P6 Paper
P6 Paper
1 P6 Training Project
1.1 Milestones
1.1.1 Letter of Award
1.1.2 Commencement of Work - Office 0 days
1.1.3 Commencement of Work - Site 0 days
1.1.4 Completion of Work 0 days
1.2 Mobilization and Demobilization
1.2.1 Mobilization of Indirect Staff 7 days
1.2.2 Demobilization 4 days
1.3 Project Management
1.3.1 Management Plans
1.3.1.1 Environmental Plans 18 days
1.3.1.2 Health and Safety Plans 18 days
1.3.1.3 Quality and ITPs 18 days
1.3.1.4 Demolition Plan 18 days
1.3.1.5 Aboriginal Development Plan 20 days
1.3.1.6 Project Management Plan 20 days
1.3.1.7 Traffic Management Plan 20 days
1.3.1.8 Project Controls 242 days
1.3.2 Baseline Programme
1.3.2.1 Submission of Baseline Programme 10 days
1.3.2.2 Programme updates 237 days
1.3.3 Licences and Approvals
1.3.3.1 Licences and Approvals from Authorities 7 days
1.3.3.2 Baseline Programme Approval - PWC Client 5 days
1.3.3.3 Design Approval Tanks - PWC Client 50% 5 days
1.3.3.4 Design Approval Tanks - PWC Client - 100% 4 days
1.3.3.5 Design Approval S/Steel - PWC Client - 50% 5 days
1.3.3.6 Design Approval S/Steel - PWC Client - 100% 4 days
1.4 Engineering and Design
1.4.1 Ground & Elevated Tanks Design - 50% 11 days
Predecessors Activity Type Calendar BOQ (PKR)