Module 4
Module 4
1
Risk Management Process
2
Risk Management Process Management Elements
SCOPE
• program to achieve Organisational
Objectives
• Governance, policy and processes
CONTEXT
• Organisational operating environment
• Organizational operations and
management
• Impact on stakeholders Scope, Context, Criteria
CRITERIA
• Determination of risk acceptance and
tolerance
Risk Assessment
Risk Treatment
Recording & Reporting
• Records Policy
• Records management system Recording & Reporting
• Access to documentation
• Reporting Channels
Risk Management Assessment and Treatment Process Elements
RISK TREATMENT
Specific selection criteria
• Physical Controls Risk Treatment
• Personal Controls
• Information Management Controls
• Work History and performance Recording and Reporting
• Cyber Controls
• Review and Improvement Processes
Identify Sources of Risk
▪ Personnel/human behavior.
▪ Management activities and controls.
▪ Economic circumstances.
▪ Natural events.
▪ Political circumstances.
▪ Technology/technical issues.
▪ Commercial and legal relationships.
▪ The activity itself.
6
Risk Identification
▪ A risk that is not identified at this stage will not be included in further
analysis
7
Example
8
Risk Analysis
9
Risk Evaluation
10
Risk Criteria
11
Example :Level of Risk
▪ Magnitude of a risk or combination of risks, expressed in terms of
the combination of consequences and their likelihood
▪ Risk levels with relation to the project objectives are evaluated using
the risk matrices
▪ Risk level of events that may have a positive impact on the project's
cost or time schedule is evaluated using the "Cost decrease" or
"Advance" risk matrices, respectively.
12
Example : Risk Matrices
13
Risk Assessment Matrix
14
Example :Risk Matrices
15
Example: Definition of Consequence
classes in the Risk Matrices
▪ you should modify a appropriate for your project scale, and maybe
add some arguments to why the values are chosen as they are:
Negligible : Event will have negligible impact on the objective.
Project cost: about ±$10k, or less
Time schedule: about ±1 week, or less
Serious : Event will have a sizeable impact on the objective.
Project cost: about ±$100k
Time schedule: about ±1 month
Major : Event will have a large impact on the objective.
Project cost: about ±$1m, or more
Time schedule: about ±6 months, or more
16
The colors of the Matrix fields indicate
Risk level:
High risk
Medium risk
Low risk
17
Example: Evaluation of Risk levels
▪ If the risk level is low, risk treatment is not required. Risk may be
accepted without further justification.
18
Risk Treatment
19
Risk Treatment
20
Monitor & Review
▪ Monitoring
▪ Continual checking, supervising, critically observing or determining
the status in order to identify change from the performance level
requires or expected
▪ Can be applied to a risk management framework, risk management
process, risk or control
▪ Reviewing
▪ Activity undertaken to determine suitability, adequacy and
effectiveness of subject matter to achieve established objectives
▪ Can be applied to a risk management framework, risk management
process, risk or control
21