Project Management
Project Management
SESSION – 20-21
PLANNED VALUE:
1. You have a project to be completed in 12 months. The budget of the project is 100,000 $. Six
months have passed and the schedule says that 50% of the work should be completed. What is
the project’s Planned Value (PV)?
ANS:
Total Budget = $100,000
Planned % Completion after 6 months = 50%
PV=100,000×0.50PV = 100,000 \times 0.50PV=100,000×0.50 PV=50,000PV = 50,000PV=50,000
So, the Planned Value (PV) is $50,000.
2. Consider a project in which the start and end dates for a task are March 1 and March 10,
respectively, and it’s March 4 completed today. If budget allotted to complete the task is 10
Lakhs, then calculate the PV for the task.
ANS:
Given Data:
Start Date: March 1
End Date: March 10
Total Duration: 10 days
Current Date: March 4
Total Budget: ₹10,00,000
Elapsed Duration: March 1 to March 4 → 4 days
Planned % Completion = 410×100=40%\frac{4}{10} \times 100 = 40\%104×100=40%
PV=10,00,000×0.40PV = 10,00,000 \times 0.40PV=10,00,000×0.40 PV=₹4,00,000PV =
₹4,00,000PV=₹4,00,000
So, the Planned Value (PV) is ₹4,00,000.
EARNED VALUE:
3. You have a project to be completed in 12 months. The budget of the project is 100,000 $. Six
months have passed and 60,000 $ has been spent, but on closer review, you find that only 40% of
the work has been completed so far. What is the project Earned Value?
ANS:
Given Data:
Total Budget = $100,000
Actual % Completion = 40%
EV=100,000×0.40EV = 100,000 \times 0.40EV=100,000×0.40 EV=40,000EV = 40,000EV=40,000
So, the Earned Value (EV) is $40,000.
4. Consider a project in which the start and end dates for a task are March 1 and March 10,
respectively. At March 4 it is observed that only one fourth of the task is completed. If budget
allotted to complete the task is 10 Lakhs, then calculate the EV for the task.
ANS:
Given Data:
Total Budget = ₹10,00,000
Actual % Completion = 14=25%\frac{1}{4} = 25\%41=25%
EV=10,00,000×0.25EV = 10,00,000 \times 0.25EV=10,00,000×0.25 EV=₹2,50,000EV =
₹2,50,000EV=₹2,50,000
So, the Earned Value (EV) is ₹2,50,000.
ACTUAL COST
5. You have a project to be completed in 12 months. The budget of the project is 100,000 USD.
Six months have passed, and 60,000 USD has been spent, but on closer review, you find that only
40% of the work has been completed so far. What is the project’s Actual Cost (AC)? Also
identify PV and EV?
ANS:
Let's calculate the required values step by step.
Given Data:
Total Budget (BAC) = $100,000
Time Passed = 6 months (out of 12 months)
Planned % Completion = 50% (since 6 months out of 12)
Actual % Completion = 40%
Amount Spent (Actual Cost, AC) = $60,000
1. Actual Cost (AC):
The Actual Cost (AC) is the amount actually spent on the project so far. Given that $60,000 has been
spent,
AC=60,000AC = 60,000AC=60,000
2. Planned Value (PV):
Planned Value (PV) is calculated using:
PV = \text{Total Budget} \times \text{Planned % Completion} PV=100,000×0.50=50,000PV =
100,000 \times 0.50 = 50,000PV=100,000×0.50=50,000
So, PV = $50,000.
3. Earned Value (EV):
Earned Value (EV) is calculated using:
EV = \text{Total Budget} \times \text{Actual % Completion} EV=100,000×0.40=40,000EV =
100,000 \times 0.40 = 40,000EV=100,000×0.40=40,000
So, EV = $40,000.
Final Answers:
Actual Cost (AC) = $60,000
Planned Value (PV) = $50,000
Earned Value (EV) = $40,000
6. Consider a project in which the start and end dates for a task are March 1 and March 10,
respectively. At March 4 it is observed that, 6 Lakhs Rs. is spent to complete one fourth of the
task. If budget allotted to complete the task is 10 Lakhs, what is AC of activity at 4th of March.
ANS:
Given Data:
Start Date: March 1
End Date: March 10
Total Budget (BAC): ₹10,00,000
Actual % Completion by March 4: 14=25%\frac{1}{4} = 25\%41=25%
Amount Spent (AC) by March 4: ₹6,00,000
Actual Cost (AC):
Actual Cost (AC) is the amount spent on the project up to a specific date.
Since ₹6,00,000 has been spent by March 4, the Actual Cost (AC) is ₹6,00,000.
COMBINED PROBLEM
7. A project team had planned to accomplish $25,000 worth of work to date. It has spent $23,000
to date and accomplished $20,000 worth of work. What is PV, EV and AC of the project as of
today?
Given Data:
Planned Value (PV) = $25,000 (Budgeted cost of scheduled work)
Earned Value (EV) = $20,000 (Budgeted cost of actual work completed)
Actual Cost (AC) = $23,000 (Actual amount spent)
Final Answers:
Planned Value (PV) = $25,000
Earned Value (EV) = $20,000
Actual Cost (AC) = $23,000
This means:
🔹 The project is behind schedule because EV < PV (i.e., only $20,000 worth of work is done instead
of the planned $25,000).
🔹 The project is over budget because EV < AC (i.e., $23,000 has been spent for work worth only
$20,000).
8. You have a project to be completed in 24 months. The budget of the project is 4,00,000 $. 12
months have passed, and you find that only 45% of the work has been completed so far and
2,40,000 has been spent. Find the PV, EV, AC, Cost Variance (CV), Schedule Variance (SV), Cost
Performance Index (CPI) and Schedule Performance Index (SPI).
ANS:
Given Data:
Total Budget (BAC) = $400,000
Total Duration = 24 months
Elapsed Time = 12 months
Planned % Completion = 1224×100=50%\frac{12}{24} \times 100 = 50\%2412×100=50%
Actual % Completion = 45%
Actual Cost (AC) = $240,000
10. A project has 10 work packages, and each work package is estimated to take 1
month to complete. The first 5 work packages are estimated to cost $12,000 each, and
the next 5 work packages are $8,000 each. At the end of month 5, the first 4 work
packages were completed at the cost of $48,000. What is PV, EV and AC of the project
at the end of month 5?
ANS:
Given Data:
Planned Value (PV) is the budgeted cost of scheduled work at a given time.
Since 5 months have passed, the planned completion is 5 work packages.
PV=Budget for First 5 Packages=5×12,000PV = \text{Budget for First 5 Packages} =
5 \times 12,000PV=Budget for First 5 Packages=5×12,000 PV=60,000PV =
60,000PV=60,000
Planned Value (PV) = $60,000
Actual Cost (AC) is the total amount spent on the work so far. Given:
AC = $48,000
S – CURVE
11. Suppose you have a budgeted cost of a project at $9,00,000. The project is to be
completed in 9 months. After a month, you have completed 10 percent of the project at
a total expense of $1,00,000. The planned completion should have been 15 percent.
Draw the S-curve and tracks progress of project.
ANS:
Step 1: Given Data
Planned Duration = 8 months
Planned Monthly Cost = $10,000
Total Budget (BAC) = 8×10,000=80,0008 \times 10,000 = 80,0008×10,000=80,000
Time Elapsed = 2 months
Actual Cost (AC) after 2 months = $40,000
Work Completed = 30%
Planned Progress after 2 months = 28×100=25%\frac{2}{8} \times 100 = 25\%82
×100=25%
Step 2: Calculate Key Project Metrics
1. Planned Value (PV)
PV=BAC×Planned Progress/ 100
PV=80,000×0.25=20,000
2. Earned Value (EV)
EV=BAC×Actual Progress/100
EV=80,000×0.30=24,000
3. Schedule Performance Index (SPI)
SPI=EV/PV=24,000/20,000=1.2
Since SPI > 1, the project is ahead of schedule.
CR=SPI×CPI
CR=1.2×0.6=0.72
Step 4: Interpretation of Critical Ratio
CR > 1 → Project is in excellent condition.
CR = 1 → Project is on track.
CR < 1 → Project is in trouble.
Since CR = 0.72 (< 1), the project is at risk due to cost overruns, even though it is
ahead of schedule. Immediate cost control measures are required.
Step 5: Overall Progress Assessment
Ahead of schedule (SPI = 1.2)
Over budget (CPI = 0.6)
Risky status (CR = 0.72)
CRITICAL RATIO
12.Suppose you are managing a software development project. The project is expected
to be completed in 8 months at a cost of $10,000 per month. After 2 months, you realize
that the project is 30 percent completed at a cost of $40,000. Calculate the Critical Ratio
of project, and identify the overall progress of the project?
ANS:
Given Data:
Total Duration = 8 months
Total Budget (BAC) = $10,000 × 8 = $80,000
Time Elapsed = 2 months
Planned % Completion = 28×100=25%\frac{2}{8} \times 100 = 25\%82×100=25%
Actual % Completion = 30%
Actual Cost (AC) = $40,000
1.You are managing a project which is into six months of its execution. You are now
reviewing the project status after the completion of four months. Project consists of two
activities: Activity A and B. The actual cost of activity A is $ 2,00,000 and that of
activity B is $ 1,00,000. The planned value of these activities are $ 1,80,000 and $ 80,000
respectively. The Activity A is 60% completed. However, Activity B is only 55%
completed. Calculate the schedule performance index and cost performance index of the
project on the review date and comment on the status of project.
ANS:
Given Data:
Activity A:
o Actual Cost (AC_A) = $200,000
o Planned Value (PV_A) = $180,000
o % Completed = 60%
Activity B:
o Actual Cost (AC_B) = $100,000
o Planned Value (PV_B) = $80,000
o % Completed = 55%
3. You have a project to build a new fence. The fence is four sided. Each side is to take
one day to build and is budgeted for $1,000 per side. The sides are planned to be
completed one after the other. Today is the end of day three. Calculate PV, EV, AC, CV,
CPI, SV, SPI, CR with following information.
ANS:
Given Data:
Total project duration: 4 days
Budget per side: $1,000
Total Budget (BAC): 4×1,000=4,0004 \times 1,000 = 4,0004×1,000=4,000
Current day: End of day 3