4 × 8m open
circuit ball mill, equipped with advanced static scale batching, metering, and dust collection
system using pulse dust collector.
The production capacity of this system is 15-18t/h, with advantages such as simple operation,
accurate batching and measurement, and lower exhaust gas emissions than national
standards.
After the ferrosilicon with a diameter of less than 15mm enters the factory, it is fed into a
ground pit, an electric vibrator, and a hoist Φ 6×18m ferrosilicon bin is used for storage, and
the bottom of the ferrosilicon bin is measured using a suspended belt weight loss scale.
At present, all magnesium metal production enterprises use fluorite powder as the
mineralizing agent for the reduction system. This project adopts Φ4. 5×6m steel bin serves as
the fluorite batching warehouse, and the bottom of the bin is measured using a suspended
belt weight loss scale.
Calcined dolime, ferrosilicon, and fluorite are all measured using weight loss scales, and the
automatic batching system measures accurately, which can be quickly adjusted according to
the material composition to ensure the magnesium yield of the reduction system. The
19 / 46
measured material is conveyed by a belt conveyor to a ball mill for grinding.
The measured material enters the ball mill for grinding, and the mixed material with qualified
fineness is discharged through the grinding tail and sent to the mixing bin for use by the
briquetting system.
Bag dust collectors are installed at each dust collection point of the grinding system to
improve the operating environment in the workshop and reduce the losses caused by material
dust. The collected dust enters the mixing silo, and there is no waste discharge in this system.
3xLYQ10 high-pressure roller briquette machines (two in use and one backup) are selected for
this project's briquette equipment, with a maximum system output of 20 t/h. The process flow
is as follows:
• the powder produced by the mill is fed into the mixing bin through the conveying
equipment,
• the materials in the bin are sent to the pre pressing bin of the briquette machine
through the chain conveyor.
• After being compressed by the briquette machine on the rollers, they are compressed
into 2.54 × 3.81×7.62cm walnut shaped pellets are loaded into the feeding ball cart,
• they are sent to the reduction workshop through the track.
The exhaust gas generated by the briquetting system is treated by the dust collector and
discharged. The fragments generated during the briquetting process are transported by the
conveying equipment to the mixing bin for re pressing.
The grinding system is equipped with a PPS64-5 gas box pulse bag dust collector, with a
processing air volume of 17,800m3/h, a filtering area of 256 ㎡, and a filtering wind speed of
1.2m/min.
The briquetting is equipped with one PPS64-5 gas box pulse bag dust collector, with a
processing air volume of 22,300m3/h, a filtering area of 320 ㎡, and a filtering wind speed of
1.2m/min.
The reduction system consists of a vacuum section, a reduction section, and a heating section,
forming an organic whole that should meet the following requirements:
(1) Due to the boiling point temperature of magnesium being 1107 ℃, the reduction process
20 / 46
temperature is generally controlled between 1180-1200 ℃. The heating part should be able to
provide and reach the required temperature.
(2) Due to the fact that the reduction reaction should be carried out under vacuum conditions
of 1.33~10Pa, the reduction tank must be able to withstand various pressures up to an
atmospheric pressure at a temperature of 1200 ℃ or higher.
(3) The vacuum unit can discharge the gas in the system within the time required for loading
and closing the reduction tank, achieving a residual pressure of 13.33Pa.
This project adopts a thermal storage reduction furnace. The thermal storage reduction
furnace overcomes the shortcomings of traditional metal magnesium reduction furnaces, such
as low combustion efficiency, serious heat waste, uneven temperature inside the furnace,
difficult temperature control, and serious pollution.
The characteristic of a heat storage reduction furnace is that the heat storage chamber is filled
with a heat storage body. Set up a conversion system outside the furnace. The furnace body is
constructed in layers using various refractory materials. The reversing system, fan, and heat
storage chamber are connected by pipelines. The reversing system controls the flow of air and
gas. Valves are installed on the pipeline to control its flow rate. A temperature measurement
hole is installed at the top of the reduction furnace to maintain the surface temperature of the
reduction tank at 1180-1200 ℃.
The preheated air and gas undergo intense combustion, generating a large amount of heat.
The tank body of the reduction tank is heated, and the smoke generated by combustion enters
the right heat storage chamber group through the right burner nozzle. At this point, the heat
storage chamber on the right is in a heat absorbing state. When the flue gas passes through, a
large amount of heat carried by the flue gas is absorbed by the heat storage body in the right
21 / 46
heat storage chamber, and then discharged from the chimney to the outside of the furnace
through the pipeline and reversing system.
After a turning cycle, the original heat storage chamber group releases heat, while the original
heat storage chamber group absorbs heat. At this point, the reversing system operates,
changing the path of air and gas entering the furnace. The direction of gas and air entering is
opposite to the original direction of entry. Repeat the combustion process described above
and repeat it over and over again.
After this combustion process, the flue gas temperature significantly decreases, dropping from
around 1200 ℃ in traditional combustion methods to below 150 ℃, effectively utilizing
energy and reducing losses. Effectively controlling the flow of gas and air can effectively
control the temperature inside the furnace, avoid large temperature fluctuations in the
furnace, and improve the service life of the reduction tank. Ensure that the temperature inside
the furnace fluctuates only slightly around the optimal reduction temperature, thereby
improving the yield and quality of magnesium metal.
This project adopts two 144 tanks metal magnesium reduction furnaces, with magnesium
discharged from the top and slag discharged from the bottom of the reduction tanks. The
reduction time is 16-20 hours.
1) System characteristics
This system adopts a programmable controller to form a practical and reliable automatic
control system.
23 / 46
temperature is generally set at 150-200 ℃, with timed directional control as
the main method and constant temperature directional control as the
auxiliary method to control the smoke exhaust temperature.
The reduction tank used in this project adopts Ф 630 × 4000mm vertical reduction tank with
central cylinder diameter Ф 273mm, using the process of upper magnesium discharge and
lower slag discharge, the crude magnesium output of a single tank is 120kg. The annual output
of two reduction furnaces is calculated as:
(330× 24/19.1613) × (120x144 × 2/1000)=413.3333 × 34.56= 14284.8 tons/year
The task of a vacuum unit should first ensure that a large amount of gas is extracted under
normal pressure at the beginning of the reduction cycle, and secondly, maintain a
considerable extraction speed throughout the entire reduction process to achieve a vacuum
degree below -5Pa. This project adopts the J2ZH2800 series mechanical vacuum unit, which is
composed of
a through type vacuum valve,
• vacuum relay,
• Roots vacuum pump,
• metal corrugated pipe,
• clamp type butterfly valve,
24 / 46
• electromagnetic relief valve,
• and slide valve vacuum pump.
Each reduction furnace is equipped with 28 sets of mechanical vacuum units as backup to
ensure the normal use of the reduction system.
This production line is used as equipment set for one-step production of magnesium ingots
and magnesium alloy ingots by adding auxiliary materials from raw magnesium. The
equipment consists of:
• thermal storage melting furnace,
• insulation pouring furnace,
• intelligent control system,
• ingot casting machine,
• and other auxiliary equipment.
The system adopts intelligent control, with a high degree of automation and saves labor. The
control system adopts computer intelligent control, and after the entire set of equipment is
put into operation, it can achieve an annual production capacity of 14,000 tons of magnesium
ingots.
1. Adopting a layout of 1sets, 4 in2, with 4 magnesium thermal storage melting furnaces
and a capacity of 3.5 tons;
2. one set of resistance type magnesium alloy insulation furnaces with a capacity of 3.0t;
3. One flux furnace and one recovery furnace each, with a capacity of 1.5 ton of flux, used
for cleaning preheating transfer pumps and casting pumps;
4, One set of 96 molds magnesium alloy ingot casting machines, automatic quantitative
casting of magnesium ingots, capable of producing 7.5Kg-12kg of various specifications of
magnesium ingots and magnesium alloy ingots;
5. One set of environmentally friendly desulfurization and dust removal systems, meeting
the requirements for dust removal, purification, and environmental emissions of
magnesium ingot refining production line;
The 3T thermal storage gas refining furnace adopts an air single thermal storage type with 4
pairs of energy-saving thermal storage burners, while the solvent furnace (or recovery furnace)
adopts an air single thermal storage type with 2 pairs of burners;
1) Each refining furnace adopts one pneumatic four-way directional valve, while solvent
furnace and recovery furnace use two four-way directional valves
Valves (i.e. 6 sets of two position four ventilation directional valves);
2) Each furnace is equipped with an independent exhaust gas induced draft fan and one
air blower;
3) The air, exhaust gas, and natural gas pipelines, as well as their corresponding pipe
supports, enter the main flue (exhaust temperature 150-180 ℃) after passing through the
induced draft fan for each furnace's exhaust gas, it enters the desulfurization tower and is
finally discharged through the chimney ;
4) Adopting air thermal storage combustion, PLC automatic directional control system and
temperature automatic detection;
6) The gas automatic reversing adopts an electrically controlled quick cut valve;
7) Each furnace is equipped with an ignition nozzle and a control room button for ignition.
The nozzle comes with flame detection, which automatically cuts off the gas supply if the
ignition is unsuccessful or extinguished, ensuring high safety;
8) Each refining furnace (including solvent furnace and recovery furnace) is equipped with
smoke exhaust thermocouples and various smoke exhaust temperature patrol
inspections;
9) Each refining furnace (including solvent furnace and recovery furnace) is equipped with
one temperature (furnace temperature) thermocouple;
10) Set parameters in the electrical control room for easy operation.
26 / 46
5 Furnace temperature ℃ 900--1000
6 Fuel type NG
7 Low heating value of fuel Kcal/Nm3 LHV~8500
8 Maximum fuel consumption Nm3/h ~120
9 Maximum air consumption Nm3/h ~1260
10 Burning method Air thermal storage combustion
11 Heating method Side heating
12 Air preheating temperature ℃ ≥900
13 Smoke exhaust temperature ℃ ~150
14 Reversing method Two position four-way directional valve
15 control mode PLC control
16 Crucible size mm Ø 1200×2050
17 Single furnace melting Cap. 3.5t Magnesium liquid
Smoke exhaust method Thermal storage positive pressure+ forced
18
smoke exhaust with induced draft fan
The heat storage refining furnace is a circular chamber heating furnace with a working
temperature of 900-1000 ℃. This scheme uses natural gas as fuel and adopts a preheated
high-temperature air heat storage combustion with air single heat storage. The burners are
symmetrically arranged. The advantages of thermal storage refining furnaces are mainly
manifested as:
2.1. Adopting efficient extreme heat recovery technology, the air is preheated to 900 ℃.
The use of thermal storage combustion technology can utilize the waste heat of flue gas to
almost the limit, recover the latent heat of flue gas to the maximum extent, and preheat
both air and gas to a temperature close to the furnace gas. The exhaust gas temperature
can be lower than 120 ℃, greatly improving the waste heat recovery rate and significantly
reducing energy consumption;
2.2 The temperature inside the furnace is uniform, with no local high temperature points
and low oxidation burn loss. The combustion under high-temperature and oxygen poor
conditions produces a uniform high-temperature reaction, forming diffuse combustion
products that can evenly fill the entire combustion space, making the furnace temperature
uniform. This can improve the product quality of the furnace, extend the furnace life, and
greatly improve the service life of the refining pot, reducing the cost of magnesium alloy
refining (melting process);
2.3 Compared to the current general magnesium metal refining furnace, it can save more
27 / 46
than 30% of energy, enhance heat transfer, and increase production. Flame stability is
different from traditional diffusion flames. Under high temperature (higher than the self
ignition temperature of the fuel) preheating air conditions, as long as the fuel diffuses,
mixes, and enters the combustible range (the combustible range is greatly expanded),
combustion will occur spontaneously without the need for a flame stabilization
mechanism, thus ensuring stable combustion.;
2.4 Adopting a PLC with reliable performance for reversing and combustion systems;
Adopting flexible and protective control methods; PID automatic temperature control,
improving melting speed and settling time;
Reducing the emissions of harmful gases such as NOx and CO by
2.5 can significantly improve the on-site production environment. In order to reduce NOx
emissions during high-temperature combustion, regenerative combustion and waste heat
recovery technologies use the method of reducing the concentration of oxygen in the
combustion space to create conditions for lean oxygen combustion. Reduce environmental
pollution. The regenerative combustion technology not only saves energy and reduces
smoke emissions, but also greatly reduces the content of harmful gases such as NOx in the
smoke, reducing environmental pollution.
The reduction tank in the reduction furnace is a vulnerable component with high annual
consumption. A can making and maintenance workshop is specially set up for the production
and maintenance of the reduction tank, as well as the maintenance and use of other
equipment.
1. Calculation of can production capacity:
The service life of the reduction tank is 60 days, with an annual working time of 330
days. The total number of reduction tanks is 288, and the calculated annual usage of
reduction tanks is 1584;
The production capacity of the can making workshop is calculated at 1.2 times, with a
production capacity of 1900 units per year;
The size of the straight section blank of the reduction tank is Φ 630X50X4040, can
weight 2890kg; The weight of the cone end blank is 220kg, and the splashing during
the casting process is considered at 3%, resulting in a total weight of 3203kg of molten
iron;
Therefore, a capacity of 3.5 tons of electric furnace is selected, and considering the
heating time of the electric furnace, 2x 3.5 ton electric furnaces are selected,
including one for heating and one for insulation, using one set of power supply. Ability
to achieve 1 tank per hour.
3. Energy consumption
• The total installed capacity of the can making and maintenance workshop is
3600KW, including 3200KW for high voltage (11/6.6kV) and 400kW for low
voltage (400V);
29 / 46
• Compressed air: 5 m3/min
• Water: 0.1 liters/hour
• Argon gas: 40 liters/1000 spectral analysis
Add waste stainless steel materials or new heat-resistant steel ingredients to the medium
frequency furnace for smelting, start feeding and add lime, fluorite and scrap steel at the
bottom of the furnace, then add the recycled materials to start the medium frequency furnace.
During the melting process, carefully observe the current, voltage and water path, and tamp
and add materials to aid melting. Gradually add slag forming materials.
After the recycled materials are melted, the temperature of molten steel rises to 1480 ℃
-1520 ℃, and then extract slag for sampling, and make new slag and adjust the slag to foam
slag, After the pre furnace sample is produced, materials such as Cr and Ni will be added based
on the analysis results. The indicators reach around Cr ≥ 25, Ni ≥ 7-8.5, Si: 1.6-1.7, Mn: 0.65-0.8,
N: 0.2-0.3, S: 0.04, P: 0.04. After the supplementary material is melted, start adding silicon
calcium for deoxygenation, with a deoxygenation time of 8-10 minutes; Until the shrinkage
sample shows small shrinkage pores, when the temperature rises to 1560 ℃ -1580 ℃, treat
the slag and add 1.5-2kg of rare earth to adjust the slag to a thin level.
Lift the intermediate frequency furnace top through the hydraulic system and pour the molten
steel into the ladle; And lift it to the fixed position of the centrifugal casting system; By using a
high-speed roller centrifuge and utilizing good centrifugal force, it can be cast at a certain
number of revolutions φ 630 × 4000mm magnesium reduction tank.
3. Composition standard for molten steel, (for reference only, subject to final actual
requirements):
30 / 46
content Cr Ni Si Mn N C S P Fea
standard ≥25 ≥7-8.5 1.6-1.7 0.65-0.8 0.23-0.27 <0.38 <0.04 <0.04 residue
B. Centrifuge composition:
The equipment mainly consists of a host, pouring components, a winch, sand delivery and
discharge pipe components, an electrical control system, and so on.
1. The host mainly includes: supporting wheel group, large floor, middle bottom plate,
supporting wheel seat, and host protective cover.
2. The pouring components include: a chute car and a set of car guide rails.
3. The sand delivery and pipe components include: the body of the sand delivery and pipe
delivery car, the sand delivery pipe, the sand delivery support wheel, the takeover support
wheel, and the horizontal track of the car.
4. Electrical control cabinet -1 set
31 / 46
1. Host
The main engine rotation is driven by a 110KW variable frequency speed regulation motor
combined with a frequency converter, which can achieve low-speed start and high-speed
constant rotation. Different proportions of pulleys can enable the maximum rotation
speed of the large pipe mold to reach 700rpm.
The combination of independent driving and driven wheels makes the adjustment of the
main engine faster and more convenient, and the weight of the pipe mold overcomes the
stall caused by the rotation of the pipe mold.
2. Chute car
The walking design of the chute car is manual.
5. Lubrication system
The main engine support wheel seat is equipped with a lubrication system, and the top is
equipped with an oil filling port. Lubricating fluid is added once per shift. Check and add
gear oil to each gearbox every three months.
In addition to electric furnaces and centrifuges, the can making and maintenance workshop is
also equipped with auxiliary equipment such as processing and metering,
1. Casting metal molds for casting the lower cone end of vertical tanks;
Using metal molds, painting, and hand casting to form.
3. The airtight testing machine is used to detect the welding effect of the weld seam
• Diameter of pressure test piece: 630mm
• Test piece length: 4500mm
• Pressure test: 0.12MPa
5. Spectral analyzer is used for rapid analysis of the composition of molten iron;
• Mainly for rapid analysis of elements such as Cr, Ni, Si, Mn, N, S, P, etc;
• Model: CCD 6500
7. Lifting equipment
7.1 Metallurgical crane, used for lifting iron ladle and pipe mold.
• Model: QDY16/3.2-12
• Lifting capacity: 16t
• Lifting height: 12m
• Span: determined based on detailed design
• Work system: A7
• Total motor power: 54kw;
7.2 electric single beam crane, used for lifting ordinary parts.
• Lifting weight: 10t
• Lifting height: 12m
33 / 46
• Work system: A5
• Total motor power: 9kw;
8. Welding equipment
Used for welding the conical end of the reduction tank, using manual welding method;
• Equipment selection: ZX7-500 Quantity: 2 units
• The technical parameters are as follows:
• Rated input voltage: AC380
• Rated input capacity: 25KVA
• No load voltage: 75V
• Input current regulation: 20-500A
• Rated working voltage: 40V
• Thrust adjustment: 0-100A
• Load duration: 60%
• Efficiency: 85%
• Power factor: 0.93
• Net weight: 18.6kg
• External dimensions: 530mmX270mmX465mm
9. Transportation equipment
The cross span transportation equipment adopts electric flatbed trucks with a rated load
capacity of 15 tons and a quantity of 1 unit. The specific parameters are as follows:
No. Parameter Name Parameter values Unit
The vibrating screen screening machine is driven by dual vibration motors. The motion
trajectory of the screening machine is a straight line. The two motor axes have an inclination
angle in the vertical direction relative to the screen surface. Under the combined force of
excitation force and material self gravity, the material is thrown up and jumps or moves
forward in a straight line on the screen surface, thereby achieving the purpose of screening
and grading the material. Suitable for screening various dry powder or granular materials with
a particle size of 0.074-5mm, a moisture content of less than 7%, and no viscosity.
The particle size of the large feed shall not exceed 10mm. This product has high screening
accuracy, large processing capacity, simple structure, low energy consumption, low noise, long
service life of the screen, good sealing, no dust overflow, and convenient maintenance.
The DZSF520 small feed vibrating screening machine is a small and medium-sized model of
feed vibrating screening equipment. The equipment is 500mm wide, 2000mm long, and has a
motor power of 1kw; The characteristics of high screening accuracy, large processing capacity,
and simple structure.
35 / 46
Chapter 6 - Electrical and Automation
This project is an annual production line of 14200 tons of magnesium, which includes
transformer and distribution, workshop power, electrical control and lighting, lightning
protection, grounding, etc., from raw materials entering the factory to finished product
packaging leaving the factory. The electrical design is based on the conditions provided by the
process and other specialties, as well as the relevant electrical data provided by the factory.
The incoming voltage of the 11kV main step-down station is 11kV. After the dual circuit power
supply line enters the factory, a 11kV main step-down station is planned to be built in the
middle of the factory area. After the voltage is reduced, it will supply power to various
electrical rooms and high-voltage motors in a 6.6kV radial manner, while reserving power
distribution for the second phase of the project. The power consumption of low-voltage
electrical appliances is planned to be supplied by transformers installed in each electrical room
after voltage reduction.
2. Technical indicators
a. Production system installed capacity: 12,000 kW
• Among them: High voltage motor: 1,810kW
• Low voltage motor: 10,190kW
b. Natural power factor: 0.7
c. Power factor after compensation: 0.95
3. Electrical measurement
Install corresponding measuring devices in each electrical room according to the specifications,
such as kilowatt hour meters, voltmeters, ammeters, power factor meters, etc., to monitor the
load changes of the entire plant and each electrical room.
The factory area supplies power to each electrical room in a 6.6kV radial manner, and the
low-voltage electrical equipment in the workshop is supplied by each electrical room in a
combination of 400V, 660V radial and chain forms.
According to the production process characteristics of each process, the control system of the
entire factory can be divided into calcination production control system, grinding ball control
system, magnesium reduction control system, refined magnesium processing control system,
can maintenance workshop and its auxiliary facilities control system (including air compressor
station control system and water circulation control system), each system is independent and
coordinated with each other. To control the entire production line. The entire factory is
equipped with a central control room, and the operation stations in the central control room
complete the sequential logic control of process equipment and the detection, adjustment,
38 / 46
and alarm of process parameters through the on-site control station.
There are five on-site control stations, five operation stations, and one programming station in
the entire factory. The high-speed data network uses fiber optic cables to form industrial
Ethernet. The can making maintenance workshop does not enter the DCS system
The on-site control station is located in the calcination production electrical room (central
control room), with control scope covering calcination screening and transportation, batching,
preheating, kiln system calcination, waste gas treatment, cooling transportation and storage.
The on-site control station is located in the electrical room of the grinding and pressing ball
workshop, and controls the batching and conveying of grinding and pressing balls into balls
according to process requirements.
The on-site control station is located in the electrical room of the reduction workshop and
completes the following tasks according to the process requirements: temperature closed-loop
control of the reduction furnace, vacuum closed-loop control, furnace front display, and alarm
control.
The on-site control station is located in the electrical room of the refining workshop to
complete the processing of magnesium ingots.
The on-site control station is located in the electrical room of the water pump room to
complete the control of the Utility system.
The on-site control station is located in the can making and maintenance workshop, mainly
responsible for centrifugal casting of reduction tanks and equipment maintenance.
The operation station is located in each electrical room and central control room. There are
five operation stations and one programming station in the entire factory, which correspond to
1) Quality control system for ingredients: In order to ensure the quality of calcination and
the balance and stability of the pressure ball, high-precision static metering batching
scales and corresponding QCS quality control systems are selected to optimize the control
of material accuracy and quality. The system includes ingredient metering equipment,
40 / 46
speed control feeding equipment, computer, external equipment, and corresponding
software.
2) A CO gas analysis device is installed at the inlet of the kiln tail dust collection, and a CO
and 02 analysis device is installed at the outlet of the secondary cylinder. The system
includes gas sampling probes, pre-treatment cabinets, analysis devices, etc.
Install a complete computer monitoring system in the management office, which is connected
to the entire plant DCS system through communication. It can help management personnel to
command production in a timely and accurate manner.
Management personnel can also use this system to understand various information about the
current and process production of the entire factory, such as querying the storage and
consumption of raw materials, equipment operation status, recent production and quality
status, etc.
1) The temperature instrument adopts armored Pt100 thermistor and armored K-type
thermocouple.
2) Select imported or imported products for pressure, differential pressure, and flow
transmitters.
3) The level detection instrument can be selected according to different purposes, using
either a heavy hammer level gauge or a resistance rotation level gauge.
1) The connection wires and DC signal wires between the transmitter and various on-site
stations for a single detection component are all made of KVVP type multi core shielded
copper core cables with sheaths. KVV copper core cables are selected for communication
and switching signals. Thermocouples are equipped with high-temperature compensating
wires with shielding and sheathing.
2) The connecting cables and wires between various equipment in the DCS system are
41 / 46
supplied as a complete set with the equipment.
The cables between the primary components and the on-site station are buried in pipes or laid
along cable trays. The cables inside the control room are laid under raised indoor floors, and
the main communication cables are laid in outdoor cable trays.
Install an instrument repair room in the central control room to complete daily maintenance
and repair of instruments and computer systems.
The Utility system of this project mainly includes the following systems:
(1) Circulating water system
(2) Fire protection system
(3) Compressed air system
(4) Nitrogen system
Due to the construction site of this project being in Oman, the fire protection system is
designed and constructed by The Client uniformly, and will not be described in detail here.
Other systems, as they involve production, are detailed below.
42 / 46
7.2 Circulating water system
43 / 46
7.2.3 Domestic water consumption
The project has a staff of 280 people, including 260 production workers and 20 laboratory
workers.
According to the labor quota water volume standard, it is 50L/person/day, and the daily living
water volume is 14m3; The water consumption of public bathrooms is 20 L/person · day, and
the daily water consumption of bathrooms is 5.6m3. According to the above, the total
domestic water consumption of this project is 19.6 m3.
Calculated based on 10% of the total water consumption, the water consumption is
(19.6+120.97) × 10%=14.06m3/d.
According to the above calculation, the total daily water consumption of this project is
120.97+19.6+14.06=168.69m3/d. (Due to the correlation between evaporation and
surrounding temperature environment, generally considering 0.4-1%)
The fire resistance rating of the factory building is Level 2, and the fire hazard is Class C. The
number of fires in the factory area at the same time is calculated as one. According to the
"Code for Fire Protection Design of Buildings" GB50016-2006, the indoor fire water
consumption is 15L/s, the outdoor fire water consumption is 25L/s, the fire duration is 2 hours,
and the total fire water consumption is 288 m3. A fire water tank and pump room are set up in
the factory area. And two fire water pumps will be installed in the pump room, one for use and
one for backup.
According to the layout of the overall process plan and the distribution of various water
consumption points, a circulating water tank and a water pump room are set up in the middle
of the production area in this project, radiating to each water consumption point through
pipelines.
Two fire water pumps with a flow rate greater than 180 m³/h are installed in the water pump
room. Variable frequency speed regulation and head guarantee the water pressure of all
fire-fighting facilities. Seven circulating water pumps are installed, of which five (four in use
and one as backup) have a flow rate of 300 m³/h. Dedicated for use in the restoration
44 / 46
workshop, two units (one for use and one for backup) with a flow rate of 100m³/h. For use by
other water points. At the same time, dosing facilities, electrical rooms, and duty rooms are set
up in the circulating pump room.
The water tank adopts a semi underground structure, with a storage capacity of 300m³ for the
fire water tank. The water demand of the circulating water tank is greater than 1000m ³。 A
cooling tower is installed on the upper part of the circulating water tank to cool down the
circulating water.
Central control, laboratory and other auxiliary facilities room the indoor water supply pipe
adopts PP-R pipe with hot melt connection; The outdoor water supply pipeline and production
workshop adopts steel water supply pipes with socket connections.
Compressed air is mainly used for backflushing of dust collectors and various pneumatic valves.
According to the operation of the process equipment at full load, the total gas consumption is
49.6m3/min, and the gas pressure is 0.5-0.7MPa.
This new construction project requires the construction of a new air compression station,
where compressed air is sent to various gas consumption points through a micro heat
adsorption dryer, two-stage oil removal, water removal filter, and pipeline for use.
There are three 50m3/min screw air compressors and one 15m3/min nitrogen generator
installed in the air compression station, with one air compressor used at each gas consumption
point on the production line of this project; One air compressor is used for nitrogen production,
and one air compressor is standby. The nitrogen generator is equipped with a 20m3 nitrogen
45 / 46
storage tank for safety protection of natural gas pipelines and use in refining workshops.
If the owner's 44m3/min compressor can be matched with a 15m3/min nitrogen generator, it
can be replaced accordingly.
7.4 Laboratory
A central laboratory is set up in the factory area, responsible for routine chemical analysis of
incoming and outgoing raw materials, fuels, semi-finished products, and finished products, to
ensure the quality of products in all production processes of the factory, and to schedule,
manage, and supervise the quality of lime products.
Considering the impact of long-distance transportation and policies, the laboratory equipment
for this project only provides the following equipment. Other reagents and containers will be
purchased locally by the client:
Unified experimental small mill SM05 500×500mm set 1
Computer sulfur analyzer 5E-8S,CLS-3000 set 1
Multifunctional heat meter CT7000,5E-1AC,FRL-3000 set 1
Stainless steel electric distilled
20L/H set 1
water heater
High temperature box type
SX2-4-10 set 2
resistance furnace
Electric blast drying oven 101C 450×550×550mm set 2
Electronic balance 200g d:0.1mg set 2
Fiberglass fume hood SZB-3 set 2
Crusher FJ-100 set 1
Gimbal balance JP-A 1000g set 2
Adjustable universal electric
KD-1 set 1
furnace
Drug cabinet 1200×400×180mm pcs 4
Platform scale 10kg, division 50g set 1
Thermostatic magnetic mixer 78HW-1 set 1
Timed electric mixer JJ-1 set 1
Water sieve 125×80mm, aperture0.08mm set 1
46 / 46