Finance Team Assignment part 2
Finance Team Assignment part 2
Task 1.
($)
0 - - -40,000 - - -640,000
WACC = ( E / V * re ) + ( D / V * rd * ( 1 - T ) )
D / E = ( D / V ) / ( E / V )
Sports
= 10.16%
Task 3
$1,097,578.17
= $1,097,578.17 − $640,000
= $457,578.17
Cash Flows:
iteratively solve for the discount rate which equates the present value of the cash inflows to
What this means is that the rate of return the project is expected to throw out is 34.56%.
Task 5
Gloomy Scenario: -Discount rate: since the WACC is to be increased by 2%, the new
10%.
Rosy Scenario:
Discount rate: Take WACC and reduce it by 2%, therefore the new WACC = 10.16% - 2% =
8.16%
First, for both the base and rosy scenarios, adjust revenues then recalculate an updated
Gloomy Scenario:
NPV: $874,163.62
This scenario would mean that the NPV is highly negative; therefore, under worsened
Rosy Scenario:
NPV: $564,535.67
Even in this optimistic case, the NPV remains negative, though better than under the gloomy
situation. However, from this analysis too, the project could still not be commercially viable.
Conclusion: From both the pessimistic and optimistic scenarios, the financial viability of the
Task 6
Financial Viability
Base Case: The NPV is $457,578.17, and the IRR is 34.56%, indicating that the project is
Rosy Scenario: Even under a more favorable set of circumstances, assuming a lower
discount rate and revenues increased by 10%, the NPV is −$564,535.67, indicating only that
the project may shallowly create value under the most favorable of circumstances.
Risk and Sensitivity This project shows high sensitivity regarding changes in revenues and
the cost of capital. In the "gloomy" case, a minor decline in the market conditions has
disproportionately changed its financials to the very sensitive condition, which could indicate
that the project itself may involve considerable risk if market conditions are unstable or
unpredictable.
Recommendations From the results of the analyses, mixed financial perspectives could be
seen in the project. While the base case provides a positive value, the pessimistic and
Go/No Go Decision:
Revise the Forecasts: Re-consider the revenue forecasts and the market volatility before
proceeding. Spend additional time conducting market research to confirm that the base case
Risk Mitigation: The company can dwell on its strategy to mitigate the potential risks that will
Cost Reduction: The Company must focus on reduction of operating cost and COGS with a
view to increase free cash flows. Operational efficiencies or better supplier terms can lead to
market conditions.
Alternative Strategy: If the company is not so confident about the project's financial viability,
expenses. That would reduce the initial investment, thereby potentially increasing the NPV.
Delay or Scale Down: To expose less financially, the product can be launched on a smaller
Final Decision
The project should be accepted if it is believed that major control of costs can be exercised
and revenue forecasts achieved. If the risks seem too great, pushing the project into the
advisable.