Section (9) or
Section (9) or
Fall Semester
PERT Analysis informs Program Managers and project personnel on the project’s tasks and the estimated time
required to complete each task. A Program Manager can estimate the minimum time required to complete the
project using this information. The following are PERT’s primary characteristics:
1. High Uncertainty: When task durations are hard to predict due to complexities or a lack of past
data, PERT charts give a more realistic view using probabilistic estimates.
2. Large and Complex Projects: PERT charts visually represent the flow of big projects with many
interconnected tasks, aiding in planning
and resource management.
1. Research and Development Projects: Innovation projects are naturally uncertain. PERT charts
help handle uncertainties and adjust plans based on ongoing discoveries.
Advantages of PERT Charts
1. Handles Uncertainty: PERT charts give a more realistic view of project timelines using probable
time estimates.
2. Better Risk Management: By identifying the path of activities that would delay a project, PERT
charts help manage risks.
3. Clear Communication: PERT charts make project scope, dependencies, and timelines
clearer.
4. Adaptability: PERT charts can be updated with new information acquired as well as when seen from
different contexts of the project’s progress.
Disadvantages of PERT Charts:
1. Time-Consuming: For complex projects, creating and updating PERT charts might consume a lot of
time.
2. Data Reliance: The accuracy of PERT analysis depends on the quality of time estimates.
3. Resource Limitation: PERT charts focus mainly on task durations and dependencies, offering limited
help with resource allocation.
4. Need for Software: Creating and analyzing complex PERT charts require specialized project
management software.
Example(1):
The following project divides into activities, based on three probabilistic times: Optimistic, Moderate, and
Pessimistic (by weeks):
ActivitiesPath O M P
A 1-2 9 15 21
B 1-3 10 13 16
C 2-4 8 12 16
D 3-4 14 16 30
E 3-5 13 15 17
F 4-6 7 11 15
G 5-6 40 44 48
Required:
1. Draw the network that represents this project.
2. How long the time needed to finish the project?
3. What is the probability to finish the project within 76 weeks, within 68 weeks, within 72weeks, between
74,76 weeks and between 70,76 weeks.
4. The total slack of each activity.
Probability under the normal distribution curve table:
Z Probability
1.11 0.3665
2.22 0.4868
Using the following equation to calculate the Expected time:
(O+4M+P/6)
Activities Expected time
A (9+4×15+21 ÷6)= 15
B (10+4×13+16 ÷6)= 13
C 12
D 18
E 15
F 11
G 44
The maximum time needed to finish the project=72
The critical path is (B E G)= 72.
Standard deviation:
𝝈 =√𝑽𝒂𝒓𝒊𝒂𝒏𝒄𝒆 𝒐𝒇 𝒄𝒓𝒊𝒕𝒊𝒄𝒂𝒍 𝒑𝒂𝒕𝒉 𝒂𝒄𝒕𝒊𝒗𝒊𝒕𝒊𝒆𝒔
𝑷−𝑶
𝝈 =√( )𝟐
𝟔
Within 72weeks:
Z=(x-x÷s)=(72-72÷1.8)=0 Probability=0.5(constant)
Between 74,76weeks:
Z=(x-x÷s)=(74-72÷1.8)=1.11 from table=0.3665
Z=(x-x÷s)=(76-72÷1.8)= 2.22 from table=0.4868
Probability=0.4868-0.3665=0.1203
Between 70,76weeks:
Z=(x-x÷s)=(70-72÷1.8)=-1.11 from table=0.3665
Z=(x-x÷s)=(76-72÷1.8)= 2.22 from table=0.4868
Probability=0.4868+0.3665=0.8533
The total slack of each activity:
The earliest start time(ES), earliest finish
time(EF), latest start time (LS)and latest finish
time (LF)for each activity are calculated in the
following table and the slack time for each:
Activities Expected Earliest Latest Slack
time ES EF(3) LS(4) LF (5-3)
(1) (2) (1+2) (5-1) (5) Or
(4-2)
A 15 0 15 34 49 34
B(Critical) 13 0 13 0 13 0
C 12 15 27 49 61 34
D 18 13 31 43 61 30
E (Critical) 15 13 28 13 28 0
F 11 31 42 61 72 30
G (Critical) 44 28 72 28 72 0
Step(1) Graph Graph