P6 Paper

The document outlines the work breakdown structure (WBS) for a P6 Training Project, detailing various tasks, their durations, and dependencies. Key components include project management, engineering and design, procurement, logistics, and construction works. The project spans multiple phases with specific milestones and task dependencies, aiming for completion by a specified date.

Uploaded by

ishfaqdirvi0313
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views8 pages

P6 Paper

The document outlines the work breakdown structure (WBS) for a P6 Training Project, detailing various tasks, their durations, and dependencies. Key components include project management, engineering and design, procurement, logistics, and construction works. The project spans multiple phases with specific milestones and task dependencies, aiming for completion by a specified date.

Uploaded by

ishfaqdirvi0313
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

WBS Task Name Duration

1 P6 Training Project
1.1 Milestones
1.1.1 Letter of Award
1.1.2 Commencement of Work - Office 0 days
1.1.3 Commencement of Work - Site 0 days
1.1.4 Completion of Work 0 days
1.2 Mobilization and Demobilization
1.2.1 Mobilization of Indirect Staff 7 days
1.2.2 Demobilization 4 days
1.3 Project Management
1.3.1 Management Plans
1.3.1.1 Environmental Plans 18 days
1.3.1.2 Health and Safety Plans 18 days
1.3.1.3 Quality and ITPs 18 days
1.3.1.4 Demolition Plan 18 days
1.3.1.5 Aboriginal Development Plan 20 days
1.3.1.6 Project Management Plan 20 days
1.3.1.7 Traffic Management Plan 20 days
1.3.1.8 Project Controls 242 days
1.3.2 Baseline Programme
1.3.2.1 Submission of Baseline Programme 10 days
1.3.2.2 Programme updates 237 days
1.3.3 Licences and Approvals
1.3.3.1 Licences and Approvals from Authorities 7 days
1.3.3.2 Baseline Programme Approval - PWC Client 5 days
1.3.3.3 Design Approval Tanks - PWC Client 50% 5 days
1.3.3.4 Design Approval Tanks - PWC Client - 100% 4 days
1.3.3.5 Design Approval S/Steel - PWC Client - 50% 5 days
1.3.3.6 Design Approval S/Steel - PWC Client - 100% 4 days
1.4 Engineering and Design
1.4.1 Ground & Elevated Tanks Design - 50% 11 days
Predecessors Activity Type Calendar BOQ (PKR)

Start Date 3/1/2025


7 Days a week
3SS+2 days Start Milestone 7 Days a week -
56SS Start Milestone 7 Days a week -
19FF,22FF,9,113,118FF,4 Finish Milestone 7 Days a week -

3SS+1 day Task Dependent 7 Days a week 3,500.00


118FF,113FF,116FF Task Dependent 7 Days a week 38,050.00

12SS Task Dependent 5 Days a week


12SS Task Dependent 5 Days a week 650.00
13SS Task Dependent 5 Days a week 650.00
13SS Task Dependent 5 Days a week -
14SS+4 days Task Dependent 5 Days a week 7,500.00
12SS Task Dependent 5 Days a week 1,950.00
17SS Task Dependent 5 Days a week 650.00
3SS,9FF Task Dependent 5 Days a week -

12SS+5 days Task Dependent 5 Days a week 8,400.00


21SS Task Dependent 5 Days a week -

8SS,4,12SS Task Dependent 5 Days a week -


21 Task Dependent 5 Days a week -
31FS-10 days,32FS-10 days Task Dependent 5 Days a week -
26FS+15 days,31,32 Task Dependent 5 Days a week -
26SS Task Dependent 5 Days a week -
28 Task Dependent 5 Days a week -

8SS+3 days Task Dependent 5 Days a week -


1.4.2 Ground & Elevated Tanks Design - 100% 9 days
1.4.3 Elevated Tank Tower S/Steel Design - 50% 5 days
1.4.4 Elevated Tank Tower S/Steel Design - 100% 10 days
1.5 Procurement
1.5.1 Tanks - 2 Days 2 days
1.5.2 Structural Steel - 3 Days 3 days
1.5.3 Precast Elements 5 days
1.5.4 Electrical Subcontract 5 days
1.5.5 Plumbing Subcontract 5 days
1.5.6 Civil Materials - Earthworks 5 days
1.5.7 Concrete - Batching & Product 5 days
1.5.8 Fencing Subcontractor 5 days
1.5.9 Land Clearing Subcontractor 5 days
1.6 Fabrication
1.6.1 Tanks - 13 Weeks 51 days
1.6.2 Structural Steel - 11 Weeks 40 days
1.6.3 Precast Ground Beams 50 days
1.7 Logistics
1.7.1 Plan, Mobilize & Site Establishment 20 days
1.7.2 Tank Shipping incl. Customs clearance - 9 weeks 47 days
1.7.3 Tank Shipping Inland transport - 2 weeks 14 days
1.7.4 Structural Steel & Precast Transport - Ex Works, Site Transit 2 weeks 14 days
1.7.5 Logistics 82 days
1.8 Decommissioning
1.8.1 Existing bypass pipe from Elevated Tank 15 days
1.8.2 Removing Water pumps Equipment and Fittings etc. 15 days
1.8.3 Removing transfer pump wall and roof cladding 15 days
1.8.4 Removing buried and above ground abandoned pipework and associated works 15 days
1.8.5 Existing Elevated Tank & Stand 15 days
1.9 Demolition
1.9.1 Remove compound fence (western elevation) 6 days
1.9.2 Remove trees & vegetation 7 days
1.9.3 Demolish existing Elevated Tank, Stand and Infrastructure (exclude Slab & footings) 7 days
8SS,31FS+14 days Task Dependent 5 Days a week -
31SS+7 days Task Dependent 5 Days a week -
33FS+9 days Task Dependent 5 Days a week -

31SS,32SS+3 days Task Dependent 6 days a week 833.33


32SS-1 day Task Dependent 6 days a week 833.33
31SS+9 days,32SS-1 day Task Dependent 6 days a week 833.33
38SS Task Dependent 6 days a week 833.33
39SS Task Dependent 6 days a week 833.33
36SS Task Dependent 6 days a week 833.33
41SS,31SS,32SS Task Dependent 6 days a week 833.33
31SS,32SS+13 days Task Dependent 6 days a week 833.33
41SS Task Dependent 6 days a week 833.34

32 Task Dependent 7 Days a week 317,743.26


37,34 Task Dependent 7 Days a week 317,743.26
38 Task Dependent 7 Days a week 317,743.26

46 Task Dependent 7 Days a week 64,286.13


46,50FF Task Dependent 7 Days a week 64,286.13
51FS+21 days Task Dependent 7 Days a week 64,286.13
54FF,52SS Task Dependent 7 Days a week 64,286.13
50SS Task Dependent 7 Days a week 64,286.13

50SS+10 days Task Dependent 7 Days a week -


56SS Task Dependent 7 Days a week -
57 Task Dependent 7 Days a week -
58SS Task Dependent 7 Days a week -
113FS+2 days,59SS+3 days Task Dependent 7 Days a week -

59FS+5 days Task Dependent 7 Days a week 32,580.55


62 Task Dependent 7 Days a week 32,580.55
63SS+2 days Task Dependent 7 Days a week 32,580.55
1.9.4 Disposal of Materials 4 days
1.1 Civil - Construction Works
1.10.1 Site Surveying 2 days
1.10.2 Earthworks - Bulk
1.10.2.1 Compound Strip & Proof Roll 5 days
1.10.2.2 Compound sub-base/base to grade 5 days
1.10.2.3 Elevated Tank Footings - bulk excavation 7 days
1.10.3 Detailed Excavation
1.10.3.1 Ground Tank 7 days
1.10.3.2 Elevated Tank 7 days
1.10.3.3 Hydraulic Services trenching 15 days
1.10.3.4 Electrical Services trenching 15 days
1.10.3.5 Hydraulic Services backfill 7 days
1.10.3.6 Electrical Services backfill 7 days
1.10.3.7 Roadworks - Make good roadway trenching 7 days
1.10.4 FRP
1.10.4.1 FR(P) (concrete) Ground Tank Slab 18 days
1.10.4.2 FR(P) (concrete) Elevated Tank Footings 10 days
1.10.4.3 FR(P) (concrete) Water Meter Assembly Slab 4 days
1.10.5 Fencing
1.10.5.1 Make good existing perimeter fence 8 days
1.10.5.2 Install perimeter Fence 7 days
1.11 Electrical Works
1.11.1 Installation of in ground services 21 days
1.11.2 Install Distribution and Switchboard systems 7 days
1.11.3 Connect Existing and New services 7 days
1.11.4 Commission system when live 7 days
1.12 Plumbing Works
1.12.1 Installation of in ground services 21 days
1.12.2 Pressure test in ground pipework 7 days
1.12.3 Install above ground pipework & valves to GL Tank 14 days
1.12.4 Install above ground pipework & valves to EV tank 14 days
1.12.5 Connect Existing and new Services 21 days
64FF Task Dependent 7 Days a week 32,580.55

65SS+2 days Task Dependent 7 Days a week 10,149.34

62SS,65 Task Dependent 7 Days a week -


69SS Task Dependent 7 Days a week 105,073.04
70 Task Dependent 7 Days a week -

71 Task Dependent 7 Days a week -


73 Task Dependent 7 Days a week -
83FS+2 days Task Dependent 7 Days a week -
75SS Task Dependent 7 Days a week -
75FS+35 days Task Dependent 7 Days a week -
76FS+14 days Task Dependent 7 Days a week -
78,77 Task Dependent 7 Days a week -

73 Task Dependent 7 Days a week 298,683.49


74FS+1 day Task Dependent 7 Days a week 317,440.26
82FF Task Dependent 7 Days a week -

65 Task Dependent 7 Days a week 20,288.93


85 Task Dependent 7 Days a week 20,288.93

76FS+7 days Task Dependent 7 Days a week 81,082.12


88SS+11 days Task Dependent 7 Days a week 51,373.93
88 Task Dependent 7 Days a week 55,187.95
90 Task Dependent 7 Days a week -

88SS Task Dependent 7 Days a week 173,398.73


93SS+14 days Task Dependent 7 Days a week -
94,93 Task Dependent 7 Days a week -
95SS Task Dependent 7 Days a week 365,527.67
93SS+14 days Task Dependent 7 Days a week -
1.12.6 Commission system (dead test) 15 days
1.13 Structural Steel
1.13.1 Erect Stage 1 Elevated Tank platform 6 days
1.13.2 Erect Stages 2 - 7 Elevated Tank Platform 28 days
1.13.3 Modifications to Transfer Pump Shed 4 days
1.14 Tank Construction
1.14.1 Tank Construction - Ground Tank 21 days
1.14.2 Tank Construction - Elevated Tank 21 days
1.15 Provisional Works - PWC Client
1.15.1 Scada & Communications - Provision 7 days
1.16 Testing and Commissioning
1.16.1 Pressure test above ground pipework 2 days
1.16.2 Flushing and Disinfection 2 days
1.16.3 Hydrotest Ground Tank 4 days
1.16.4 Hydrotest Elevated Tank 4 days
1.16.5 Bacteriological test and confirm results to PWC guidelines 7 days
1.16.6 Testing and commissioning - Electrical & Piping 7 days
1.17 Contractor Continegency
1.17.1 Contractor Contingency 27 days
1.18 Completion
1.18.1 Completion 0 days
97SS+14 days Task Dependent 7 Days a week -

81FS+4 days Task Dependent 7 Days a week -


100 Task Dependent 7 Days a week 399,625.00
101 Task Dependent 7 Days a week -

81FS+4 days Task Dependent 7 Days a week -


104FS-8 days Task Dependent 7 Days a week -

91 Task Dependent 7 Days a week 30,000.00

95 Task Dependent 7 Days a week -


109 Task Dependent 7 Days a week -
104 Task Dependent 7 Days a week -
105 Task Dependent 7 Days a week -
112,111,110,107,110FF,109 Task Dependent 7 Days a week -
107,98,113 Task Dependent 7 Days a week -

60SS,113 Task Dependent 7 Days a week -

116FF Finish Milestone 7 Days a week -