CS 6022 Software Project Management

This document outlines the examination details for the B.E. Software Project Management course at Anna University for the seventh semester. It includes instructions for answering questions, a breakdown of the exam structure with parts A, B, and C, and a list of questions covering various topics in software project management. The exam is scheduled for 3 hours and carries a maximum of 100 marks.

Uploaded by

cajilajayareeta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views3 pages

CS 6022 Software Project Management

This document outlines the examination details for the B.E. Software Project Management course at Anna University for the seventh semester. It includes instructions for answering questions, a breakdown of the exam structure with parts A, B, and C, and a list of questions covering various topics in software project management. The exam is scheduled for 3 hours and carries a maximum of 100 marks.

Uploaded by

cajilajayareeta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Roll No.

D E P A R T M E N T O F C O M P U T E R S C I E N C E AND E N G I N E E R I N G
ANNA U N I V E R S I T Y , CHENNAI-25.

B.E END SEMESTER EXAMINATION - NOV/DEC 2023

B.E(Computer Science and Engineering)


Seventh Semester

(Regulation 2018 - RUSA)

CS6022 - Software Project Management

Time: 3 Hours Answer A L L Questions Max.Marks: 100

Instructions:
Write your Register Number at the top of each page of the a n s w e r sheets.
Put y o u r s i g n a t u r e at the b o t t o m o f e a c h p a g e o f the a n s w e r s h e e t s .

PART-A (10 X 2 = 20 Marks)

Max CO
Q.No Question
marks Mapping
1. What is the need o f feasibility study in software process? 2 CO 1

2. L i s t out the w a y s to evaluate the required functionality o f the hardware COl


2
and software?
3. Differentiate programme managers versus project managers 2 CO 2
4. H o w dependency diagram differ from activity network CO 3
2

5. State P a r k i n s o n ' s law and B r o o k ' s law on under and over estimate in a CO 3
2
project.
6. What is dangle? 2 CO 4

7. D r a w the principles o f Theory X & Y . 2 COS

8. G i v e two different axes o f leadership styles. 2 CO S

9. Calculate the effort for the system size 3 K L O C while the productivity CO 5
2
rate is 40 days per L O C .
10. H o w the progress and effectiveness of the project can be measured ? 2 CO 6

Part - B (8x8=64 marks)

Answer any 8 questions

Max CO
Question
Q.No marlts Mapping
11. With necessary diagram, explain stepwise project planning. CO 1
8
12. E x p l a i n the various cost involved in the life o f project analysis. CO 2

13. Elaborate the various quality indicators and management indicators CO 2


used for managing a modern software process and give the overview o f
each.
14. Discuss the need o f analyzing risk before start the project. What are the CO 3
various risk may occur in software development process. Detail risk
identification and risk evaluation with an sample scenario.
15. With an example, explain earned value analysis. COS

Consider a system for office automation is to be designed with the COS


16. requirements of five modules of size 1.5 K L O C , 2.0 K L O C , 2.5 K L O C , 1.0
K L O C , and 2.0 K L O C respectively. Complexity and reliability requirements
are high. Also the programmers' capability and experience is low and all other
factors are of normal rating. Use COCOMO model to determine the overall
cost and schedule estimates.
17. Discuss the important factors o f Oldham H a c k m a n job characteristic CO 3
model.
18. L i s t out various data visualization techniques should a progress COS
manager use when presenting data by considering the key factors o f
audience, purpose of presentation and also the type o f data
19. Elaborate the approaches to identify the activities or tasks that make up COS
the project.
20. Calculate the productivity rates and using productivity rates to the COS
project effort.
Project Work-months SLOC Productivity(S
LOC/month)
A 16.7 6050 362
B 22.6 8363 370
C 32.2 13334 414
D 3.9 5942 1524
E 17.3 3315 192
F 67.7 38988 676
G 12.1 38614 3823
H 19.3 12762 661
I 59.5 26,000 445
Calculate the estimated effort.
21. Is it necessary whether data is related to productivity and quality? COS
Should be made public within software organizations at the team and
project levels. Justify it.
22. Compute the function point value for a project with the following CO 4
infonnation domain characteristics:
i) Number of user inputs = 40
ii) Number of User Outputs = 52
iii) Number o f User Enquiries=16
iv) Number o f Files=09
v ) Number of E x t e r n a l Interfaces = 12
In addition to the above the system requires Significant Data
Communication, Performance level is very critical. Designed code is
moderately reusable. Systems is not designed for multiple installations
in different organizations. Other Complexity adjustment factors are
treated average.
Part - C (2x8=16 marks)

23. Create a precedence activity network and find the critical path for the 8 CO 4
following details
Activity Precedence Duration

A - 6

B A 7

C B 6

D A 5

E D 10

F B 15

G B 4

H G,H 8

1 CD 4

J G 4

K E 5

L 1 3

Design your organizational structure by incorporating the parameter 8 COS


24. such as cost o f your project, technical requirements, locations and
working relationships w h i c h can influence your structure and discuss
how?