CS 6022 Software Project Management
CS 6022 Software Project Management
D E P A R T M E N T O F C O M P U T E R S C I E N C E AND E N G I N E E R I N G
ANNA U N I V E R S I T Y , CHENNAI-25.
Instructions:
Write your Register Number at the top of each page of the a n s w e r sheets.
Put y o u r s i g n a t u r e at the b o t t o m o f e a c h p a g e o f the a n s w e r s h e e t s .
Max CO
Q.No Question
marks Mapping
1. What is the need o f feasibility study in software process? 2 CO 1
5. State P a r k i n s o n ' s law and B r o o k ' s law on under and over estimate in a CO 3
2
project.
6. What is dangle? 2 CO 4
9. Calculate the effort for the system size 3 K L O C while the productivity CO 5
2
rate is 40 days per L O C .
10. H o w the progress and effectiveness of the project can be measured ? 2 CO 6
Max CO
Question
Q.No marlts Mapping
11. With necessary diagram, explain stepwise project planning. CO 1
8
12. E x p l a i n the various cost involved in the life o f project analysis. CO 2
23. Create a precedence activity network and find the critical path for the 8 CO 4
following details
Activity Precedence Duration
A - 6
B A 7
C B 6
D A 5
E D 10
F B 15
G B 4
H G,H 8
1 CD 4
J G 4
K E 5
L 1 3