Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
132kV Marudi Junc on to Miri Airport Transmission Line 270418 586 12-Feb-18 11-Feb-20 0 11-Feb-20, 132kV Marudi Junc on to Miri
Project Master Schedule 586 12-Feb-18 11-Feb-20 0 11-Feb-20, Project Master Schedule
Project Key Milestone 586 12-Feb-18 11-Feb-20 0 11-Feb-20, Project Key Milestone
MST-1000 Project Commencement 0 12-Feb-18 0 Project Commencement, 12-Feb-18
MST-1010 Applica on of Early Commencement by NREB 0 03-May-18 57 Applica on of Early Commencement by NREB, 03-May-18
MST-4050 Hand Over of Miri Airport - Tudan 33kV Line 0 12-Feb-19 43 Hand Over of Miri Airport - Tudan 33kV Line, 12-Feb-19
MST-2030 Design and Engineering Comple on (Not Including MS and ITP) 0 27-Feb-19 234 Design and Engineering Comple on (Not Including MS and ITP),
MST-6030 Line Turn In at Eastwood Substa on 0 08-Jun-19* 18 Line Turn In at Eastwood Substa on,
MST-6035 Line Turn In at Tudan Miri Airport Line 0 25-Jun-19* 4 Line Turn In at Tudan Miri Airport Line,
MST-4040 Tower Founda on Works Comple on 0 05-Sep-19 128 Tower Founda on Works Comple on,
MST-2060 FAT Comple on 0 06-Sep-19 127 FAT Comple on,
MST-2050 Manufacturing Comple on 0 25-Sep-19 114 Manufacturing Comple on,
MST-3040 Material Delivery Comple on 0 30-Oct-19 84 Material Delivery Comple on,
MST-5020 Tower Erec on Comple on 0 16-Dec-19 45 Tower Erec on Comple on,
MST-6020 Stringing Works Comple on 0 16-Jan-20 20 Stringing Works Comple on,
MST-7010 Commencement of Final Inspec on, Line Tes ng and Commisioning 0 17-Jan-20 20 Commencement of Final Inspec on, Line Tes ng
MST-9000 Project Comple on 0 11-Feb-20 0 Project Comple on,
Preliminaries Work 576 26-Feb-18 11-Feb-20 0 11-Feb-20, Preliminaries Work
Prelim_1000 Submission of Performance Bond 0 26-Feb-18 467 Submission of Performance Bond,
Prelim_1020 CIDB Registra on 0 26-Feb-18 481 CIDB Registra on,
Prelim_1050 Submission of Work Programme 30 14-Mar-18 25-Apr-18 439 Submission of Work Programme
Prelim_1110 Set Up of Project Execu on 562 14-Mar-18 11-Feb-20 0 Set Up of Project Execu on
Prelim_1010 Submission of Project Insurance 0 15-Mar-18 467 Submission of Project Insurance,
Prelim_1100 Submission of Monthly QAQC Report 558 19-Mar-18 11-Feb-20 0 Submission of Monthly QAQC Report
Prelim_1040 Site Mobilisa on 5 21-Mar-18 26-Mar-18 1 Site Mobilisa on
Prelim_1070 Submission of Progress Monthly Report 553 24-Mar-18 11-Feb-20 0 Submission of Progress Monthly Report
Prelim_1080 Submission of Monthly HSE Report 553 24-Mar-18 11-Feb-20 0 Submission of Monthly HSE Report
Prelim_1030 Se ng up of Site Office & IT Facili es 30 29-Mar-18 04-May-18 519 Se ng up of Site Office & IT Facili es
Prelim_1060 Provision of Site Vehicles 1 29-Mar-18 29-Mar-18 548 Provision of Site Vehicles
Prelim_1090 Submission of Environmental Report 512 14-May-18 11-Feb-20 0 Submission of Environmental Report
Design and Engineering 458 08-Mar-18 20-Jan-20 15 20-Jan-20, Design and Engineering
Design Concept and Parameters 116 16-Apr-18 08-Oct-18 331 08-Oct-18, Design Concept and Parameters
DE_CP_10000 Subm. & Appr. of Design basis report of tower 30 16-Apr-18 28-May-18 2 Subm. & Appr. of Design basis report of tower
DE_CP_10010 Subm. & Appr. of Design basis report of normal founda on 30 29-May-18 12-Jul-18 387 Subm. & Appr. of Design basis report of normal founda on
DE_CP_10020 Subm. & Appr. of Design basis report of pile founda on for tower 30 09-Jul-18 20-Aug-18 65 Subm. & Appr. of Design basis report of pile founda on for tower
DE_CP_10030 Subm. & Appr. of Design basis report of pile founda on for monopole 30 21-Aug-18 08-Oct-18 133 Subm. & Appr. of Design basis report of pile founda on for monopole
Line Equipments / Material Specifica ons 102 30-Apr-18 02-Oct-18 98 02-Oct-18, Line Equipments / Material Specifica ons
DE_LEMS_10080 Subm. & Appr. of Steel Material Specifica on 30 30-Apr-18 13-Jun-18 112 Subm. & Appr. of Steel Material Specifica on
DE_LEMS_10040 Subm. & Appr. of Warning Sphere Specifica on 30 30-Apr-18 13-Jun-18 39 Subm. & Appr. of Warning Sphere Specifica on
DE_LEMS_10060 Subm. & Appr. of Bolt and Nut Specifica on 30 30-Apr-18 13-Jun-18 117 Subm. & Appr. of Bolt and Nut Specifica on
DE_LEMS_10070 Subm. & Appr. of ATN Specifica on 30 30-Apr-18 13-Jun-18 39 Subm. & Appr. of ATN Specifica on
DE_LEMS_10000 Subm. & Appr. of Insulator Specifica on 30 30-Apr-18 13-Jun-18 6 Subm. & Appr. of Insulator Specifica on
DE_LEMS_10010 Subm. & Appr. of Conductor Specifica on 30 30-Apr-18 13-Jun-18 6 Subm. & Appr. of Conductor Specifica on
DE_LEMS_10020 Subm. & Appr. of OPGW Specifica on 30 30-Apr-18 13-Jun-18 6 Subm. & Appr. of OPGW Specifica on
DE_LEMS_10030 Subm. & Appr. of OPUG Specifica on 30 30-Apr-18 13-Jun-18 6 Subm. & Appr. of OPUG Specifica on
DE_LEMS_10090 Subm. & Appr. of Spun Pile Specifica on 30 15-May-18 28-Jun-18 160 Subm. & Appr. of Spun Pile Specifica on
DE_LEMS_10100 Subm. & Appr. of Tower Earthing Specifica on 30 22-May-18 05-Jul-18 46 Subm. & Appr. of Tower Earthing Specifica on
DE_LEMS_10050 Subm. & Appr. of Avia on Light Specifica on 30 15-Aug-18 02-Oct-18 39 Subm. & Appr. of Avia on Light Specifica on
Line Fi ngs Drawings And Accessories 35 22-May-18 12-Jul-18 177 12-Jul-18, Line Fi ngs Drawings And Accessories
Conductor Line Fi ngs 35 22-May-18 12-Jul-18 177 12-Jul-18, Conductor Line Fi ngs
DE_LFDA_20200 Subm. & Appr. of Jumper Suspension Set 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Jumper Suspension Set
DE_LFDA_20300 Subm. & Appr. of Double Tension Set - Angle Tower 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Double Tension Set - Angle Tower
DE_LFDA_20400 Subm. & Appr. of Inverted Light Duty Tension Set 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Inverted Light Duty Tension Set
DE_LFDA_20000 Subm. & Appr. of Single Suspension Set 30 22-May-18 05-Jul-18 49 Subm. & Appr. of Single Suspension Set
DE_LFDA_20100 Subm. & Appr. of Double Suspension Set 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Double Suspension Set
Conductor Line Accessories 35 22-May-18 12-Jul-18 177 12-Jul-18, Conductor Line Accessories
DE_LFDA_21710 Subm. & Appr. of Counter Weight 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Counter Weight
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 1 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
DE_LFDA_20500 Subm. & Appr. of Jumper Spacer 30 22-May-18 05-Jul-18 49 Subm. & Appr. of Jumper Spacer
DE_LFDA_20600 Subm. & Appr. of Spacer Damper 35 22-May-18 12-Jul-18 104 Subm. & Appr. of Spacer Damper
DE_LFDA_20700 Subm. & Appr. of Vibra on Damper 35 22-May-18 12-Jul-18 104 Subm. & Appr. of Vibra on Damper
DE_LFDA_20800 Subm. & Appr. of Mid Span Joint 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Mid Span Joint
DE_LFDA_20900 Subm. & Appr. of Repair Sleeves 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Repair Sleeves
DE_LFDA_21000 Subm. & Appr. of Line Spacer 35 22-May-18 12-Jul-18 104 Subm. & Appr. of Line Spacer
OPGW / Earthwire Fi ngs & Accessories 35 22-May-18 12-Jul-18 177 12-Jul-18, OPGW / Earthwire Fi ngs & Accessories
DE_LFDA_21100 Subm. & Appr. of OPGW Suspension Set 35 22-May-18 12-Jul-18 177 Subm. & Appr. of OPGW Suspension Set
DE_LFDA_21200 Subm. & Appr. of OPGW Tension Set 35 22-May-18 12-Jul-18 177 Subm. & Appr. of OPGW Tension Set
DE_LFDA_21300 Subm. & Appr. of OPGW Tension Set with Connec on to Joint Box 35 22-May-18 12-Jul-18 177 Subm. & Appr. of OPGW Tension Set with Connec on to Joint Box
DE_LFDA_21400 Subm. & Appr. of OPGW Tension Set with Connec on to Gantry 35 22-May-18 12-Jul-18 177 Subm. & Appr. of OPGW Tension Set with Connec on to Gantry
DE_LFDA_21500 Subm. & Appr. of Joint Box for OPGW 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Joint Box for OPGW
DE_LFDA_21600 Subm. & Appr. of Vibra on Damper for OPGW 35 22-May-18 12-Jul-18 177 Subm. & Appr. of Vibra on Damper for OPGW
DE_LFDA_21700 Subm. & Appr. of other OPGW accessories 35 22-May-18 12-Jul-18 177 Subm. & Appr. of other OPGW accessories
Line Design 213 16-Apr-18 27-Feb-19 225 27-Feb-19, Line Design
Sag and Tension 45 16-Apr-18 21-Jun-18 47 21-Jun-18, Sag and Tension
DE_LDST_30000 Subm. & Appr. of Sag and Tension Calcula on Report for Conductor AAAC Sycamore
45 16-Apr-18 21-Jun-18 47 Subm. & Appr. of Sag and Tension Calcula on Report for Conductor AAAC Sycamore
DE_LDST_30010 Subm. & Appr. of Sag and Tension Calcula on Report for OPGW 45 16-Apr-18 21-Jun-18 47 Subm. & Appr. of Sag and Tension Calcula on Report for OPGW
Tower Electrical Clearance Check 151 27-Apr-18 10-Dec-18 2 10-Dec-18, Tower Electrical Clearance Check
DE_LDEC_30000 Subm. & Appr. of 1NS tower electrical clearance 35 27-Apr-18 20-Jun-18 7 Subm. & Appr. of 1NS tower electrical clearance
DE_LDEC_30020 Subm. & Appr. of 1LA tower electrical clearance 35 06-Jun-18 26-Jul-18 18 Subm. & Appr. of 1LA tower electrical clearance
DE_LDEC_30010 Subm. & Appr. of 1HS tower electrical clearance 35 29-Jun-18 17-Aug-18 8 Subm. & Appr. of 1HS tower electrical clearance
DE_LDEC_30030 Subm. & Appr. of 1MA tower electrical clearance 35 20-Jul-18 13-Sep-18 52 Subm. & Appr. of 1MA tower electrical clearance
DE_LDEC_30040 Subm. & Appr. of 1HA tower electrical clearance 35 06-Sep-18 29-Oct-18 20 Subm. & Appr. of 1HA tower electrical clearance
DE_LDEC_30050 Subm. & Appr. of 1DE tower electrical clearance 35 22-Oct-18 10-Dec-18 2 Subm. & Appr. of 1DE tower electrical clearance
Line Profile 49 30-May-18 10-Aug-18 228 10-Aug-18, Line Profile
Sec on 2 - T4/1 - AT5 35 22-Jun-18 10-Aug-18 171 10-Aug-18, Sec on 2 - T4/1 - AT5
DE_LDLP_30040 Subm. & Appr. of Line Profile Sec on 2 - T4/5 - T4/8 35 22-Jun-18 10-Aug-18 147 Subm. & Appr. of Line Profile Sec on 2 - T4/5 - T4/8
DE_LDLP_30050 Subm. & Appr. of Line Profile Sec on 2 - T4/9 - AT5 35 22-Jun-18 10-Aug-18 171 Subm. & Appr. of Line Profile Sec on 2 - T4/9 - AT5
DE_LDLP_30030 Subm. & Appr. of Line Profile Sec on 2 - T4/1 - T4/4 35 22-Jun-18 10-Aug-18 141 Subm. & Appr. of Line Profile Sec on 2 - T4/1 - T4/4
Sec on 3 - T5/1 - AT6 35 22-Jun-18 10-Aug-18 228 10-Aug-18, Sec on 3 - T5/1 - AT6
DE_LDLP_30060 Subm. & Appr. of Line Profile Sec on 3 - T5/1 - T5/4 35 22-Jun-18 10-Aug-18 178 Subm. & Appr. of Line Profile Sec on 3 - T5/1 - T5/4
DE_LDLP_30070 Subm. & Appr. of Line Profile Sec on 3 - T5/5 - T5/8 35 22-Jun-18 10-Aug-18 183 Subm. & Appr. of Line Profile Sec on 3 - T5/5 - T5/8
DE_LDLP_30080 Subm. & Appr. of Line Profile Sec on 3 - T5/9 - T5/12 35 22-Jun-18 10-Aug-18 205 Subm. & Appr. of Line Profile Sec on 3 - T5/9 - T5/12
DE_LDLP_30090 Subm. & Appr. of Line Profile Sec on 3 - T5/13 - T5/16 35 22-Jun-18 10-Aug-18 227 Subm. & Appr. of Line Profile Sec on 3 - T5/13 - T5/16
DE_LDLP_30100 Subm. & Appr. of Line Profile Sec on 3 - T5/17 - AT6 35 22-Jun-18 10-Aug-18 228 Subm. & Appr. of Line Profile Sec on 3 - T5/17 - AT6
Sec on 1 - AT1 - AT4 35 22-Jun-18 10-Aug-18 130 10-Aug-18, Sec on 1 - AT1 - AT4
DE_LDLP_30000 Subm. & Appr. of Line Profile Sec on 1 - AT1 - AT3 35 22-Jun-18 10-Aug-18 117 Subm. & Appr. of Line Profile Sec on 1 - AT1 - AT3
DE_LDLP_30010 Subm. & Appr. of Line Profile Sec on 1 - T3/1 - T3/3 35 22-Jun-18 10-Aug-18 117 Subm. & Appr. of Line Profile Sec on 1 - T3/1 - T3/3
DE_LDLP_30020 Subm. & Appr. of Line Profile Sec on 1 - T3/4 - AT4 35 22-Jun-18 10-Aug-18 130 Subm. & Appr. of Line Profile Sec on 1 - T3/4 - AT4
Sec on 4 - AT7 - AT8 (Monopoles) 35 30-May-18 20-Jul-18 242 20-Jul-18, Sec on 4 - AT7 - AT8 (Monopoles)
DE_LDLP_30110 Subm. & Appr. of Line Profile Sec on 4 - AT7 - T7/3 35 30-May-18 20-Jul-18 217 Subm. & Appr. of Line Profile Sec on 4 - AT7 - T7/3
DE_LDLP_30120 Subm. & Appr. of Line Profile Sec on 4 - T7/4 - T7/7 35 30-May-18 20-Jul-18 242 Subm. & Appr. of Line Profile Sec on 4 - T7/4 - T7/7
DE_LDLP_30130 Subm. & Appr. of Line Profile Sec on 4 - T7/8 - T7/11 35 30-May-18 20-Jul-18 242 Subm. & Appr. of Line Profile Sec on 4 - T7/8 - T7/11
DE_LDLP_30140 Subm. & Appr. of Line Profile Sec on 4 - T7/12 - T7/15 35 30-May-18 20-Jul-18 242 Subm. & Appr. of Line Profile Sec on 4 - T7/12 - T7/15
DE_LDLP_30150 Subm. & Appr. of Line Profile Sec on 4 - T7/16 - T7/19 35 30-May-18 20-Jul-18 242 Subm. & Appr. of Line Profile Sec on 4 - T7/16 - T7/19
DE_LDLP_30160 Subm. & Appr. of Line Profile Sec on 4 - T7/20 - AT8 35 30-May-18 20-Jul-18 242 Subm. & Appr. of Line Profile Sec on 4 - T7/20 - AT8
Diagonal Profile 61 05-Jul-18 05-Oct-18 323 05-Oct-18, Diagonal Profile
Sec on 1 - AT! - AT4 35 13-Aug-18 05-Oct-18 54 05-Oct-18, Sec on 1 - AT! - AT4
DE_LDDP_50000 Subm. & Appr. of Diagonal Profile Sec on 1 - AT1 - AT3 35 13-Aug-18 05-Oct-18 47 Subm. & Appr. of Diagonal Profile Sec on 1 - AT1 - AT3
DE_LDDP_50010 Subm. & Appr. of Diagonal Profile Sec on 1 - T3/1 - T3/3 35 13-Aug-18 05-Oct-18 47 Subm. & Appr. of Diagonal Profile Sec on 1 - T3/1 - T3/3
DE_LDDP_50020 Subm. & Appr. of Diagonal Profile Sec on 1 - T3/4 - AT4 35 13-Aug-18 05-Oct-18 54 Subm. & Appr. of Diagonal Profile Sec on 1 - T3/4 - AT4
Sec on 2 - T4/1 - AT5 35 13-Aug-18 05-Oct-18 136 05-Oct-18, Sec on 2 - T4/1 - AT5
DE_LDDP_50040 Subm. & Appr. of Diagonal Profile Sec on 2 - T4/5 - T4/8 35 13-Aug-18 05-Oct-18 112 Subm. & Appr. of Diagonal Profile Sec on 2 - T4/5 - T4/8
DE_LDDP_50050 Subm. & Appr. of Diagonal Profile Sec on 2 - T4/9 - AT5 35 13-Aug-18 05-Oct-18 136 Subm. & Appr. of Diagonal Profile Sec on 2 - T4/9 - AT5
DE_LDDP_50030 Subm. & Appr. of Diagonal Profile Sec on 2 - T4/1 - T4/4 35 13-Aug-18 05-Oct-18 106 Subm. & Appr. of Diagonal Profile Sec on 2 - T4/1 - T4/4
Sec on 3 - T5/1 - AT6 35 13-Aug-18 05-Oct-18 175 05-Oct-18, Sec on 3 - T5/1 - AT6
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 2 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
DE_LDDP_50060 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/1 - T5/4 35 13-Aug-18 05-Oct-18 108 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/1 - T5/4
DE_LDDP_50070 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/5 - T5/8 35 13-Aug-18 05-Oct-18 113 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/5 - T5/8
DE_LDDP_50080 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/9 - T5/12 35 13-Aug-18 05-Oct-18 135 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/9 - T5/12
DE_LDDP_50090 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/13 - T5/16 35 13-Aug-18 05-Oct-18 157 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/13 - T5/16
DE_LDDP_50100 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/17 - AT6 35 13-Aug-18 05-Oct-18 175 Subm. & Appr. of Diagonal Profile Sec on 3 - T5/17 - AT6
Sec on 4 - AT7 - AT8 (Monopoles) 35 05-Jul-18 24-Aug-18 349 24-Aug-18, Sec on 4 - AT7 - AT8 (Monopoles)
DE_LDDP_50110 Subm. & Appr. of Diagonal Profile Sec on 4 - AT7 - T7/3 35 05-Jul-18 24-Aug-18 229 Subm. & Appr. of Diagonal Profile Sec on 4 - AT7 - T7/3
DE_LDDP_50120 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/4 - T7/7 35 05-Jul-18 24-Aug-18 264 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/4 - T7/7
DE_LDDP_50130 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/8 - T7/11 35 05-Jul-18 24-Aug-18 292 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/8 - T7/11
DE_LDDP_50140 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/12 - T7/15 35 05-Jul-18 24-Aug-18 298 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/12 - T7/15
DE_LDDP_50150 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/16 - T7/19 35 05-Jul-18 24-Aug-18 322 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/16 - T7/19
DE_LDDP_50160 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/20 - AT8 35 05-Jul-18 24-Aug-18 349 Subm. & Appr. of Diagonal Profile Sec on 4 - T7/20 - AT8
Material Schedules & Line Schedules 84 30-May-18 05-Oct-18 157 05-Oct-18, Material Schedules & Line Schedules
DE_MSLS_60300 Subm. & Appr. of Line Schedules from AT7-AT8 (Monopole) 35 30-May-18 20-Jul-18 171 Subm. & Appr. of Line Schedules from AT7-AT8 (Monopole)
DE_MSLS_60100 Subm. & Appr. of Line Schedules from AT1-AT6 (Steel La ce) 35 22-Jun-18 10-Aug-18 47 Subm. & Appr. of Line Schedules from AT1-AT6 (Steel La ce)
DE_MSLS_60000 Subm. & Appr. of Material Schedules from AT1-AT6 (Steel La ce) 35 13-Aug-18 05-Oct-18 157 Subm. & Appr. of Material Schedules from AT1-AT6 (Steel La ce)
DE_MSLS_60200 Subm. & Appr. of Material Schedules from AT7-AT8 (Monopole) 35 13-Aug-18 05-Oct-18 157 Subm. & Appr. of Material Schedules from AT7-AT8 (Monopole)
Conductor and OPGW Stringing Schedules 70 15-Nov-18 27-Feb-19 213 27-Feb-19, Conductor and OPGW Stringing Schedules
DE_SS_70200 Subm. & Appr. Stringing Chart of Conductor AAAC Sycamorefor Marudi Jucn on 35- Miri Airport15-Nov-18 07-Jan-19 130 Subm. & Appr. Stringing Chart of Conductor AAAC Sycamorefor Marudi Jucn on - Miri Airport
DE_SS_70300 Subm. & Appr. Stringing Chart of OPGW for Marudi Jucn on - Miri Airport 35 15-Nov-18 07-Jan-19 130 Subm. & Appr. Stringing Chart of OPGW for Marudi Jucn on - Miri Airport
DE_SS_70400 Subm. & Appr. Offset Clipping Report of Conductor AAAC Sycamorefor Marudi Jucn
35 on - Miri Airport
15-Nov-18 07-Jan-19 130 Subm. & Appr. Offset Clipping Report of Conductor AAAC Sycamorefor Marudi Jucn on - Miri Airport
DE_SS_70500 Subm. & Appr. Offset Clipping Report of OPGW for Marudi Jucn on - Miri Airport
35 15-Nov-18 07-Jan-19 130 Subm. & Appr. Offset Clipping Report of OPGW for Marudi Jucn on - Miri Airport
DE_SS_70100 Subm. & Appr. Running Sag Table of Conductor and OPGW in Miri Airport S/S 35 11-Dec-18 30-Jan-19 133 Subm. & Appr. Running Sag Table of Conductor and OPGW in Miri Airport S/S
DE_SS_70000 Subm. & Appr. of Stringing Schedule for Marudi Junc on to Miri Airport 35 03-Jan-19 22-Feb-19 133 Subm. & Appr. of Stringing Schedule for Marudi Junc on to Miri Airport
DE_SS_70800 Subm. & Appr. Vibra on Damper Placement Chart of OPGW 35 08-Jan-19 27-Feb-19 130 Subm. & Appr. Vibra on Damper Placement Chart of OPGW
DE_SS_70900 Subm. & Appr. Installa on Drawing of Jumper Line for Conductor AAAC Sycamore35 08-Jan-19 27-Feb-19 130 Subm. & Appr. Installa on Drawing of Jumper Line for Conductor AAAC Sycamore
DE_SS_71000 Subm. & Appr. OPGW Joint Box Loca on Schedule for Marudi Jucn on - Miri Airport
35 08-Jan-19 27-Feb-19 213 Subm. & Appr. OPGW Joint Box Loca on Schedule for Marudi Jucn on - Miri Airport
DE_SS_71100 Subm. & Appr. Installa on Table of Warning Sphere for Marudi Jucn on - Miri Airport
35 08-Jan-19 27-Feb-19 205 Subm. & Appr. Installa on Table of Warning Sphere for Marudi Jucn on - Miri Airport
DE_SS_70600 Subm. & Appr. Spacer Damper Placement Chart of Conductor AAAC Sycamore35 08-Jan-19 27-Feb-19 130 Subm. & Appr. Spacer Damper Placement Chart of Conductor AAAC Sycamore
DE_SS_70700 Subm. & Appr. Vibra on Damper Placement Chart of Conductor AAAC Sycamore 35 08-Jan-19 27-Feb-19 130 Subm. & Appr. Vibra on Damper Placement Chart of Conductor AAAC Sycamore
Line Support Design Calcula on Reports & Sketch 173 30-Apr-18 14-Jan-19 41 14-Jan-19, Line Support Design Calcula on Reports & Sketch
Tower Design Calcula on Reports & Outline 170 30-Apr-18 09-Jan-19 2 09-Jan-19, Tower Design Calcula on Reports & Outline
DE_TDCR_10000 Subm. & Appr. of 1NS Load Computa on and Load Trees 35 30-Apr-18 21-Jun-18 6 Subm. & Appr. of 1NS Load Computa on and Load Trees
DE_TDCR_10010 Subm. & Appr. of 1NS Design Calcula on Report 35 18-May-18 10-Jul-18 6 Subm. & Appr. of 1NS Design Calcula on Report
DE_TDCR_10040 Subm. & Appr. of 1LA Load Computa on and Load Trees 35 06-Jun-18 26-Jul-18 18 Subm. & Appr. of 1LA Load Computa on and Load Trees
DE_TDCR_10020 Subm. & Appr. of 1HS Load Computa on and Load Trees 35 29-Jun-18 17-Aug-18 8 Subm. & Appr. of 1HS Load Computa on and Load Trees
DE_TDCR_10050 Subm. & Appr. of 1LA Design Calcula on Report 35 04-Jul-18 23-Aug-18 18 Subm. & Appr. of 1LA Design Calcula on Report
DE_TDCR_10030 Subm. & Appr. of 1HS Design Calcula on Report 35 20-Jul-18 13-Sep-18 8 Subm. & Appr. of 1HS Design Calcula on Report
DE_TDCR_10060 Subm. & Appr. of 1MA Load Computa on and Load Trees 35 20-Jul-18 13-Sep-18 52 Subm. & Appr. of 1MA Load Computa on and Load Trees
DE_TDCR_10070 Subm. & Appr. of 1MA Design Calcula on Report 35 20-Aug-18 12-Oct-18 52 Subm. & Appr. of 1MA Design Calcula on Report
DE_TDCR_10080 Subm. & Appr. of 1HA Load Computa on and Load Trees 35 06-Sep-18 29-Oct-18 20 Subm. & Appr. of 1HA Load Computa on and Load Trees
DE_TDCR_10090 Subm. & Appr. of 1HA Design Calcula on Report 35 04-Oct-18 22-Nov-18 20 Subm. & Appr. of 1HA Design Calcula on Report
DE_TDCR_10100 Subm. & Appr. of 1DE Load Computa on and Load Trees 35 22-Oct-18 10-Dec-18 2 Subm. & Appr. of 1DE Load Computa on and Load Trees
DE_TDCR_10110 Subm. & Appr. of 1DE Design Calcula on Report 35 19-Nov-18 09-Jan-19 2 Subm. & Appr. of 1DE Design Calcula on Report
Stub Design Calcula ons & Sketch (Normal/Pile Founda on) 157 23-May-18 14-Jan-19 39 14-Jan-19, Stub Design Calcula ons & Sketch (Normal/Pile Founda on)
DE_SDCR_20000 Subm. & Appr. of Stubs Design for Tower Type 1NS 35 23-May-18 13-Jul-18 33 Subm. & Appr. of Stubs Design for Tower Type 1NS
DE_SDCR_20020 Subm. & Appr. of Stubs Design for Tower Type 1LA 35 09-Jul-18 28-Aug-18 18 Subm. & Appr. of Stubs Design for Tower Type 1LA
DE_SDCR_20010 Subm. & Appr. of Stubs Design for Tower Type 1HS 35 24-Jul-18 14-Sep-18 8 Subm. & Appr. of Stubs Design for Tower Type 1HS
DE_SDCR_20030 Subm. & Appr. of Stubs Design for Tower Type 1MA 35 23-Aug-18 16-Oct-18 65 Subm. & Appr. of Stubs Design for Tower Type 1MA
DE_SDCR_20040 Subm. & Appr. of Stubs Design for Tower Type 1HA 35 08-Oct-18 26-Nov-18 37 Subm. & Appr. of Stubs Design for Tower Type 1HA
DE_SDCR_20050 Subm. & Appr. of Stubs Design for Tower Type 1DE 35 23-Nov-18 14-Jan-19 39 Subm. & Appr. of Stubs Design for Tower Type 1DE
Anchor Bolt Design for Monopole 35 11-Jun-18 31-Jul-18 152 31-Jul-18, Anchor Bolt Design for Monopole
DE_ABDCR_30000 Subm. & Appr. of 1CQL Anchor Bolt Design Calcula on Report 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQL Anchor Bolt Design Calcula on Report
DE_ABDCR_30100 Subm. & Appr. of 1CQ1 Anchor Bolt Design Calcula on Report 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQ1 Anchor Bolt Design Calcula on Report
DE_ABDCR_30200 Subm. & Appr. of 1CQ3 Anchor Bolt Design Calcula on Report 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQ3 Anchor Bolt Design Calcula on Report
DE_ABDCR_30300 Subm. & Appr. of 1CQT Anchor Bolt Design Calcula on Report 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQT Anchor Bolt Design Calcula on Report
Line Support Outline Drawings & Assembly Drawings For Construc on Phase 189 30-Apr-18 07-Feb-19 25 07-Feb-19, Line Support Outline Drawings & Assembly Drawings For Construc on Phase
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 3 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Tower Outline Drawings 150 30-Apr-18 10-Dec-18 22 10-Dec-18, Tower Outline Drawings
DE_TDD_40000 Subm. & Appr. of 1NS Tower Outline 35 30-Apr-18 21-Jun-18 19 Subm. & Appr. of 1NS Tower Outline
DE_TDD_40200 Subm. & Appr. of 1LA Tower Outline 35 06-Jun-18 26-Jul-18 55 Subm. & Appr. of 1LA Tower Outline
DE_TDD_40100 Subm. & Appr. of 1HS Tower Outline 35 29-Jun-18 17-Aug-18 84 Subm. & Appr. of 1HS Tower Outline
DE_TDD_40300 Subm. & Appr. of 1MA Tower Outline 35 20-Jul-18 13-Sep-18 72 Subm. & Appr. of 1MA Tower Outline
DE_TDD_40400 Subm. & Appr. of 1HA Tower Outline 35 06-Sep-18 29-Oct-18 37 Subm. & Appr. of 1HA Tower Outline
DE_TDD_40500 Subm. & Appr. of 1DE Tower Outline 35 22-Oct-18 10-Dec-18 22 Subm. & Appr. of 1DE Tower Outline
Tower Erec on Drawings 158 18-Jun-18 07-Feb-19 2 07-Feb-19, Tower Erec on Drawings
DE_TDD_41200 Subm. & Appr. of Typical An Climbing Device Drawing 35 18-Jun-18 06-Aug-18 112 Subm. & Appr. of Typical An Climbing Device Drawing
DE_TDD_41300 Subm. & Appr. of Designa on, Danger and Tower Number Drawing 35 18-Jun-18 06-Aug-18 112 Subm. & Appr. of Designa on, Danger and Tower Number Drawing
DE_TDD_40600 Subm. & Appr. of 1NS Tower Erec on Drawing 35 18-Jun-18 06-Aug-18 6 Subm. & Appr. of 1NS Tower Erec on Drawing
DE_TDD_40800 Subm. & Appr. of 1LA Tower Erec on Drawing 35 01-Aug-18 25-Sep-18 36 Subm. & Appr. of 1LA Tower Erec on Drawing
DE_TDD_40700 Subm. & Appr. of 1HS Tower Erec on Drawing 35 17-Aug-18 11-Oct-18 69 Subm. & Appr. of 1HS Tower Erec on Drawing
DE_TDD_40900 Subm. & Appr. of 1MA Tower Erec on Drawing 35 18-Sep-18 05-Nov-18 52 Subm. & Appr. of 1MA Tower Erec on Drawing
DE_TDD_41000 Subm. & Appr. of 1HA Tower Erec on Drawing 35 01-Nov-18 20-Dec-18 20 Subm. & Appr. of 1HA Tower Erec on Drawing
DE_TDD_41100 Subm. & Appr. of 1DE Tower Erec on Drawing 35 17-Dec-18 07-Feb-19 2 Subm. & Appr. of 1DE Tower Erec on Drawing
Stub Se ng Drawings (Normal founda on) 157 23-May-18 14-Jan-19 39 14-Jan-19, Stub Se ng Drawings (Normal founda on)
DE_TDD_41400 Subm. & Appr. of 1NS Normal Fdn Stub 35 23-May-18 13-Jul-18 33 Subm. & Appr. of 1NS Normal Fdn Stub
DE_TDD_41600 Subm. & Appr. of 1LA Normal Fdn Stub 35 09-Jul-18 28-Aug-18 18 Subm. & Appr. of 1LA Normal Fdn Stub
DE_TDD_41500 Subm. & Appr. of 1HS Normal Fdn Stub 35 24-Jul-18 14-Sep-18 8 Subm. & Appr. of 1HS Normal Fdn Stub
DE_TDD_41700 Subm. & Appr. of 1MA Normal Fdn Stub 35 23-Aug-18 16-Oct-18 65 Subm. & Appr. of 1MA Normal Fdn Stub
DE_TDD_41800 Subm. & Appr. of 1HA Normal Fdn Stub 35 08-Oct-18 26-Nov-18 37 Subm. & Appr. of 1HA Normal Fdn Stub
DE_TDD_41900 Subm. & Appr. of 1DE Normal Fdn Stub 35 23-Nov-18 14-Jan-19 39 Subm. & Appr. of 1DE Normal Fdn Stub
Stub Se ng Drawings (Pile) 35 27-Sep-18 14-Nov-18 44 14-Nov-18, Stub Se ng Drawings (Pile)
DE_TDD_42000 Subm. & Appr. of 1NS Pile Fdn Stub 35 27-Sep-18 14-Nov-18 44 Subm. & Appr. of 1NS Pile Fdn Stub
DE_TDD_42100 Subm. & Appr. of 1HS Pile Fdn Stub 35 27-Sep-18 14-Nov-18 44 Subm. & Appr. of 1HS Pile Fdn Stub
DE_TDD_42200 Subm. & Appr. of 1LA Pile Fdn Stub 35 27-Sep-18 14-Nov-18 44 Subm. & Appr. of 1LA Pile Fdn Stub
DE_TDD_42300 Subm. & Appr. of 1MA Pile Fdn Stub 35 27-Sep-18 14-Nov-18 44 Subm. & Appr. of 1MA Pile Fdn Stub
DE_TDD_42400 Subm. & Appr. of 1HA Pile Fdn Stub 35 27-Sep-18 14-Nov-18 44 Subm. & Appr. of 1HA Pile Fdn Stub
DE_TDD_42500 Subm. & Appr. of 1DE Pile Fdn Stub 35 27-Sep-18 14-Nov-18 44 Subm. & Appr. of 1DE Pile Fdn Stub
Anchor Bolt Drawings 35 11-Jun-18 31-Jul-18 152 31-Jul-18, Anchor Bolt Drawings
DE_TDD_42600 Subm. & Appr. of 1CQL Anchor Bolt Drawing 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQL Anchor Bolt Drawing
DE_TDD_42700 Subm. & Appr. of 1CQ1 Anchor Bolt Drawing 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQ1 Anchor Bolt Drawing
DE_TDD_42800 Subm. & Appr. of 1CQ3 Anchor Bolt Drawing 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQ3 Anchor Bolt Drawing
DE_TDD_42900 Subm. & Appr. of 1CQT Anchor Bolt Drawing 35 11-Jun-18 31-Jul-18 152 Subm. & Appr. of 1CQT Anchor Bolt Drawing
Founda on Design Calcula ons Reports & Sketch 188 30-Apr-18 04-Feb-19 249 04-Feb-19, Founda on Design Calcula ons Reports & Sketch
General Design for Founda on 79 30-Apr-18 24-Aug-18 73 24-Aug-18, General Design for Founda on
DE_FDND_50100 Subm. & Appr. of Concrete Mix Design (Ready Mix / Site Mix) 35 30-Apr-18 21-Jun-18 117 Subm. & Appr. of Concrete Mix Design (Ready Mix / Site Mix)
DE_FDND_50000 Subm. & Appr. of Founda on Classifica on 35 05-Jul-18 24-Aug-18 66 Subm. & Appr. of Founda on Classifica on
Tower Normal Founda on Design Calcula on Reports & Sketch 159 13-Jun-18 04-Feb-19 70 04-Feb-19, Tower Normal Founda on Design Calcula on Reports & Sketch
DE_FDND_50200 Subm. & Appr. of 1NS NF Design Report 35 13-Jun-18 02-Aug-18 33 Subm. & Appr. of 1NS NF Design Report
DE_FDND_50400 Subm. & Appr. of 1LA NF Design Report 35 30-Jul-18 21-Sep-18 70 Subm. & Appr. of 1LA NF Design Report
DE_FDND_50300 Subm. & Appr. of 1HS NF Design Report 35 14-Aug-18 08-Oct-18 71 Subm. & Appr. of 1HS NF Design Report
DE_FDND_50500 Subm. & Appr. of 1MA NF Design Report 35 13-Sep-18 01-Nov-18 134 Subm. & Appr. of 1MA NF Design Report
DE_FDND_50600 Subm. & Appr. of 1HA NF Design Report 35 29-Oct-18 17-Dec-18 91 Subm. & Appr. of 1HA NF Design Report
DE_FDND_50700 Subm. & Appr. of 1DE NF Design Report 35 14-Dec-18 04-Feb-19 65 Subm. & Appr. of 1DE NF Design Report
Monopole Normal Founda on Design Calcula on Reports & Sketch 35 25-Jun-18 13-Aug-18 366 13-Aug-18, Monopole Normal Founda on Design Calcula on Reports & Sketch
DE_FDND_50800 Subm. & Appr. of 1CQL NF Design Report 35 25-Jun-18 13-Aug-18 366 Subm. & Appr. of 1CQL NF Design Report
DE_FDND_50900 Subm. & Appr. of 1CQ1 NF Design Report 35 25-Jun-18 13-Aug-18 366 Subm. & Appr. of 1CQ1 NF Design Report
DE_FDND_51000 Subm. & Appr. of 1CQ3 NF Design Report 35 25-Jun-18 13-Aug-18 366 Subm. & Appr. of 1CQ3 NF Design Report
DE_FDND_51100 Subm. & Appr. of 1CQT NF Design Report 35 25-Jun-18 13-Aug-18 366 Subm. & Appr. of 1CQT NF Design Report
Tower Pile Founda on Design Calcula on Reports & Sketch 129 09-Jul-18 16-Jan-19 78 16-Jan-19, Tower Pile Founda on Design Calcula on Reports & Sketch
DE_FDND_51200 Subm. & Appr. of Single Pile Capacity and Pile Set Criteria Design 30 09-Jul-18 20-Aug-18 45 Subm. & Appr. of Single Pile Capacity and Pile Set Criteria Design
DE_FDND_51300 Subm. & Appr. of 1NS PF Design 35 24-Sep-18 09-Nov-18 46 Subm. & Appr. of 1NS PF Design
DE_FDND_51500 Subm. & Appr. of 1HA PF Design 45 24-Sep-18 26-Nov-18 72 Subm. & Appr. of 1HA PF Design
DE_FDND_51600 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/4 - T5/7 35 12-Nov-18 02-Jan-19 46 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/4 - T5/7
DE_FDND_51700 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/8 - T5/11 35 12-Nov-18 02-Jan-19 53 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/8 - T5/11
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 4 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
DE_FDND_51800 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/12, T5/13, T5/15 35 12-Nov-18 02-Jan-19 54 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/12, T5/13, T5/15
DE_FDND_51900 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/16 - T5/19 35 12-Nov-18 02-Jan-19 88 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 T5/16 - T5/19
DE_FDND_52000 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 AT6, T5/14 35 27-Nov-18 16-Jan-19 72 Subm. & Appr. of Tower Geotechnical Design - Sec on 3 AT6, T5/14
Monopole Pile Founda on Design Calcula on Reports & Sketch 80 24-Sep-18 16-Jan-19 218 16-Jan-19, Monopole Pile Founda on Design Calcula on Reports & Sketch
DE_FDND_52200 Subm. & Appr. of 1CQ1 PF Design Report 35 24-Sep-18 09-Nov-18 137 Subm. & Appr. of 1CQ1 PF Design Report
DE_FDND_52300 Subm. & Appr. of 1CQ3 PF Design Report 35 24-Sep-18 09-Nov-18 92 Subm. & Appr. of 1CQ3 PF Design Report
DE_FDND_52400 Subm. & Appr. of 1CQT PF Design Report 35 24-Sep-18 09-Nov-18 242 Subm. & Appr. of 1CQT PF Design Report
DE_FDND_52100 Subm. & Appr. of 1CQL PF Design Report 35 09-Oct-18 27-Nov-18 133 Subm. & Appr. of 1CQL PF Design Report
DE_FDND_52500 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/2, T7/3, T7/5, T7/645 07-Nov-18 11-Jan-19 147 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/2, T7/3, T7/5, T7/6
DE_FDND_52600 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/7, T7/8, T7/11, T7/12
45 07-Nov-18 11-Jan-19 160 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/7, T7/8, T7/11, T7/12
DE_FDND_52700 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/13, T7/16, T7/17, T7/18,
45 T7/20 07-Nov-18 11-Jan-19 160 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/13, T7/16, T7/17, T7/18, T7/20
DE_FDND_52800 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/1, T7/4, T7/9, T7/1045(CQ1) 12-Nov-18 16-Jan-19 137 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/1, T7/4, T7/9, T7/10 (CQ1)
DE_FDND_52900 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/14, T7/15, T7/19 (CQ1)
45 12-Nov-18 16-Jan-19 211 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 T7/14, T7/15, T7/19 (CQ1)
DE_FDND_53000 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 AT7 (CQ3) 21 12-Nov-18 11-Dec-18 92 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 AT7 (CQ3)
DE_FDND_53100 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 AT8 (CQT) 21 12-Nov-18 11-Dec-18 242 Subm. & Appr. of Tower Geotechnical Design - Sec on 4 AT8 (CQT)
Founda on Drawings For Construc on Phase 159 13-Jun-18 04-Feb-19 211 04-Feb-19, Founda on Drawings For Construc on Phase
Tower Normal Founda on Drawings 159 13-Jun-18 04-Feb-19 70 04-Feb-19, Tower Normal Founda on Drawings
DE_FDNDW_60000 Subm. & Appr. of 1NS LF Drawings 35 13-Jun-18 02-Aug-18 33 Subm. & Appr. of 1NS LF Drawings
DE_FDNDW_60100 Subm. & Appr. of 1NS HF Drawings 35 13-Jun-18 02-Aug-18 33 Subm. & Appr. of 1NS HF Drawings
DE_FDNDW_60400 Subm. & Appr. of 1LA LF Drawings 35 30-Jul-18 21-Sep-18 70 Subm. & Appr. of 1LA LF Drawings
DE_FDNDW_60500 Subm. & Appr. of 1LA HF Drawings 35 30-Jul-18 21-Sep-18 70 Subm. & Appr. of 1LA HF Drawings
DE_FDNDW_60200 Subm. & Appr. of 1HS LF Drawings 35 14-Aug-18 08-Oct-18 71 Subm. & Appr. of 1HS LF Drawings
DE_FDNDW_60300 Subm. & Appr. of 1HS HF Drawings 35 14-Aug-18 08-Oct-18 71 Subm. & Appr. of 1HS HF Drawings
DE_FDNDW_60600 Subm. & Appr. of 1MA LF Drawings 35 13-Sep-18 01-Nov-18 134 Subm. & Appr. of 1MA LF Drawings
DE_FDNDW_60700 Subm. & Appr. of 1MA HF Drawings 35 13-Sep-18 01-Nov-18 134 Subm. & Appr. of 1MA HF Drawings
DE_FDNDW_60800 Subm. & Appr. of 1HA LF Drawings 35 29-Oct-18 17-Dec-18 91 Subm. & Appr. of 1HA LF Drawings
DE_FDNDW_60900 Subm. & Appr. of 1HA HF Drawings 35 29-Oct-18 17-Dec-18 91 Subm. & Appr. of 1HA HF Drawings
DE_FDNDW_61000 Subm. & Appr. of 1DE LF Drawings 35 14-Dec-18 04-Feb-19 65 Subm. & Appr. of 1DE LF Drawings
DE_FDNDW_61100 Subm. & Appr. of 1DE HF Drawings 35 14-Dec-18 04-Feb-19 65 Subm. & Appr. of 1DE HF Drawings
Tower Pile Founda on Drawings 35 24-Sep-18 09-Nov-18 167 09-Nov-18, Tower Pile Founda on Drawings
DE_FDNDW_61200 Subm. & Appr. of 1NS Tower Pile Point Drawings 35 24-Sep-18 09-Nov-18 60 Subm. & Appr. of 1NS Tower Pile Point Drawings
DE_FDNDW_61300 Subm. & Appr. of 1HA Tower Pile Point Drawings 35 24-Sep-18 09-Nov-18 117 Subm. & Appr. of 1HA Tower Pile Point Drawings
DE_FDNDW_61400 Subm. & Appr. of 1NS Tower Pilecap Drawings 35 24-Sep-18 09-Nov-18 83 Subm. & Appr. of 1NS Tower Pilecap Drawings
DE_FDNDW_61500 Subm. & Appr. of 1HA Tower Pilecap Drawings 35 24-Sep-18 09-Nov-18 167 Subm. & Appr. of 1HA Tower Pilecap Drawings
Monopole Pile Founda on Drawings 58 24-Sep-18 13-Dec-18 246 13-Dec-18, Monopole Pile Founda on Drawings
DE_FDNDW_61700 Subm. & Appr. of 1CQ1 Pile Point Drawings 35 24-Sep-18 09-Nov-18 137 Subm. & Appr. of 1CQ1 Pile Point Drawings
DE_FDNDW_61800 Subm. & Appr. of 1CQ3 Pile Point Drawings 35 24-Sep-18 09-Nov-18 92 Subm. & Appr. of 1CQ3 Pile Point Drawings
DE_FDNDW_61900 Subm. & Appr. of 1CQT Pile Point Drawings 35 24-Sep-18 09-Nov-18 257 Subm. & Appr. of 1CQT Pile Point Drawings
DE_FDNDW_61600 Subm. & Appr. of 1CQL Pile Point Drawings 35 09-Oct-18 27-Nov-18 133 Subm. & Appr. of 1CQL Pile Point Drawings
DE_FDNDW_62100 Subm. & Appr. of 1CQ1 Pilecap Drawings 35 10-Oct-18 28-Nov-18 137 Subm. & Appr. of 1CQ1 Pilecap Drawings
DE_FDNDW_62200 Subm. & Appr. of 1CQ3 Pilecap Drawings 35 10-Oct-18 28-Nov-18 131 Subm. & Appr. of 1CQ3 Pilecap Drawings
DE_FDNDW_62300 Subm. & Appr. of 1CQT Pilecap Drawings 35 10-Oct-18 28-Nov-18 257 Subm. & Appr. of 1CQT Pilecap Drawings
DE_FDNDW_62000 Subm. & Appr. of 1CQL Pilecap Drawings 35 25-Oct-18 13-Dec-18 133 Subm. & Appr. of 1CQL Pilecap Drawings
Inspec on and Test Plan 458 08-Mar-18 20-Jan-20 12 20-Jan-20, Inspec on and Test Plan
Field Inves ga on Report 130 04-May-18 14-Nov-18 185 14-Nov-18, Field Inves ga on Report
DE_FIR_10000 Subm. & Appr. of Soil Probe Test Report Sec on 1 21 04-May-18 05-Jun-18 81 Subm. & Appr. of Soil Probe Test Report Sec on 1
DE_FIR_10100 Subm. & Appr. of Soil Probe Test Report Sec on 2 21 15-May-18 14-Jun-18 74 Subm. & Appr. of Soil Probe Test Report Sec on 2
DE_FIR_10300 Subm. & Appr. of Soil Probe Test Report Sec on 4 21 15-May-18 14-Jun-18 74 Subm. & Appr. of Soil Probe Test Report Sec on 4
DE_FIR_10200 Subm. & Appr. of Soil Probe Test Report Sec on 3 21 25-May-18 27-Jun-18 66 Subm. & Appr. of Soil Probe Test Report Sec on 3
DE_FIR_11700 Subm. & Appr. of Borehole Report Sec on 4 - T7/20 - AT8 45 28-Jun-18 03-Sep-18 45 Subm. & Appr. of Borehole Report Sec on 4 - T7/20 - AT8
DE_FIR_11600 Subm. & Appr. of Borehole Report Sec on 4 - T7/16 - T7/19 45 12-Jul-18 20-Sep-18 224 Subm. & Appr. of Borehole Report Sec on 4 - T7/16 - T7/19
DE_FIR_11100 Subm. & Appr. of Borehole Report Sec on 3 - T5/17 - AT6 45 27-Jul-18 04-Oct-18 83 Subm. & Appr. of Borehole Report Sec on 3 - T5/17 - AT6
DE_FIR_11500 Subm. & Appr. of Borehole Report Sec on 4 - T7/12 - T7/15 45 27-Jul-18 04-Oct-18 214 Subm. & Appr. of Borehole Report Sec on 4 - T7/12 - T7/15
DE_FIR_11000 Subm. & Appr. of Borehole Report Sec on 3 - T5/13 - T5/16 45 10-Aug-18 18-Oct-18 73 Subm. & Appr. of Borehole Report Sec on 3 - T5/13 - T5/16
DE_FIR_11400 Subm. & Appr. of Borehole Report Sec on 4 - T7/8 - T7/11 45 10-Aug-18 18-Oct-18 184 Subm. & Appr. of Borehole Report Sec on 4 - T7/8 - T7/11
DE_FIR_10900 Subm. & Appr. of Borehole Report Sec on 3 - T5/9 - T5/12 45 27-Aug-18 01-Nov-18 63 Subm. & Appr. of Borehole Report Sec on 3 - T5/9 - T5/12
DE_FIR_11300 Subm. & Appr. of Borehole Report Sec on 4 - T7/4 - T7/7 45 27-Aug-18 01-Nov-18 174 Subm. & Appr. of Borehole Report Sec on 4 - T7/4 - T7/7
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 5 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
DE_FIR_10800 Subm. & Appr. of Borehole Report Sec on 3 - T5/5 - T5/8 45 11-Sep-18 14-Nov-18 54 Subm. & Appr. of Borehole Report Sec on 3 - T5/5 - T5/8
DE_FIR_11200 Subm. & Appr. of Borehole Report Sec on 4 - AT7 - T7/3 30 11-Sep-18 24-Oct-18 104 Subm. & Appr. of Borehole Report Sec on 4 - AT7 - T7/3
DE_FIR_10700 Subm. & Appr. of Borehole Report Sec on 3 - T5/4 14 18-Sep-18 05-Oct-18 44 Subm. & Appr. of Borehole Report Sec on 3 - T5/4
Design / Type Test Procedure & Report 69 14-Jun-18 27-Sep-18 123 27-Sep-18, Design / Type Test Procedure & Report
DE_TEST_10000 Subm. & Appr. of Insulator Type Test Procedure & Report 30 14-Jun-18 27-Jul-18 53 Subm. & Appr. of Insulator Type Test Procedure & Report
DE_TEST_10100 Subm. & Appr. of Conductor Type Test Procedure & Report 30 14-Jun-18 27-Jul-18 65 Subm. & Appr. of Conductor Type Test Procedure & Report
DE_TEST_10200 Subm. & Appr. of OPGW Type Test Procedure & Report 30 14-Jun-18 27-Jul-18 61 Subm. & Appr. of OPGW Type Test Procedure & Report
DE_TEST_10300 Subm. & Appr. of OPUG Type Test Procedure & Report 30 14-Jun-18 27-Jul-18 61 Subm. & Appr. of OPUG Type Test Procedure & Report
DE_TEST_10600 Subm. & Appr. of Insulator String Type Test Procedure & Report 30 14-Jun-18 27-Jul-18 53 Subm. & Appr. of Insulator String Type Test Procedure & Report
DE_TEST_10400 Subm. & Appr. of Damper Type Test Procedure & Report 30 06-Jul-18 17-Aug-18 49 Subm. & Appr. of Damper Type Test Procedure & Report
DE_TEST_10500 Subm. & Appr. of Spacer Type Test Procedure & Report 30 06-Jul-18 17-Aug-18 49 Subm. & Appr. of Spacer Type Test Procedure & Report
DE_TEST_11100 Subm. & Appr. of Plate Bearing Test Proceduce & Report 30 13-Jul-18 27-Aug-18 68 Subm. & Appr. of Plate Bearing Test Proceduce & Report
DE_TEST_10900 Subm. & Appr. of Normal Founda on Upli Test Procedure & Report 30 13-Jul-18 27-Aug-18 33 Subm. & Appr. of Normal Founda on Upli Test Procedure & Report
DE_TEST_11200 Subm. & Appr. of PDA Test Proceduce & Report 30 18-Jul-18 30-Aug-18 139 Subm. & Appr. of PDA Test Proceduce & Report
DE_TEST_11000 Subm. & Appr. of Pile Founda on Upli , Compression & Lateral Test Proceduce30
& Report 18-Jul-18 30-Aug-18 57 Subm. & Appr. of Pile Founda on Upli , Compression & Lateral Test Proceduce & Report
DE_TEST_10700 Subm. & Appr. of Tower Prototype Assembly Test Procedure & Report (with Erec21on Drawing)24-Aug-18 27-Sep-18 5 Subm. & Appr. of Tower Prototype Assembly Test Procedure & Report (with Erec on Drawing)
DE_TEST_10800 Subm. & Appr. of Tower Load Test Procedure & Report 21 24-Aug-18 27-Sep-18 5 Subm. & Appr. of Tower Load Test Procedure & Report
FAT Procedure & Report 155 08-Oct-18 22-May-19 65 22-May-19, FAT Procedure & Report
DE_FATR_10300 Subm. & Appr. of OPUG FAT Procedure & Report 30 08-Oct-18 16-Nov-18 180 Subm. & Appr. of OPUG FAT Procedure & Report
DE_FATR_10500 Subm. & Appr. of Steel La ce FAT Procedure & Report 30 29-Nov-18 11-Jan-19 15 Subm. & Appr. of Steel La ce FAT Procedure & Report
DE_FATR_10600 Subm. & Appr. of Monopoles FAT Procedure & Report 30 29-Nov-18 11-Jan-19 15 Subm. & Appr. of Monopoles FAT Procedure & Report
DE_FATR_10200 Subm. & Appr. of OPGW FAT Procedure & Report 30 04-Mar-19 12-Apr-19 80 Subm. & Appr. of OPGW FAT Procedure & Report
DE_FATR_10400 Subm. & Appr. of Line Fi ngs FAT Procedure & Report 30 14-Mar-19 25-Apr-19 72 Subm. & Appr. of Line Fi ngs FAT Procedure & Report
DE_FATR_10000 Subm. & Appr. of Insulator FAT Procedure & Report 30 18-Mar-19 29-Apr-19 63 Subm. & Appr. of Insulator FAT Procedure & Report
DE_FATR_10100 Subm. & Appr. of Conductor FAT Procedure & Report 30 25-Mar-19 07-May-19 75 Subm. & Appr. of Conductor FAT Procedure & Report
DE_FATR_10700 Subm. & Appr. of ATN FAT Procedure & Report 30 08-Apr-19 22-May-19 62 Subm. & Appr. of ATN FAT Procedure & Report
Field Rou ne Test Procedures & Report 223 16-Jul-18 14-Jun-19 46 14-Jun-19, Field Rou ne Test Procedures & Report
DE_FRT_10000 Subm. & Appr. of Tower Earth Resistance Test Procedure & Report 30 16-Jul-18 28-Aug-18 135 Subm. & Appr. of Tower Earth Resistance Test Procedure & Report
DE_FRT_10200 Subm. & Appr. of OPGW Drum Test Procedure & Report 30 11-Apr-19 27-May-19 57 Subm. & Appr. of OPGW Drum Test Procedure & Report
DE_FRT_10100 Subm. & Appr. of Mid Span Joint Resistance Test Procedure & Report 30 29-Apr-19 14-Jun-19 46 Subm. & Appr. of Mid Span Joint Resistance Test Procedure & Report
Final Line Test 14 31-Dec-19 20-Jan-20 12 20-Jan-20, Final Line Test
DE_FLT_10000 Subm. & Appr. of Final Line Tes ng Procedure & Report 14 31-Dec-19 20-Jan-20 12 Subm. & Appr. of Final Line Tes ng Procedure &
DE_FLT_10100 Subm. & Appr. of Earth Resistance Test procedure & Report 14 31-Dec-19 20-Jan-20 12 Subm. & Appr. of Earth Resistance Test procedu
DE_FLT_10200 Subm. & Appr. of OTDR Test procedure & Report 14 31-Dec-19 20-Jan-20 12 Subm. & Appr. of OTDR Test procedure & Repo
DE_FLT_10300 Subm. & Appr. of Power Meter Test (End to End Test) 14 31-Dec-19 20-Jan-20 12 Subm. & Appr. of Power Meter Test (End to End
Method Statement 138 08-Mar-18 02-Oct-18 231 02-Oct-18, Method Statement
DE_MS_10000 Subm. & Appr. of MS Line Route Survey 14 08-Mar-18 27-Mar-18 0 Subm. & Appr. of MS Line Route Survey
DE_MS_10100 Subm. & Appr. of MS SI Works 14 16-Apr-18 04-May-18 43 Subm. & Appr. of MS SI Works
DE_MS_10200 Subm. & Appr. of MS Vegeta on Clearing 14 30-Apr-18 18-May-18 42 Subm. & Appr. of MS Vegeta on Clearing
DE_MS_10400 Subm. & Appr. of MS Piling Works 20 15-May-18 13-Jun-18 160 Subm. & Appr. of MS Piling Works
DE_MS_10300 Subm. & Appr. of MS Founda on Works 20 30-May-18 29-Jun-18 111 Subm. & Appr. of MS Founda on Works
DE_MS_10700 Subm. & Appr. of MS Tower Earthing 20 30-May-18 29-Jun-18 111 Subm. & Appr. of MS Tower Earthing
DE_MS_10500 Subm. & Appr. of MS Tower Erec on 20 02-Jul-18 30-Jul-18 231 Subm. & Appr. of MS Tower Erec on
DE_MS_10600 Subm. & Appr. of MS Stringing and Sagging 20 30-Aug-18 02-Oct-18 231 Subm. & Appr. of MS Stringing and Sagging
DE_MS_10800 Subm. & Appr. of MS OPGW Join ng & Splicing 20 30-Aug-18 02-Oct-18 231 Subm. & Appr. of MS OPGW Join ng & Splicing
DE_MS_10900 Subm. & Appr. of MS Mid Span Joint & Repair of Damage Conductor 20 30-Aug-18 02-Oct-18 231 Subm. & Appr. of MS Mid Span Joint & Repair of Damage Conductor
Procurement, Manufacturing, FAT and Delivery 440 28-Apr-18 30-Oct-19 84 30-Oct-19, Procurement, Manufacturing, FAT and Delivery
Procurement 86 28-Apr-18 14-Aug-18 118 14-Aug-18, Procurement
PRO_10200 Issuance of Purchase Order for OPGW 1 28-Apr-18 28-Apr-18 7 Issuance of Purchase Order for OPGW
PRO_10300 Issuance of Purchase Order for OPUG 1 28-Apr-18 28-Apr-18 7 Issuance of Purchase Order for OPUG
PRO_11100 Issuance of Purchase Order for ATN 1 28-Apr-18 28-Apr-18 45 Issuance of Purchase Order for ATN
PRO_10100 Issuance of Purchase Order for Tower Structures 1 28-Apr-18 28-Apr-18 133 Issuance of Purchase Order for Tower Structures
PRO_10400 Issuance of Purchase Order for Insulator 1 28-Apr-18 28-Apr-18 7 Issuance of Purchase Order for Insulator
PRO_10500 Issuance of Purchase Order for Conductor 1 28-Apr-18 28-Apr-18 7 Issuance of Purchase Order for Conductor
PRO_10000 Issuance of Purchase Order for Stubs 1 28-Apr-18 28-Apr-18 118 Issuance of Purchase Order for Stubs
PRO_10700 Issuance of Purchase Order for Warning Sphere 1 28-Apr-18 28-Apr-18 45 Issuance of Purchase Order for Warning Sphere
PRO_11000 Issuance of Purchase Order for Spun Pile 1 14-May-18 14-May-18 191 Issuance of Purchase Order for Spun Pile
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 6 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
PRO_10900 Issuance of Purchase Order for Tower Earthing 1 21-May-18 21-May-18 54 Issuance of Purchase Order for Tower Earthing
PRO_10600 Issuance of Purchase Order for Line Fi ngs 1 21-May-18 21-May-18 57 Issuance of Purchase Order for Line Fi ngs
PRO_10800 Issuance of Purchase Order for Avia on Light 1 14-Aug-18 14-Aug-18 47 Issuance of Purchase Order for Avia on Light
Manufaturing 447 06-Jul-18 25-Sep-19 93 25-Sep-19, Manufaturing
Stubs Manufacturing 123 15-Sep-18 15-Jan-19 55 15-Jan-19, Stubs Manufacturing
MAN_20000 Stubs Manufacturing Batch 1 40 15-Sep-18 24-Oct-18 13 Stubs Manufacturing Batch 1
MAN_20100 Stubs Manufacturing Batch 2 50 27-Nov-18 15-Jan-19 55 Stubs Manufacturing Batch 2
Achor Bolt 50 01-Aug-18 19-Sep-18 226 19-Sep-18, Achor Bolt
MAN_20200 Anchor Bolt Batch 1 50 01-Aug-18 19-Sep-18 226 Anchor Bolt Batch 1
Tower Structures Manufacturing 110 29-Nov-18 18-Mar-19 4 18-Mar-19, Tower Structures Manufacturing
MAN_20400 Tower Structure Manufacturing Batch 1 60 29-Nov-18 27-Jan-19 7 Tower Structure Manufacturing Batch 1
MAN_20500 Tower Structure Manufacturing Batch 2 60 18-Jan-19 18-Mar-19 4 Tower Structure Manufacturing Batch 2
Insulators Manufacturing 60 16-Mar-19 14-May-19 82 14-May-19, Insulators Manufacturing
MAN_20600 Insulator Disc Manufacturing 60 16-Mar-19 14-May-19 82 Insulator Disc Manufacturing
AAAC Sycamore Conductor Manufacturing 120 23-Mar-19 20-Jul-19 160 20-Jul-19, AAAC Sycamore Conductor Manufacturing
MAN_20700 Conductor Manufacturing Batch 1 60 23-Mar-19 21-May-19 99 Conductor Manufacturing Batch 1
MAN_20710 Conductor Manufacturing Batch 2 60 22-May-19 20-Jul-19 160 Conductor Manufacturing Batch 2
OPGW Manufacturing 180 02-Mar-19 28-Aug-19 92 28-Aug-19, OPGW Manufacturing
MAN_20800 OPGW Manufacturing Batch 1 40 02-Mar-19 10-Apr-19 89 OPGW Manufacturing Batch 1
MAN_20810 OPGW Manufacturing Batch 2 40 20-Jul-19 28-Aug-19 92 OPGW Manufacturing Batch 2
Line Fi ngs Manufacturing 105 14-Mar-19 26-Jun-19 184 26-Jun-19, Line Fi ngs Manufacturing
MAN_20900 Line Fi ng Manufacturing Batch 1 45 14-Mar-19 27-Apr-19 72 Line Fi ng Manufacturing Batch 1
MAN_21000 Line Fi ng Manufacturing Batch 2 60 28-Apr-19 26-Jun-19 184 Line Fi ng Manufacturing Batch 2
Micellaneous Item Manufacturing 447 06-Jul-18 25-Sep-19 60 25-Sep-19, Micellaneous Item Manufacturing
MAN_21400 Tower Earthing Manufacturing 50 06-Jul-18 24-Aug-18 74 Tower Earthing Manufacturing
MAN_21100 OPUG Manufacturing 40 06-Oct-18 14-Nov-18 269 OPUG Manufacturing
MAN_21500 ATN Manufacturing 75 06-Apr-19 19-Jun-19 65 ATN Manufacturing
MAN_21200 Warning Sphere Manufacturing 50 07-Aug-19 25-Sep-19 60 Warning Sphere Manufacturing
MAN_21300 Ava on Light Manufacturing 50 07-Aug-19 25-Sep-19 60 Ava on Light Manufacturing
Tower Loading Test 89 07-Aug-18 26-Nov-18 46 26-Nov-18, Tower Loading Test
Tower Loading Test Tower 1LA 51 26-Sep-18 26-Nov-18 46 26-Nov-18, Tower Loading Test Tower 1LA
TWR_LOAD_30300 Fabrica on of Tower Type 1LA for Tes ng 14 26-Sep-18 11-Oct-18 46 Fabrica on of Tower Type 1LA for Tes ng
TWR_LOAD_30400 Inspec on of Tower Type 1LA Prototype 6 03-Nov-18 09-Nov-18 46 Inspec on of Tower Type 1LA Prototype
TWR_LOAD_30500 Tower Loading Test of Tower Type 1LA 6 19-Nov-18 26-Nov-18 46 Tower Loading Test of Tower Type 1LA
Tower Loading Test Tower 1NS 59 07-Aug-18 20-Oct-18 6 20-Oct-18, Tower Loading Test Tower 1NS
TWR_LOAD_30000 Fabrica on of Tower Type 1NS for Tes ng 14 07-Aug-18 23-Aug-18 7 Fabrica on of Tower Type 1NS for Tes ng
TWR_LOAD_30100 Inspec on of Tower Type 1NS Prototype 6 28-Sep-18 04-Oct-18 6 Inspec on of Tower Type 1NS Prototype
TWR_LOAD_30200 Tower Loading Test of Tower Type 1NS 6 15-Oct-18 20-Oct-18 6 Tower Loading Test of Tower Type 1NS
Electrical Type Test 30 14-Sep-18 20-Oct-18 64 20-Oct-18, Electrical Type Test
ELEC_TT_31000 Type Test for Conductor 6 14-Sep-18 21-Sep-18 78 Type Test for Conductor
ELEC_TT_33000 Type Test for OPGW & OPUG 6 29-Sep-18 05-Oct-18 73 Type Test for OPGW & OPUG
ELEC_TT_32000 Type Test for Line Fi ngs 10 06-Oct-18 18-Oct-18 59 Type Test for Line Fi ngs
ELEC_TT_30000 Type Test for Insulator 6 15-Oct-18 20-Oct-18 64 Type Test for Insulator
Factory Acceptance Test (FAT) 178 28-Jan-19 06-Sep-19 97 06-Sep-19, Factory Acceptance Test (FAT)
Tower Structures FAT 47 28-Jan-19 25-Mar-19 4 25-Mar-19, Tower Structures FAT
FAT_40000 Tower Structure FAT Batch 1 6 28-Jan-19 02-Feb-19 6 Tower Structure FAT Batch 1
FAT_40100 Tower Structure FAT Batch 2 6 19-Mar-19 25-Mar-19 4 Tower Structure FAT Batch 2
Insulators FAT 6 15-May-19 22-May-19 64 22-May-19, Insulators FAT
FAT_40200 Insulator Disc FAT 6 15-May-19 22-May-19 64 Insulator Disc FAT
Conductor FAT 54 22-May-19 29-Jul-19 128 29-Jul-19, Conductor FAT
FAT_40300 Conductor FAT Batch 1 6 22-May-19 28-May-19 79 Conductor FAT Batch 1
FAT_40400 Conductor FAT Batch 2 6 23-Jul-19 29-Jul-19 128 Conductor FAT Batch 2
OPGW & OPUG FAT 115 13-Apr-19 06-Sep-19 73 06-Sep-19, OPGW & OPUG FAT
FAT_40500 OPGW & OPUG FAT Batch 1 6 13-Apr-19 20-Apr-19 97 OPGW & OPUG FAT Batch 1
FAT_40600 OPGW & OPUG FAT BAtch 2 6 29-Aug-19 06-Sep-19 73 OPGW & OPUG FAT BAtch 2
Line Fi ngs FAT 51 29-Apr-19 03-Jul-19 149 03-Jul-19, Line Fi ngs FAT
FAT_40700 Line Fi ngs FAT Batch 1 6 29-Apr-19 06-May-19 85 Line Fi ngs FAT Batch 1
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 7 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
FAT_40800 Line Fi ngs FAT Batch 2 6 27-Jun-19 03-Jul-19 149 Line Fi ngs FAT Batch 2
CIDB Steel Test 42 09-Oct-18 28-Nov-18 44 28-Nov-18, CIDB Steel Test
CIDB_1000 Conduct CIDB Tes ng for Raw Material Tower Batch 1 (before manufacturing) 6 09-Oct-18 16-Oct-18 42 Conduct CIDB Tes ng for Raw Material Tower Batch 1 (before manufacturing)
CIDB_1010 Conduct CIDB Tes ng for Raw Material Tower Batch 2 (before manufacturing) 6 22-Nov-18 28-Nov-18 44 Conduct CIDB Tes ng for Raw Material Tower Batch 2 (before manufacturing)
Delivery 346 25-Aug-18 30-Oct-19 84 30-Oct-19, Delivery
Stubs Delivery 110 25-Oct-18 07-Mar-19 45 07-Mar-19, Stubs Delivery
DELI_50000 Stubs Delivery Batch 1 30 25-Oct-18 29-Nov-18 11 Stubs Delivery Batch 1
DELI_50100 Stubs Delivery Batch 2 30 30-Jan-19 07-Mar-19 45 Stubs Delivery Batch 2
Anchor Bolt Delivery 30 20-Sep-18 25-Oct-18 186 25-Oct-18, Anchor Bolt Delivery
DELI_51410 Anchor Bolt Batch 1 30 20-Sep-18 25-Oct-18 186 Anchor Bolt Batch 1
Tower Structures Delivery 71 04-Feb-19 30-Apr-19 4 30-Apr-19, Tower Structures Delivery
DELI_50200 Tower Structure Delivery Batch 1 30 04-Feb-19 12-Mar-19 6 Tower Structure Delivery Batch 1
DELI_50300 Tower Structure Delivery Batch 2 30 26-Mar-19 30-Apr-19 4 Tower Structure Delivery Batch 2
Insulator Discs Delivery 30 23-May-19 01-Jul-19 64 01-Jul-19, Insulator Discs Delivery
DELI_50400 Insulator Disc Delivery 30 23-May-19 01-Jul-19 64 Insulator Disc Delivery
AAAC Sycamore Conductor Delivery 78 29-May-19 05-Sep-19 128 05-Sep-19, AAAC Sycamore Conductor Delivery
DELI_50500 AAAC Sycamore Conductor Delivery Batch 1 30 29-May-19 06-Jul-19 79 AAAC Sycamore Conductor Delivery Batch 1
DELI_50600 AAAC Sycamore Conductor Delivery Batch 2 30 30-Jul-19 05-Sep-19 128 AAAC Sycamore Conductor Delivery Batch 2
OPGW & OPUG Delivery 110 28-May-19 15-Oct-19 73 15-Oct-19, OPGW & OPUG Delivery
DELI_50700 OPGW Delivery Batch 1 30 28-May-19 05-Jul-19 68 OPGW Delivery Batch 1
DELI_50800 OPGW & OPUG Delivery Batch 2 30 07-Sep-19 15-Oct-19 73 OPGW & OPUG Delivery Batch 2
Line Fi ngs Delivery 46 15-Jun-19 08-Aug-19 149 08-Aug-19, Line Fi ngs Delivery
DELI_50900 Line Fi ng Delivery Batch 1 30 15-Jun-19 19-Jul-19 56 Line Fi ng Delivery Batch 1
DELI_51000 Line Fi ng Delivery Batch 2 30 04-Jul-19 08-Aug-19 149 Line Fi ng Delivery Batch 2
Micellaneous Item Delivery 346 25-Aug-18 30-Oct-19 50 30-Oct-19, Micellaneous Item Delivery
DELI_51300 Tower Earthing Delivery 30 25-Aug-18 03-Oct-18 58 Tower Earthing Delivery
DELI_51400 ATN Delivery 30 20-Jun-19 25-Jul-19 54 ATN Delivery
DELI_51100 Warning Sphere Delivery 30 26-Sep-19 30-Oct-19 50 Warning Sphere Delivery
DELI_51200 Avia on Light Delivery 30 26-Sep-19 30-Oct-19 50 Avia on Light Delivery
Site Construc ons 529 28-Mar-18 15-Jan-20 21 15-Jan-20, Site Construc ons
Survey Works 27 28-Mar-18 28-Apr-18 43 28-Apr-18, Survey Works
Sec on 1 - AT1 - AT4 9 28-Mar-18 07-Apr-18 3 07-Apr-18, Sec on 1 - AT1 - AT4
SW_10000 Survey Wk : Sec on 1 - AT1 - AT3 3 28-Mar-18 31-Mar-18 3 Survey Wk : Sec on 1 - AT1 - AT3
SW_10010 Survey Wk : Sec on 1 - T3/1 - T3/3 3 02-Apr-18 04-Apr-18 3 Survey Wk : Sec on 1 - T3/1 - T3/3
SW_10020 Survey Wk : Sec on 1 - T3/4 - AT4 3 05-Apr-18 07-Apr-18 3 Survey Wk : Sec on 1 - T3/4 - AT4
Sec on 2 - T4/1 - AT5 9 09-Apr-18 18-Apr-18 43 18-Apr-18, Sec on 2 - T4/1 - AT5
SW_10030 Survey Wk : Sec on 2 - T4/1 - T4/4 3 09-Apr-18 11-Apr-18 43 Survey Wk : Sec on 2 - T4/1 - T4/4
SW_10040 Survey Wk : Sec on 2 - T4/5 - T4/8 3 12-Apr-18 14-Apr-18 43 Survey Wk : Sec on 2 - T4/5 - T4/8
SW_10050 Survey Wk : Sec on 2 - T4/9 - AT5 3 16-Apr-18 18-Apr-18 43 Survey Wk : Sec on 2 - T4/9 - AT5
Sec on 3 - T5/1 - AT6 9 19-Apr-18 28-Apr-18 43 28-Apr-18, Sec on 3 - T5/1 - AT6
SW_10060 Survey Wk : Sec on 3 - T5/1 - T5/4 3 19-Apr-18 21-Apr-18 43 Survey Wk : Sec on 3 - T5/1 - T5/4
SW_10100 Survey Wk : Sec on 3 - T5/17 - AT6 3 19-Apr-18 21-Apr-18 43 Survey Wk : Sec on 3 - T5/17 - AT6
SW_10070 Survey Wk : Sec on 3 - T5/5 - T5/8 3 23-Apr-18 25-Apr-18 43 Survey Wk : Sec on 3 - T5/5 - T5/8
SW_10090 Survey Wk : Sec on 3 - T5/13 - T5/16 3 23-Apr-18 25-Apr-18 43 Survey Wk : Sec on 3 - T5/13 - T5/16
SW_10080 Survey Wk : Sec on 3 - T5/9 - T5/12 3 26-Apr-18 28-Apr-18 43 Survey Wk : Sec on 3 - T5/9 - T5/12
Sec on 4 - AT7 - AT8 (Monopoles) 18 28-Mar-18 18-Apr-18 0 18-Apr-18, Sec on 4 - AT7 - AT8 (Monopoles)
SW_10110 Survey Wk : Sec on 4 - AT7 - T7/3 3 28-Mar-18 31-Mar-18 0 Survey Wk : Sec on 4 - AT7 - T7/3
SW_10120 Survey Wk : Sec on 4 - T7/4 - T7/7 3 02-Apr-18 04-Apr-18 0 Survey Wk : Sec on 4 - T7/4 - T7/7
SW_10130 Survey Wk : Sec on 4 - T7/8 - T7/11 3 05-Apr-18 07-Apr-18 0 Survey Wk : Sec on 4 - T7/8 - T7/11
SW_10140 Survey Wk : Sec on 4 - T7/12 - T7/15 3 09-Apr-18 11-Apr-18 0 Survey Wk : Sec on 4 - T7/12 - T7/15
SW_10150 Survey Wk : Sec on 4 - T7/16 - T7/19 3 12-Apr-18 14-Apr-18 0 Survey Wk : Sec on 4 - T7/16 - T7/19
SW_10160 Survey Wk : Sec on 4 - T7/20 - AT8 3 16-Apr-18 18-Apr-18 0 Survey Wk : Sec on 4 - T7/20 - AT8
Soil Inves ga ons 75 12-Jun-18 14-Sep-18 122 14-Sep-18, Soil Inves ga ons
Sec on 3 - T5/4 - AT6 51 12-Jul-18 14-Sep-18 53 14-Sep-18, Sec on 3 - T5/4 - AT6
SIS3_20400 SI Wk : Sec on 3 - T5/17 - AT6 12 12-Jul-18 26-Jul-18 53 SI Wk : Sec on 3 - T5/17 - AT6
SIS3_20300 SI Wk : Sec on 3 - T5/13 - T5/16 12 27-Jul-18 09-Aug-18 53 SI Wk : Sec on 3 - T5/13 - T5/16
SIS3_20200 SI Wk : Sec on 3 - T5/9 - T5/12 12 10-Aug-18 24-Aug-18 53 SI Wk : Sec on 3 - T5/9 - T5/12
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 8 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
SIS3_20100 SI Wk : Sec on 3 - T5/5 - T5/8 12 25-Aug-18 08-Sep-18 53 SI Wk : Sec on 3 - T5/5 - T5/8
SIS3_20000 SI Wk : Sec on 3 - T5/4 3 11-Sep-18 14-Sep-18 53 SI Wk : Sec on 3 - T5/4
Sec on 4 - AT7 - AT8 (Monopoles) 72 12-Jun-18 08-Sep-18 125 08-Sep-18, Sec on 4 - AT7 - AT8 (Monopoles)
SIS4_20500 SI Wk : Sec on 4 - T7/20 - AT8 12 12-Jun-18 27-Jun-18 55 SI Wk : Sec on 4 - T7/20 - AT8
SIS4_20400 SI Wk : Sec on 4 - T7/16 - T7/19 12 28-Jun-18 11-Jul-18 125 SI Wk : Sec on 4 - T7/16 - T7/19
SIS4_20300 SI Wk : Sec on 4 - T7/12 - T7/15 12 12-Jul-18 26-Jul-18 125 SI Wk : Sec on 4 - T7/12 - T7/15
SIS4_20200 SI Wk : Sec on 4 - T7/8 - T7/11 12 27-Jul-18 09-Aug-18 125 SI Wk : Sec on 4 - T7/8 - T7/11
SIS4_20100 SI Wk : Sec on 4 - T7/4 - T7/7 12 10-Aug-18 24-Aug-18 125 SI Wk : Sec on 4 - T7/4 - T7/7
SIS4_20000 SI Wk : Sec on 4 - AT7 - T7/3 12 25-Aug-18 08-Sep-18 125 SI Wk : Sec on 4 - AT7 - T7/3
Vegeta on Clearing Works 232 19-May-18 05-Mar-19 247 05-Mar-19, Vegeta on Clearing Works
Sec on 1 - AT1 - AT4 93 28-May-18 25-Sep-18 65 25-Sep-18, Sec on 1 - AT1 - AT4
VCS1_30200 Vege. Clearing Wk : Sec on 1 - AT1 - AT3 31 28-May-18 07-Jul-18 43 Vege. Clearing Wk : Sec on 1 - AT1 - AT3
VCS1_30300 Vege. Clearing Wk : Sec on 1 - T3/1 - T3/3 31 09-Jul-18 14-Aug-18 61 Vege. Clearing Wk : Sec on 1 - T3/1 - T3/3
VCS1_30400 Vege. Clearing Wk : Sec on 1 - T3/4 - AT4 31 15-Aug-18 25-Sep-18 65 Vege. Clearing Wk : Sec on 1 - T3/4 - AT4
Sec on 2 - T4/1 - AT5 93 26-Sep-18 16-Jan-19 69 16-Jan-19, Sec on 2 - T4/1 - AT5
VCS2_30200 Vege. Clearing Wk : Sec on 2 - T4/1 - T4/4 31 26-Sep-18 01-Nov-18 69 Vege. Clearing Wk : Sec on 2 - T4/1 - T4/4
VCS2_30300 Vege. Clearing Wk : Sec on 2 - T4/5 - T4/8 31 02-Nov-18 08-Dec-18 69 Vege. Clearing Wk : Sec on 2 - T4/5 - T4/8
VCS2_30400 Vege. Clearing Wk : Sec on 2 - T4/9 - AT5 31 10-Dec-18 16-Jan-19 69 Vege. Clearing Wk : Sec on 2 - T4/9 - AT5
Sec on 3 - T5/1 - AT6 149 19-May-18 23-Nov-18 101 23-Nov-18, Sec on 3 - T5/1 - AT6
VCS3_30200 Vege. Clearing Wk : Sec on 3 - T5/1 - T5/4 31 19-May-18 29-Jun-18 93 Vege. Clearing Wk : Sec on 3 - T5/1 - T5/4
VCS3_30300 Vege. Clearing Wk : Sec on 3 - T5/5 - T5/8 45 30-Jun-18 23-Aug-18 101 Vege. Clearing Wk : Sec on 3 - T5/5 - T5/8
VCS3_30400 Vege. Clearing Wk : Sec on 3 - T5/9 - T5/12 31 24-Aug-18 03-Oct-18 101 Vege. Clearing Wk : Sec on 3 - T5/9 - T5/12
VCS3_30500 Vege. Clearing Wk : Sec on 3 - T5/13 - T5/16 21 04-Oct-18 29-Oct-18 101 Vege. Clearing Wk : Sec on 3 - T5/13 - T5/16
VCS3_30600 Vege. Clearing Wk : Sec on 3 - T5/17 - AT6 21 30-Oct-18 23-Nov-18 101 Vege. Clearing Wk : Sec on 3 - T5/17 - AT6
Sec on 4 - AT7 - AT8 (Monopoles) 156 24-Aug-18 05-Mar-19 247 05-Mar-19, Sec on 4 - AT7 - AT8 (Monopoles)
VCS4_30500 Vege. Clearing Wk : Sec on 4 - T7/12 - T7/15 31 24-Aug-18 03-Oct-18 258 Vege. Clearing Wk : Sec on 4 - T7/12 - T7/15
VCS4_30600 Vege. Clearing Wk : Sec on 4 - T7/16 - T7/19 31 04-Oct-18 09-Nov-18 258 Vege. Clearing Wk : Sec on 4 - T7/16 - T7/19
VCS4_30700 Vege. Clearing Wk : Sec on 4 - T7/20 - AT8 31 10-Nov-18 17-Dec-18 310 Vege. Clearing Wk : Sec on 4 - T7/20 - AT8
VCS4_30200 Vege. Clearing Wk : Sec on 4 - AT7 - T7/3 21 24-Nov-18 18-Dec-18 101 Vege. Clearing Wk : Sec on 4 - AT7 - T7/3
VCS4_30300 Vege. Clearing Wk : Sec on 4 - T7/4 - T7/7 31 19-Dec-18 25-Jan-19 150 Vege. Clearing Wk : Sec on 4 - T7/4 - T7/7
VCS4_30400 Vege. Clearing Wk : Sec on 4 - T7/8 - T7/11 31 26-Jan-19 05-Mar-19 150 Vege. Clearing Wk : Sec on 4 - T7/8 - T7/11
Access Road 344 15-May-18 17-Jul-19 143 17-Jul-19, Access Road
Access Road Proposal 158 15-May-18 29-Nov-18 46 29-Nov-18, Access Road Proposal
ARPRO_40000 Proposal & Approval for Access Road : Sec on 1 35 15-May-18 29-Jun-18 3 Proposal & Approval for Access Road : Sec on 1
ARPRO_40300 Proposal & Approval for Access Road : Sec on 4 35 18-May-18 03-Jul-18 0 Proposal & Approval for Access Road : Sec on 4
ARPRO_40100 Proposal & Approval for Access Road : Sec on 2 35 18-Jun-18 28-Jul-18 145 Proposal & Approval for Access Road : Sec on 2
ARPRO_40200 Proposal & Approval for Access Road : Sec on 3 35 28-Jun-18 08-Aug-18 43 Proposal & Approval for Access Road : Sec on 3
VCS1_30000 Crop Coun ng for Access Road 60 04-Jul-18 18-Sep-18 0 Crop Coun ng for Access Road
VCS1_30100 Crop Compensa on affected by Access Road 90 09-Aug-18 29-Nov-18 0 Crop Compensa on affected by Access Road
Sec on 1 - AT1 - AT4 105 09-Aug-18 17-Dec-18 0 17-Dec-18, Sec on 1 - AT1 - AT4
ARS1_40000 Access Road Const. : Sec on 1 - AT1 - AT3 35 09-Aug-18 24-Sep-18 0 Access Road Const. : Sec on 1 - AT1 - AT3
ARS1_40100 Access Road Const. : Sec on 1 - T3/1 - T3/3 35 25-Sep-18 05-Nov-18 0 Access Road Const. : Sec on 1 - T3/1 - T3/3
ARS1_40200 Access Road Const. : Sec on 1 - T3/4 - AT4 35 06-Nov-18 17-Dec-18 0 Access Road Const. : Sec on 1 - T3/4 - AT4
Sec on 2 - T4/1 - AT5 93 18-Dec-18 09-Apr-19 0 09-Apr-19, Sec on 2 - T4/1 - AT5
ARS2_40000 Access Road Const. : Sec on 2 - T4/1 - T4/4 31 18-Dec-18 24-Jan-19 0 Access Road Const. : Sec on 2 - T4/1 - T4/4
ARS2_40100 Access Road Const. : Sec on 2 - T4/5 - T4/8 31 25-Jan-19 04-Mar-19 0 Access Road Const. : Sec on 2 - T4/5 - T4/8
ARS2_40200 Access Road Const. : Sec on 2 - T4/9 - AT5 31 05-Mar-19 09-Apr-19 0 Access Road Const. : Sec on 2 - T4/9 - AT5
Sec on 3 - T5/1 - AT6 143 09-Aug-18 01-Feb-19 43 01-Feb-19, Sec on 3 - T5/1 - AT6
ARS3_40000 Access Road Const. : Sec on 3 - T5/1 - T5/4 35 09-Aug-18 24-Sep-18 43 Access Road Const. : Sec on 3 - T5/1 - T5/4
ARS3_40100 Access Road Const. : Sec on 3 - T5/5 - T5/8 35 25-Sep-18 05-Nov-18 43 Access Road Const. : Sec on 3 - T5/5 - T5/8
ARS3_40200 Access Road Const. : Sec on 3 - T5/9 - T5/12 31 06-Nov-18 12-Dec-18 43 Access Road Const. : Sec on 3 - T5/9 - T5/12
ARS3_40300 Access Road Const. : Sec on 3 - T5/13 - T5/16 21 13-Dec-18 08-Jan-19 43 Access Road Const. : Sec on 3 - T5/13 - T5/16
ARS3_40400 Access Road Const. : Sec on 3 - T5/17 - AT6 21 09-Jan-19 01-Feb-19 43 Access Road Const. : Sec on 3 - T5/17 - AT6
Sec on 4 - AT7 - AT8 (Monopoles) 133 02-Feb-19 17-Jul-19 143 17-Jul-19, Sec on 4 - AT7 - AT8 (Monopoles)
ARS4_40000 Access Road Const. : Sec on 4 - AT7 - T7/3 21 02-Feb-19 28-Feb-19 43 Access Road Const. : Sec on 4 - AT7 - T7/3
ARS4_40100 Access Road Const. : Sec on 4 - T7/4 - T7/7 31 01-Mar-19 05-Apr-19 92 Access Road Const. : Sec on 4 - T7/4 - T7/7
ARS4_40200 Access Road Const. : Sec on 4 - T7/8 - T7/11 31 06-Apr-19 14-May-19 92 Access Road Const. : Sec on 4 - T7/8 - T7/11
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 9 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
ARS4_40400 Access Road Const. : Sec on 4 - T7/16 - T7/19 35 20-Apr-19 04-Jun-19 95 Access Road Const. : Sec on 4 - T7/16 - T7/19
ARS4_40300 Access Road Const. : Sec on 4 - T7/12 - T7/15 35 15-May-19 29-Jun-19 92 Access Road Const. : Sec on 4 - T7/12 - T7/15
ARS4_40500 Access Road Const. : Sec on 4 - T7/20 - AT8 35 07-Jun-19 17-Jul-19 143 Access Road Const. : Sec on 4 - T7/20 - AT8
Founda on Works 327 26-Jul-18 05-Sep-19 128 05-Sep-19, Founda on Works
Founda on Sub-Milestone 91 11-May-19 05-Sep-19 128 05-Sep-19, Founda on Sub-Milestone
FDN_MILE_50000 Comple on of Normal Founda on 0 11-May-19 219 Comple on of Normal Founda on,
FDN_MILE_50100 Comple on of Piling Works 0 01-Jul-19 181 Comple on of Piling Works,
FDN_MILE_50200 Comple on of Pile Cap 0 05-Sep-19 128 Comple on of Pile Cap,
Founda on Works 327 26-Jul-18 05-Sep-19 90 05-Sep-19, Founda on Works
Founda on Test 74 26-Jul-18 26-Oct-18 39 26-Oct-18, Founda on Test
Normal Founda on Test 47 28-Aug-18 26-Oct-18 39 26-Oct-18, Normal Founda on Test
FDN_TEST_9000 Normal Founda on Test Mobilisa on 6 28-Aug-18 04-Sep-18 39 Normal Founda on Test Mobilisa on
FDN_TEST_9100 Prepara on and Installa on of Normal Test Founda on (includ. curing) 21 05-Sep-18 02-Oct-18 39 Prepara on and Installa on of Normal Test Founda on (includ. curing)
FDN_TEST_9200 Normal Founda on Upli Test for Light Fdn 5 09-Oct-18 15-Oct-18 39 Normal Founda on Upli Test for Light Fdn
FDN_TEST_9300 Normal Founda on Upli Test for Heavy Fdn 5 16-Oct-18 20-Oct-18 39 Normal Founda on Upli Test for Heavy Fdn
FDN_TEST_9400 Ground Bearing Test for Normal Fdn 5 22-Oct-18 26-Oct-18 39 Ground Bearing Test for Normal Fdn
Piled Test 25 26-Jul-18 24-Aug-18 54 24-Aug-18, Piled Test
FDN_TEST_9500 Test Piles Mobiliza on 2 26-Jul-18 27-Jul-18 69 Test Piles Mobiliza on
FDN_TEST_9600 Installa on of Test Piles for Upli & Compression 5 28-Jul-18 02-Aug-18 69 Installa on of Test Piles for Upli & Compression
FDN_TEST_9700 Conduct Pile Upli , Compression and Lateral Tests 3 21-Aug-18 24-Aug-18 54 Conduct Pile Upli , Compression and Lateral Tests
Normal Founda on Works 134 30-Nov-18 11-May-19 67 11-May-19, Normal Founda on Works
Sec on 1 - AT1 - AT4 134 30-Nov-18 11-May-19 67 11-May-19, Sec on 1 - AT1 - AT4
NFS1_60000 NF for 1NS Tower - Sec on 1 : T3/3 6 30-Nov-18 06-Dec-18 11 NF for 1NS Tower - Sec on 1 : T3/3
NFS1_60010 NF for 1NS Tower - Sec on 1 : T3/6 6 10-Dec-18 15-Dec-18 11 NF for 1NS Tower - Sec on 1 : T3/6
NFS1_60110 NF for 1LA Tower - Sec on 1 : T3/4 & T3/5 12 19-Dec-18 03-Jan-19 11 NF for 1LA Tower - Sec on 1 : T3/4 & T3/5
NFS1_60300 NF for 1HS Tower - Sec on 1 : T3/2 6 07-Jan-19 12-Jan-19 11 NF for 1HS Tower - Sec on 1 : T3/2
NFS1_60100 NF for 1LA Tower - Sec on 1 : AT3 & T3/1 12 16-Jan-19 29-Jan-19 11 NF for 1LA Tower - Sec on 1 : AT3 & T3/1
NFS1_60200 NF for 1HS Tower - Sec on 1 : T2/1 (LAST) 6 01-Feb-19 09-Feb-19 11 NF for 1HS Tower - Sec on 1 : T2/1 (LAST)
NFS1_60600 NF for 1DE Tower - Sec on 1 : AT1 6 27-Apr-19 04-May-19 11 NF for 1DE Tower - Sec on 1 : AT1
NFS1_60500 NF for 1HA Tower - Sec on 1 : AT4 (lAST) 6 29-Apr-19 06-May-19 72 NF for 1HA Tower - Sec on 1 : AT4 (lAST)
NFS1_60400 NF for 1MA Tower - Sec on 1 : AT2 6 06-May-19 11-May-19 11 NF for 1MA Tower - Sec on 1 : AT2
Sec on 2 - T4/1 - AT5 92 05-Jan-19 25-Apr-19 13 25-Apr-19, Sec on 2 - T4/1 - AT5
NFS2_60000 NF for 1NS Tower - Sec on 2 : T4/2 6 05-Jan-19 11-Jan-19 11 NF for 1NS Tower - Sec on 2 : T4/2
NFS2_60100 NF for 1NS Tower - Sec on 2 : T4/5, T4/6, T4/7, T4/8 27 25-Jan-19 27-Feb-19 2 NF for 1NS Tower - Sec on 2 : T4/5, T4/6, T4/7, T4/8
NFS2_60200 NF for 1NS Tower - Sec on 2 : T4/10, T4/11 12 05-Mar-19 18-Mar-19 0 NF for 1NS Tower - Sec on 2 : T4/10, T4/11
NFS2_60410 NF for 1HS Tower - Sec on 2 : T4/9 6 21-Mar-19 27-Mar-19 13 NF for 1HS Tower - Sec on 2 : T4/9
NFS2_60400 NF for 1HS Tower - Sec on 2 : T4/4 6 30-Mar-19 05-Apr-19 13 NF for 1HS Tower - Sec on 2 : T4/4
NFS2_60310 NF for 1LA Tower - Sec on 2 : T4/3 6 09-Apr-19 15-Apr-19 13 NF for 1LA Tower - Sec on 2 : T4/3
NFS2_60500 NF for 1HA Tower - Sec on 2 : AT5 6 17-Apr-19 24-Apr-19 11 NF for 1HA Tower - Sec on 2 : AT5
NFS2_60300 NF for 1LA Tower - Sec on 2 : T4/1 6 18-Apr-19 25-Apr-19 13 NF for 1LA Tower - Sec on 2 : T4/1
Sec on 3 - T5/1 - T5/3 22 21-Mar-19 15-Apr-19 11 15-Apr-19, Sec on 3 - T5/1 - T5/3
NFS3_60000 NF for 1NS Tower - Sec on 3 : T5/1, T5/2, T5/3 22 21-Mar-19 15-Apr-19 11 NF for 1NS Tower - Sec on 3 : T5/1, T5/2, T5/3
Piling Works 171 01-Dec-18 01-Jul-19 136 01-Jul-19, Piling Works
Sec on 3 - T5/4 - AT6 117 01-Dec-18 22-Apr-19 75 22-Apr-19, Sec on 3 - T5/4 - AT6
PWS3_50000 1NS Piling Wk : Sec on 3 - T5/4 6 01-Dec-18 07-Dec-18 57 1NS Piling Wk : Sec on 3 - T5/4
PWS3_50100 1NS Piling Wk : Sec on 3 - T5/5 - T5/8 24 11-Dec-18 09-Jan-19 57 1NS Piling Wk : Sec on 3 - T5/5 - T5/8
PWS3_50200 1NS Piling Wk : Sec on 3 - T5/9 - T5/12 24 12-Jan-19 11-Feb-19 57 1NS Piling Wk : Sec on 3 - T5/9 - T5/12
PWS3_50300 1NS Piling Wk : Sec on 3 - T5/13 6 14-Feb-19 20-Feb-19 57 1NS Piling Wk : Sec on 3 - T5/13
PWS3_50600 1HA Piling Wk : Sec on 3 - T5/14 6 23-Feb-19 01-Mar-19 57 1HA Piling Wk : Sec on 3 - T5/14
PWS3_50400 1NS Piling Wk : Sec on 3 - T5/15 & T5/16 12 05-Mar-19 18-Mar-19 57 1NS Piling Wk : Sec on 3 - T5/15 & T5/16
PWS3_50500 1NS Piling Wk : Sec on 3 - T5/17 - T5/19 18 21-Mar-19 10-Apr-19 57 1NS Piling Wk : Sec on 3 - T5/17 - T5/19
PWS3_50700 1HA Piling Wk : Sec on 3 - AT6 7 13-Apr-19 22-Apr-19 75 1HA Piling Wk : Sec on 3 - AT6
Sec on 4 - AT7 - AT8 (Monopoles) 119 02-Feb-19 01-Jul-19 136 01-Jul-19, Sec on 4 - AT7 - AT8 (Monopoles)
PWS4_51300 1CQ3 Piling Wk : Sec on 4 - AT7 6 02-Feb-19 11-Feb-19 43 1CQ3 Piling Wk : Sec on 4 - AT7
PWS4_50700 1CQ1 Piling Wk : Sec on 4 - T7/1 6 14-Feb-19 20-Feb-19 89 1CQ1 Piling Wk : Sec on 4 - T7/1
PWS4_50000 1CQL Piling Wk : Sec on 4 - T7/2 & T2/3 10 23-Feb-19 06-Mar-19 89 1CQL Piling Wk : Sec on 4 - T7/2 & T2/3
PWS4_50800 1CQ1 Piling Wk : Sec on 4 - T7/4 6 09-Mar-19 15-Mar-19 89 1CQ1 Piling Wk : Sec on 4 - T7/4
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 10 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
PWS4_50100 1CQL Piling Wk : Sec on 4 - T7/5 - T7/7 18 19-Mar-19 08-Apr-19 89 1CQL Piling Wk : Sec on 4 - T7/5 - T7/7
PWS4_50200 1CQL Piling Wk : Sec on 4 - T7/8 5 11-Apr-19 16-Apr-19 89 1CQL Piling Wk : Sec on 4 - T7/8
PWS4_50900 1CQ1 Piling Wk : Sec on 4 - T7/9 6 20-Apr-19 26-Apr-19 89 1CQ1 Piling Wk : Sec on 4 - T7/9
PWS4_51000 1CQ1 Piling Wk : Sec on 4 - T7/10 6 30-Apr-19 07-May-19 89 1CQ1 Piling Wk : Sec on 4 - T7/10
PWS4_51200 1CQ1 Piling Wk : Sec on 4 - T7/19 6 08-May-19 14-May-19 156 1CQ1 Piling Wk : Sec on 4 - T7/19
PWS4_50300 1CQL Piling Wk : Sec on 4 - T7/11 5 10-May-19 15-May-19 89 1CQL Piling Wk : Sec on 4 - T7/11
PWS4_50400 1CQL Piling Wk : Sec on 4 - T7/12 & T7/13 8 18-May-19 28-May-19 89 1CQL Piling Wk : Sec on 4 - T7/12 & T7/13
PWS4_51100 1CQ1 Piling Wk : Sec on 4 - T7/14 & T7/15 6 31-May-19 11-Jun-19 89 1CQ1 Piling Wk : Sec on 4 - T7/14 & T7/15
PWS4_50600 1CQL Piling Wk : Sec on 4 - T7/20 5 07-Jun-19 12-Jun-19 143 1CQL Piling Wk : Sec on 4 - T7/20
PWS4_50500 1CQL Piling Wk : Sec on 4 - T7/16 - T7/18 15 14-Jun-19 01-Jul-19 89 1CQL Piling Wk : Sec on 4 - T7/16 - T7/18
PWS4_51400 1CQT Piling Wk : Sec on 4 - AT8 7 15-Jun-19 22-Jun-19 143 1CQT Piling Wk : Sec on 4 - AT8
Construc on of Pile Cap 204 26-Dec-18 05-Sep-19 90 05-Sep-19, Construc on of Pile Cap
Sec on 3 - T5/4 - AT6 120 26-Dec-18 21-May-19 59 21-May-19, Sec on 3 - T5/4 - AT6
PCS3_70000 1NS Pile Cap Const.: Sec on 3 - T5/4 6 26-Dec-18 02-Jan-19 64 1NS Pile Cap Const.: Sec on 3 - T5/4
PCS3_70100 1NS Pile Cap Const.: Sec on 3 - T5/5 - T5/8 27 10-Jan-19 12-Feb-19 58 1NS Pile Cap Const.: Sec on 3 - T5/5 - T5/8
PCS3_70200 1NS Pile Cap Const.: Sec on 3 - T5/9 - T5/12 27 13-Feb-19 15-Mar-19 58 1NS Pile Cap Const.: Sec on 3 - T5/9 - T5/12
PCS3_70300 1NS Pile Cap Const.: Sec on 3 - T5/13 6 16-Mar-19 22-Mar-19 58 1NS Pile Cap Const.: Sec on 3 - T5/13
PCS3_70400 1NS Pile Cap Const.: Sec on 3 - T5/15 & T5/16 15 23-Mar-19 09-Apr-19 58 1NS Pile Cap Const.: Sec on 3 - T5/15 & T5/16
PCS3_70500 1NS Pile Cap Const.: Sec on 3 - T5/17 - T5/19 18 11-Apr-19 03-May-19 57 1NS Pile Cap Const.: Sec on 3 - T5/17 - T5/19
PCS3_70600 1HA Pile Cap Const.: Sec on 3 - T5/14 7 04-May-19 11-May-19 59 1HA Pile Cap Const.: Sec on 3 - T5/14
PCS3_70700 1HA Pile Cap Const.: Sec on 3 - AT6 7 13-May-19 21-May-19 59 1HA Pile Cap Const.: Sec on 3 - AT6
Sec on 4 - AT7 - AT8 (Monopoles) 84 22-May-19 05-Sep-19 90 05-Sep-19, Sec on 4 - AT7 - AT8 (Monopoles)
PCS4_70300 1CQL Pile Cap Const.: Sec on 4 - T7/11 5 22-May-19 27-May-19 91 1CQL Pile Cap Const.: Sec on 4 - T7/11
PCS4_71300 1CQ3 Pile Cap Const.: Sec on 4 - AT7 6 28-May-19 07-Jun-19 11 1CQ3 Pile Cap Const.: Sec on 4 - AT7
PCS4_70400 1CQL Pile Cap Const.: Sec on 4 - T7/12 & T7/13 12 30-May-19 17-Jun-19 91 1CQL Pile Cap Const.: Sec on 4 - T7/12 & T7/13
PCS4_70700 1CQ1 Pile Cap Const.: Sec on 4 - T7/1 6 11-Jun-19 17-Jun-19 11 1CQ1 Pile Cap Const.: Sec on 4 - T7/1
PCS4_70000 1CQL Pile Cap Const.: Sec on 4 - T7/2 & T2/3 12 20-Jun-19 03-Jul-19 11 1CQL Pile Cap Const.: Sec on 4 - T7/2 & T2/3
PCS4_71100 1CQ1 Pile Cap Const.: Sec on 4 - T7/14 & T7/15 15 20-Jun-19 06-Jul-19 91 1CQ1 Pile Cap Const.: Sec on 4 - T7/14 & T7/15
PCS4_70800 1CQ1 Pile Cap Const.: Sec on 4 - T7/4 6 06-Jul-19 12-Jul-19 23 1CQ1 Pile Cap Const.: Sec on 4 - T7/4
PCS4_70500 1CQL Pile Cap Const.: Sec on 4 - T7/16 - T7/18 20 10-Jul-19 02-Aug-19 89 1CQL Pile Cap Const.: Sec on 4 - T7/16 - T7/18
PCS4_70100 1CQL Pile Cap Const.: Sec on 4 - T7/5 - T7/7 20 13-Jul-19 06-Aug-19 23 1CQL Pile Cap Const.: Sec on 4 - T7/5 - T7/7
PCS4_71200 1CQ1 Pile Cap Const.: Sec on 4 - T7/19 6 06-Aug-19 13-Aug-19 92 1CQ1 Pile Cap Const.: Sec on 4 - T7/19
PCS4_70200 1CQL Pile Cap Const.: Sec on 4 - T7/8 5 09-Aug-19 15-Aug-19 31 1CQL Pile Cap Const.: Sec on 4 - T7/8
PCS4_70600 1CQL Pile Cap Const.: Sec on 4 - T7/20 5 16-Aug-19 21-Aug-19 92 1CQL Pile Cap Const.: Sec on 4 - T7/20
PCS4_70900 1CQ1 Pile Cap Const.: Sec on 4 - T7/9 6 19-Aug-19 24-Aug-19 31 1CQ1 Pile Cap Const.: Sec on 4 - T7/9
PCS4_71400 1CQT Pile Cap Const.: Sec on 4 - AT8 (LAST) 7 24-Aug-19 03-Sep-19 92 1CQT Pile Cap Const.: Sec on 4 - AT8 (LAST)
PCS4_71000 1CQ1 Pile Cap Const.: Sec on 4 - T7/10 6 28-Aug-19 05-Sep-19 31 1CQ1 Pile Cap Const.: Sec on 4 - T7/10
Monopole Dismantling and Reinstall Works 235 28-Feb-19 16-Dec-19 45 16-Dec-19, Monopole Dismantling and Reinstall Works
Dismantling of Conductors, OPGW, Line Fi ngs 141 28-Feb-19 21-Aug-19 119 21-Aug-19, Dismantling of Conductors, OPGW, Line Fi ngs
MONO_DISM_15000 Installa on of Temporary Earthing 21 28-Feb-19 23-Mar-19 43 Installa on of Temporary Earthing
MONO_DISM_16000 Dismantling Conductors, OPGW & Line Fi ngs : 30% Complete 30 25-Mar-19 29-Apr-19 43 Dismantling Conductors, OPGW & Line Fi ngs : 30% Complete
MONO_DISM_16100 Dismantling Conductors, OPGW & Line Fi ngs : 60% Complete 30 30-Apr-19 10-Jun-19 43 Dismantling Conductors, OPGW & Line Fi ngs : 60% Complete
MONO_DISM_16200 Dismantling Conductors, OPGW & Line Fi ngs : 90% Complete 30 11-Jun-19 15-Jul-19 54 Dismantling Conductors, OPGW & Line Fi ngs : 90% Complete
MONO_DISM_16300 Dismantling Conductors, OPGW & Line Fi ngs : 100% Complete 30 16-Jul-19 21-Aug-19 119 Dismantling Conductors, OPGW & Line Fi ngs : 100% Complete
Dismantling of Monopoles 140 30-Apr-19 24-Oct-19 89 24-Oct-19, Dismantling of Monopoles
MONO_DISM_15100 Dismantling Monopole of Tudan - Miri Airport TL : 30% Complete 30 30-Apr-19 10-Jun-19 43 Dismantling Monopole of Tudan - Miri Airport TL : 30% Complete
MONO_DISM_15200 Dismantling Monopole of Tudan - Miri Airport TL : 60% Complete 30 11-Jun-19 15-Jul-19 43 Dismantling Monopole of Tudan - Miri Airport TL : 60% Complete
MONO_DISM_15300 Dismantling Monopole of Tudan - Miri Airport TL : 90% Complete 30 16-Jul-19 21-Aug-19 54 Dismantling Monopole of Tudan - Miri Airport TL : 90% Complete
MONO_DISM_15400 Dismantling Monopole of Tudan - Miri Airport TL : 100% Complete 30 22-Aug-19 01-Oct-19 59 Dismantling Monopole of Tudan - Miri Airport TL : 100% Complete
MONO_DISM_15500 Packaging and Delivery of Unused Monopole, Conductor & fi ngs to Tudan Substa
20 on 02-Oct-19 24-Oct-19 89 Packaging and Delivery of Unused Monopole, Conductor & fi ngs t
Monopole Reinstalla on 120 20-Jul-19 16-Dec-19 11 16-Dec-19, Monopole Reinstalla on
MONO_REINS_11300 1CQ3 Monopole Reinst. : Sec on 4 - AT7 4 20-Jul-19 25-Jul-19 11 1CQ3 Monopole Reinst. : Sec on 4 - AT7
MONO_REINS_10700 1CQ1 Monopole Reinst. : Sec on 4 - T7/1 4 29-Jul-19 01-Aug-19 11 1CQ1 Monopole Reinst. : Sec on 4 - T7/1
MONO_REINS_10000 1CQL Monopole Reinst. : Sec on 4 - T7/2 & T2/3 8 05-Aug-19 14-Aug-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/2 & T2/3
MONO_REINS_10800 1CQ1 Monopole Reinst. : Sec on 4 - T7/4 4 17-Aug-19 21-Aug-19 11 1CQ1 Monopole Reinst. : Sec on 4 - T7/4
MONO_REINS_10100 1CQL Monopole Reinst. : Sec on 4 - T7/5 - T7/7 15 24-Aug-19 13-Sep-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/5 - T7/7
MONO_REINS_10200 1CQL Monopole Reinst. : Sec on 4 - T7/8 4 19-Sep-19 23-Sep-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/8
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 11 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
MONO_REINS_10900 1CQ1 Monopole Reinst. : Sec on 4 - T7/9 4 26-Sep-19 30-Sep-19 11 1CQ1 Monopole Reinst. : Sec on 4 - T7/9
MONO_REINS_11000 1CQ1 Monopole Reinst. : Sec on 4 - T7/10 4 03-Oct-19 07-Oct-19 11 1CQ1 Monopole Reinst. : Sec on 4 - T7/10
MONO_REINS_10300 1CQL Monopole Reinst. : Sec on 4 - T7/11 4 10-Oct-19 14-Oct-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/11
MONO_REINS_10400 1CQL Monopole Reinst. : Sec on 4 - T7/12 & T7/13 8 17-Oct-19 25-Oct-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/12 & T7/13
MONO_REINS_11100 1CQ1 Monopole Reinst. : Sec on 4 - T7/14 & T7/15 8 29-Oct-19 06-Nov-19 11 1CQ1 Monopole Reinst. : Sec on 4 - T7/14 & T7/15
MONO_REINS_10500 1CQL Monopole Reinst. : Sec on 4 - T7/16 - T7/18 15 09-Nov-19 27-Nov-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/16 - T7/18
MONO_REINS_11200 1CQ1 Monopole Reinst. : Sec on 4 - T7/19 4 30-Nov-19 04-Dec-19 11 1CQ1 Monopole Reinst. : Sec on 4 - T7/19
MONO_REINS_10600 1CQL Monopole Reinst. : Sec on 4 - T7/20 4 05-Dec-19 09-Dec-19 11 1CQL Monopole Reinst. : Sec on 4 - T7/20
MONO_REINS_11400 1CQT Monopole Reinst. : Sec on 4 - AT8 4 12-Dec-19 16-Dec-19 11 1CQT Monopole Reinst. : Sec on 4 - AT8
Demoli on works of Exis ng Monopole Fdn 120 11-Jun-19 05-Nov-19 59 05-Nov-19, Demoli on works of Exis ng Monopole Fdn
MONO_DISM_15600 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 30% Complete 30 11-Jun-19 15-Jul-19 59 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 30% Complete
MONO_DISM_15700 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 60% Complete 30 16-Jul-19 21-Aug-19 59 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 60% Complete
MONO_DISM_15800 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 90% Complete 30 22-Aug-19 01-Oct-19 59 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 90% Com
MONO_DISM_15900 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 100% Complete30 02-Oct-19 05-Nov-19 59 Demoli on work of Exis ng Pilecap at Tudan - Miri Airport TL : 10
Tower Erec on Works - Steel La ce 224 13-Mar-19 16-Dec-19 11 16-Dec-19, Tower Erec on Works - Steel La ce
Tower Sor ng and Tower Shi ing 100 13-Mar-19 15-Jul-19 57 15-Jul-19, Tower Sor ng and Tower Shi ing
Sec on 1 - AT1 - AT4 75 11-Apr-19 15-Jul-19 57 15-Jul-19, Sec on 1 - AT1 - AT4
TSTS_S1_80000 Tower Sor ng & Shi ing for 1NS Tower - Sec on 1 : T3/3 (T2 1st) 3 11-Apr-19 13-Apr-19 17 Tower Sor ng & Shi ing for 1NS Tower - Sec on 1 : T3/3 (T2 1st)
TSTS_S1_80001 Tower Sor ng & Shi ing for 1NS Tower - Sec on 1 : T3/6 3 17-Apr-19 20-Apr-19 17 Tower Sor ng & Shi ing for 1NS Tower - Sec on 1 : T3/6
TSTS_S1_80010 Tower Sor ng & Shi ing for 1LA Tower - Sec on 1 : AT3, T3/1 6 04-Jun-19 12-Jun-19 18 Tower Sor ng & Shi ing for 1LA Tower - Sec on 1 : AT3, T3/1
TSTS_S1_80020 Tower Sor ng & Shi ing for 1HS Tower - Sec on 1 : T2/1 3 15-Jun-19 18-Jun-19 60 Tower Sor ng & Shi ing for 1HS Tower - Sec on 1 : T2/1
TSTS_S1_80040 Tower Sor ng & Shi ing for 1MA Tower - Sec on 1 : AT2 3 21-Jun-19 24-Jun-19 65 Tower Sor ng & Shi ing for 1MA Tower - Sec on 1 : AT2
TSTS_S1_80060 Tower Sor ng & Shi ing for 1DE Tower - Sec on 1 : AT1 3 27-Jun-19 29-Jun-19 70 Tower Sor ng & Shi ing for 1DE Tower - Sec on 1 : AT1
TSTS_S1_80011 Tower Sor ng & Shi ing for 1LA Tower - Sec on 1 : T3/4 & T3/5 6 27-Jun-19 03-Jul-19 37 Tower Sor ng & Shi ing for 1LA Tower - Sec on 1 : T3/4 & T3/5
TSTS_S1_80030 Tower Sor ng & Shi ing for 1HS Tower - Sec on 1 : T3/2 3 06-Jul-19 09-Jul-19 47 Tower Sor ng & Shi ing for 1HS Tower - Sec on 1 : T3/2
TSTS_S1_80050 Tower Sor ng & Shi ing for 1HA Tower - Sec on 1 : AT4 3 12-Jul-19 15-Jul-19 52 Tower Sor ng & Shi ing for 1HA Tower - Sec on 1 : AT4
Sec on 2 - T4/1 - AT5 64 13-Mar-19 29-May-19 13 29-May-19, Sec on 2 - T4/1 - AT5
TSTS_S2_80000 Tower Sor ng & Shi ing for 1NS Tower - Sec on 2 : T4/2 3 13-Mar-19 15-Mar-19 6 Tower Sor ng & Shi ing for 1NS Tower - Sec on 2 : T4/2
TSTS_S2_80010 Tower Sor ng & Shi ing for 1NS Tower - Sec on 2 : T4/5, T4/6, T4/7, T4/8 12 19-Mar-19 01-Apr-19 6 Tower Sor ng & Shi ing for 1NS Tower - Sec on 2 : T4/5, T4/6, T4/7, T4/8
TSTS_S2_80020 Tower Sor ng & Shi ing for 1NS Tower - Sec on 2 : T4/10, T4/11 6 04-Apr-19 10-Apr-19 17 Tower Sor ng & Shi ing for 1NS Tower - Sec on 2 : T4/10, T4/11
TSTS_S2_80030 Tower Sor ng & Shi ing for 1LA Tower - Sec on 2 : T4/1 3 02-May-19 04-May-19 9 Tower Sor ng & Shi ing for 1LA Tower - Sec on 2 : T4/1
TSTS_S2_80031 Tower Sor ng & Shi ing for 1LA Tower - Sec on 2 : T4/3 3 08-May-19 10-May-19 9 Tower Sor ng & Shi ing for 1LA Tower - Sec on 2 : T4/3
TSTS_S2_80040 Tower Sor ng & Shi ing for 1HS Tower - Sec on 2 : T4/4 3 14-May-19 16-May-19 9 Tower Sor ng & Shi ing for 1HS Tower - Sec on 2 : T4/4
TSTS_S2_80045 Tower Sor ng & Shi ing for 1HS Tower - Sec on 2 : T4/9 3 21-May-19 23-May-19 11 Tower Sor ng & Shi ing for 1HS Tower - Sec on 2 : T4/9
TSTS_S2_80050 Tower Sor ng & Shi ing for 1HA Tower - Sec on 2 : AT5 (T2 last) 3 27-May-19 29-May-19 13 Tower Sor ng & Shi ing for 1HA Tower - Sec on 2 : AT5 (T2 last)
Sec on 3 - T5/1 - AT6 82 13-Mar-19 24-Jun-19 37 24-Jun-19, Sec on 3 - T5/1 - AT6
TSTS_S3_80010 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/4 (T1 1st) 3 13-Mar-19 15-Mar-19 47 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/4 (T1 1st)
TSTS_S3_80020 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/5 - T5/8 12 19-Mar-19 01-Apr-19 47 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/5 - T5/8
TSTS_S3_80000 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 : T5/1, T5/2, T5/3 9 16-Apr-19 26-Apr-19 37 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 : T5/1, T5/2, T5/3
TSTS_S3_80030 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/9 - T5/12 12 27-Apr-19 11-May-19 37 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/9 - T5/12
TSTS_S3_80040 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/13 3 15-May-19 17-May-19 37 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/13
TSTS_S3_80050 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/15 & T5/16 6 18-May-19 25-May-19 37 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/15 & T5/16
TSTS_S3_80060 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/17 - T5/19 9 29-May-19 12-Jun-19 37 Tower Sor ng & Shi ing for 1NS Tower - Sec on 3 - T5/17 - T5/19
TSTS_S3_80070 Tower Sor ng & Shi ing for 1HA Tower - Sec on 3 - T5/14 3 15-Jun-19 18-Jun-19 37 Tower Sor ng & Shi ing for 1HA Tower - Sec on 3 - T5/14
TSTS_S3_80080 Tower Sor ng & Shi ing for 1HA Tower - Sec on 3 - AT6 (T1 last) 3 21-Jun-19 24-Jun-19 37 Tower Sor ng & Shi ing for 1HA Tower - Sec on 3 - AT6 (T1 last)
Erec on Works 205 04-Apr-19 16-Dec-19 11 16-Dec-19, Erec on Works
Tower Erec on Sub-Milestone 142 24-Jun-19 16-Dec-19 11 16-Dec-19, Tower Erec on Sub-Milestone
TE_MILE_10100 Comple on of Tower Erec on for Sec on 2 0 24-Jun-19 97 Comple on of Tower Erec on for Sec on 2,
TE_MILE_10000 Comple on of Tower Erec on for Sec on 1 0 27-Aug-19 27 Comple on of Tower Erec on for Sec on 1,
TE_MILE_10200 Comple on of Tower Erec on for Sec on 3 0 20-Sep-19 28 Comple on of Tower Erec on for Sec on 3,
TE_MILE_10300 Comple on of Tower Erec on for Sec on 4 - Monopoles 0 16-Dec-19 11 Comple on of Tower Erec on for Sec on 4 - Monopole
Sec on 1 - AT1 - AT4 53 25-Jun-19 27-Aug-19 27 27-Aug-19, Sec on 1 - AT1 - AT4
TE_S1_90000 Tower Erec on for 1NS Tower - Sec on 1 : T3/3 4 25-Jun-19 28-Jun-19 0 Tower Erec on for 1NS Tower - Sec on 1 : T3/3
TE_S1_90100 Tower Erec on for 1NS Tower - Sec on 1 : T3/6 4 29-Jun-19 03-Jul-19 0 Tower Erec on for 1NS Tower - Sec on 1 : T3/6
TE_S1_90200 Tower Erec on for 1LA Tower - Sec on 1 : AT3, T3/1 10 04-Jul-19 15-Jul-19 0 Tower Erec on for 1LA Tower - Sec on 1 : AT3, T3/1
TE_S1_90300 Tower Erec on for 1LA Tower - Sec on 1 : T3/4 & T3/5 10 16-Jul-19 27-Jul-19 27 Tower Erec on for 1LA Tower - Sec on 1 : T3/4 & T3/5
TE_S1_90400 Tower Erec on for 1HS Tower - Sec on 1 : T2/1 5 29-Jul-19 02-Aug-19 27 Tower Erec on for 1HS Tower - Sec on 1 : T2/1
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 12 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TE_S1_90500 Tower Erec on for 1HS Tower - Sec on 1 : T3/2 5 03-Aug-19 08-Aug-19 27 Tower Erec on for 1HS Tower - Sec on 1 : T3/2
TE_S1_90600 Tower Erec on for 1MA Tower - Sec on 1 : AT2 5 09-Aug-19 15-Aug-19 27 Tower Erec on for 1MA Tower - Sec on 1 : AT2
TE_S1_90700 Tower Erec on for 1HA Tower - Sec on 1 : AT4 5 16-Aug-19 21-Aug-19 27 Tower Erec on for 1HA Tower - Sec on 1 : AT4
TE_S1_90800 Tower Erec on for 1DE Tower - Sec on 1 : AT1 5 22-Aug-19 27-Aug-19 27 Tower Erec on for 1DE Tower - Sec on 1 : AT1
Sec on 2 - T4/1 - AT5 63 04-Apr-19 24-Jun-19 0 24-Jun-19, Sec on 2 - T4/1 - AT5
TE_S2_90000 Tower Erec on for 1NS Tower - Sec on 2 : T4/2 4 04-Apr-19 08-Apr-19 0 Tower Erec on for 1NS Tower - Sec on 2 : T4/2
TE_S2_90100 Tower Erec on for 1NS Tower - Sec on 2 : T4/5, T4/6, T4/7, T4/8 22 09-Apr-19 06-May-19 0 Tower Erec on for 1NS Tower - Sec on 2 : T4/5, T4/6, T4/7, T4/8
TE_S2_90200 Tower Erec on for 1NS Tower - Sec on 2 : T4/10, T4/11 8 07-May-19 15-May-19 0 Tower Erec on for 1NS Tower - Sec on 2 : T4/10, T4/11
TE_S2_90300 Tower Erec on for 1LA Tower - Sec on 2 : T4/1 4 18-May-19 23-May-19 0 Tower Erec on for 1LA Tower - Sec on 2 : T4/1
TE_S2_90400 Tower Erec on for 1LA Tower - Sec on 2 : T4/3 4 24-May-19 28-May-19 0 Tower Erec on for 1LA Tower - Sec on 2 : T4/3
TE_S2_90500 Tower Erec on for 1HS Tower - Sec on 2 : T4/4 5 29-May-19 07-Jun-19 0 Tower Erec on for 1HS Tower - Sec on 2 : T4/4
TE_S2_90510 Tower Erec on for 1HS Tower - Sec on 2 : T4/9 5 11-Jun-19 15-Jun-19 0 Tower Erec on for 1HS Tower - Sec on 2 : T4/9
TE_S2_90600 Tower Erec on for 1HA Tower - Sec on 2 : AT5 5 19-Jun-19 24-Jun-19 0 Tower Erec on for 1HA Tower - Sec on 2 : AT5
Sec on 3 - T5/1 - AT6 82 10-Jun-19 20-Sep-19 28 20-Sep-19, Sec on 3 - T5/1 - AT6
TE_S3_90000 Tower Erec on for 1NS Tower - Sec on 3 : T5/1, T5/2, T5/3 12 10-Jun-19 22-Jun-19 28 Tower Erec on for 1NS Tower - Sec on 3 : T5/1, T5/2, T5/3
TE_S3_90100 Tower Erec on for 1NS Tower - Sec on 3 - T5/4 4 24-Jun-19 27-Jun-19 28 Tower Erec on for 1NS Tower - Sec on 3 - T5/4
TE_S3_90200 Tower Erec on for 1NS Tower - Sec on 3 - T5/5 - T5/8 16 28-Jun-19 16-Jul-19 28 Tower Erec on for 1NS Tower - Sec on 3 - T5/5 - T5/8
TE_S3_90300 Tower Erec on for 1NS Tower - Sec on 3 - T5/9 - T5/12 16 17-Jul-19 05-Aug-19 28 Tower Erec on for 1NS Tower - Sec on 3 - T5/9 - T5/12
TE_S3_90400 Tower Erec on for 1NS Tower - Sec on 3 - T5/13 4 06-Aug-19 09-Aug-19 28 Tower Erec on for 1NS Tower - Sec on 3 - T5/13
TE_S3_90500 Tower Erec on for 1NS Tower - Sec on 3 - T5/15 & T5/16 8 10-Aug-19 20-Aug-19 28 Tower Erec on for 1NS Tower - Sec on 3 - T5/15 & T5/16
TE_S3_90600 Tower Erec on for 1NS Tower - Sec on 3 - T5/17 - T5/19 12 21-Aug-19 05-Sep-19 28 Tower Erec on for 1NS Tower - Sec on 3 - T5/17 - T5/19
TE_S3_90700 Tower Erec on for 1HA Tower - Sec on 3 - T5/14 5 06-Sep-19 12-Sep-19 28 Tower Erec on for 1HA Tower - Sec on 3 - T5/14
TE_S3_90800 Tower Erec on for 1HA Tower - Sec on 3 - AT6 5 13-Sep-19 20-Sep-19 28 Tower Erec on for 1HA Tower - Sec on 3 - AT6
Stringing Works 90 12-Sep-19 30-Dec-19 0 30-Dec-19, Stringing Works
Stringing Sec on 1 from AT1-AT5 48 12-Sep-19 08-Nov-19 0 08-Nov-19, Stringing Sec on 1 from AT1-AT5
STG_S1_1000 Prepara on Works for Stringing Sec on 1 - AT1 - AT5 11 12-Sep-19 26-Sep-19 0 Prepara on Works for Stringing Sec on 1 - AT1 - AT5
STG_S1_1100 Insulator Hois ng at Sec on 1 - AT1 - AT5 8 23-Sep-19 01-Oct-19 0 Insulator Hois ng at Sec on 1 - AT1 - AT5
STG_S1_1200 Running out Pilot Wire and Hanging Pulley Block at Sec on 1 - AT1 - AT5 6 02-Oct-19 08-Oct-19 0 Running out Pilot Wire and Hanging Pulley Block at Sec on 1 - AT1 - AT5
STG_S1_1300 OPGW Paying Out at Sec on 1 - AT1 - AT5 6 09-Oct-19 15-Oct-19 0 OPGW Paying Out at Sec on 1 - AT1 - AT5
STG_S1_1400 Conductor Paying Out at Sec on 1 - AT1 - AT5 6 16-Oct-19 22-Oct-19 0 Conductor Paying Out at Sec on 1 - AT1 - AT5
STG_S1_1500 Conductor & OPGW Sagging, Tensioning & Clamping at Sec on 1 - AT1 - AT5 6 23-Oct-19 29-Oct-19 0 Conductor & OPGW Sagging, Tensioning & Clamping at Sec on 1
STG_S1_1600 Installa on of Dampers, Spacers and JUmpers at Sec on 1 - AT1 - AT5 10 29-Oct-19 08-Nov-19 0 Installa on of Dampers, Spacers and JUmpers at Sec on 1 - AT1
Stringing Sec on 2 from AT5-AT8 42 09-Nov-19 30-Dec-19 0 30-Dec-19, Stringing Sec on 2 from AT5-AT8
STG_S2_1000 Prepara on Works for Stringing Sec on 2 - AT5-AT8 11 09-Nov-19 22-Nov-19 0 Prepara on Works for Stringing Sec on 2 - AT5-AT8
STG_S2_1100 Insulator Hois ng at Sec on 2 - AT5-AT8 8 15-Nov-19 23-Nov-19 0 Insulator Hois ng at Sec on 2 - AT5-AT8
STG_S2_1200 Running out Pilot Wire and Hanging Pulley Block at Sec on 2 - AT5-AT8 6 21-Nov-19 27-Nov-19 0 Running out Pilot Wire and Hanging Pulley Block at Sec on
STG_S2_1300 OPGW Paying Out at Sec on 2 - AT5-AT8 6 28-Nov-19 04-Dec-19 0 OPGW Paying Out at Sec on 2 - AT5-AT8
STG_S2_1400 Conductor Paying Out at Sec on 2 - AT5-AT8 6 05-Dec-19 11-Dec-19 0 Conductor Paying Out at Sec on 2 - AT5-AT8
STG_S2_1500 Conductor & OPGW Sagging, Tensioning & Clamping at Sec on 2 - AT5-AT8 6 12-Dec-19 18-Dec-19 0 Conductor & OPGW Sagging, Tensioning & Clamping a
STG_S2_1600 Installa on of Dampers, Spacers and JUmpers at Sec on 2 - AT5-AT8 10 18-Dec-19 30-Dec-19 0 Installa on of Dampers, Spacers and JUmpers at Sec
Avia on Light, Warning Sphere, ATN & Reclearing 113 28-Aug-19 15-Jan-20 19 15-Jan-20, Avia on Light, Warning Sphere, ATN &
STG_MISC_2200 Installa on of ATN - Sec on 1 35 28-Aug-19 12-Oct-19 27 Installa on of ATN - Sec on 1
STG_MISC_2500 Reclearing Works - Sec on 1 Stringing 40 09-Oct-19 25-Nov-19 3 Reclearing Works - Sec on 1 Stringing
STG_MISC_2300 Installa on of ATN - Sec on 2 35 14-Oct-19 23-Nov-19 27 Installa on of ATN - Sec on 2
STG_MISC_2100 Installa on of Warning Sphere 14 31-Oct-19 16-Nov-19 50 Installa on of Warning Sphere
STG_MISC_2400 Installa on of ATN - Sec on 3 35 25-Nov-19 06-Jan-20 27 Installa on of ATN - Sec on 3
STG_MISC_2600 Reclearing Works - Sec on 2 Stringing 40 28-Nov-19 15-Jan-20 1 Reclearing Works - Sec on 2 Stringing
STG_MISC_2000 Installa on of Avia on Light 14 17-Dec-19 03-Jan-20 11 Installa on of Avia on Light
Line Turn Works at Eastwood and Tudan 109 11-Feb-19 25-Jun-19 4 25-Jun-19, Line Turn Works at Eastwood and Tudan
LINE_TURNIN_2000 Founda on Works for Line Turn In to Eastwood 14 11-Feb-19 26-Feb-19 11 Founda on Works for Line Turn In to Eastwood
LINE_TURNIN_2210 Founda on Works for Line Turn In to Tudan Miri Airport Line 14 05-Mar-19 20-Mar-19 11 Founda on Works for Line Turn In to Tudan Miri Airport Line
LINE_TURNIN_2100 Tower Erec on for Line 1 & 2 for Turn In to Eastwood 14 02-May-19 17-May-19 4 Tower Erec on for Line 1 & 2 for Turn In to Eastwood
LINE_TURNIN_2200 Line Turn in to Line 1 & 2 in Eastwood Substa on 14 18-May-19 08-Jun-19 4 Line Turn in to Line 1 & 2 in Eastwood Substa on
LINE_TURNIN_2220 Tower Erec on for Line 1 & 2 for Turn In to Tudan Miri Airport Line 14 18-May-19 08-Jun-19 4 Tower Erec on for Line 1 & 2 for Turn In to Tudan Miri Airport Line
LINE_TURNIN_2230 Line Turn in to Line 1 & 2 in Tudan Miri Airport Line 14 10-Jun-19 25-Jun-19 4 Line Turn in to Line 1 & 2 in Tudan Miri Airport Line
Slope Protec on 159 25-Jun-19 07-Jan-20 28 07-Jan-20, Slope Protec on
SLOPE_3100 Provision of Slope Protec on - Sec on 2 90 25-Jun-19 15-Oct-19 97 Provision of Slope Protec on - Sec on 2
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 13 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Sarawak Energy Berhad PLS160131-Marudi Junction to Airport 132kV TL Persafe Engineering JV XD Power Transmission (M)
Activity ID Activity Name Original Duration Start Finish Total Float Critical 2018 2019 2020
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
SLOPE_3000 Provision of Slope Protec on - Sec on 1 90 28-Aug-19 17-Dec-19 44 Provision of Slope Protec on - Sec on 1
SLOPE_3200 Provision of Slope Protec on - Sec on 3 90 21-Sep-19 07-Jan-20 28 Provision of Slope Protec on - Sec on 3
Inspec on, Tes ng and Commissioning 325 04-Jan-19 11-Feb-20 0 11-Feb-20, Inspec on, Tes ng and Commi
Tower Earthing Checking 124 07-May-19 11-Oct-19 24 11-Oct-19, Tower Earthing Checking
TWR_EARTH_50100 Sec on 2 Tower Earthing Checking 45 07-May-19 03-Jul-19 55 Sec on 2 Tower Earthing Checking
TWR_EARTH_50000 Sec on 1 Tower Earthing Checking 45 16-Jul-19 11-Sep-19 0 Sec on 1 Tower Earthing Checking
TWR_EARTH_50200 Sec on 3 Tower Earthing Checking 45 17-Jul-19 12-Sep-19 47 Sec on 3 Tower Earthing Checking
TWR_EARTH_50300 Sec on 4 Tower Earthing Checking 45 15-Aug-19 11-Oct-19 24 Sec on 4 Tower Earthing Checking
MC Walkdown 305 04-Jan-19 16-Jan-20 0 16-Jan-20, MC Walkdown
Founda on Works 206 04-Jan-19 19-Sep-19 11 19-Sep-19, Founda on Works
MCWD_50000 Sec on 1 Fdn Work MC Walkdown 60 04-Jan-19 16-Mar-19 124 Sec on 1 Fdn Work MC Walkdown
MCWD_50100 Sec on 2 Fdn Work MC Walkdown 60 19-Mar-19 30-May-19 0 Sec on 2 Fdn Work MC Walkdown
MCWD_50200 Sec on 3 Fdn Work MC Walkdown 60 16-Apr-19 02-Jul-19 54 Sec on 3 Fdn Work MC Walkdown
MCWD_50300 Sec on 4 Fdn Work MC Walkdown 60 04-Jul-19 19-Sep-19 11 Sec on 4 Fdn Work MC Walkdown
Stringing Works 56 09-Nov-19 16-Jan-20 0 16-Jan-20, Stringing Works
MCWD_50800 Sec on 1 Stringing Works MC Walkdown 14 09-Nov-19 26-Nov-19 42 Sec on 1 Stringing Works MC Walkdown
MCWD_50900 Sec on 2 Stringing Works MC Walkdown 14 31-Dec-19 16-Jan-20 0 Sec on 2 Stringing Works MC Walkdown
Tower Erec on 139 07-May-19 29-Oct-19 24 29-Oct-19, Tower Erec on
MCWD_50500 Sec on 2 Tower Erec on MC Walkdown 60 07-May-19 20-Jul-19 55 Sec on 2 Tower Erec on MC Walkdown
MCWD_50400 Sec on 1 Tower Erec on MC Walkdown 60 16-Jul-19 01-Oct-19 0 Sec on 1 Tower Erec on MC Walkdown
MCWD_50600 Sec on 3 Tower Erec on MC Walkdown 60 17-Jul-19 02-Oct-19 47 Sec on 3 Tower Erec on MC Walkdown
MCWD_50700 Sec on 4 Tower Erec on MC Walkdown 60 15-Aug-19 29-Oct-19 24 Sec on 4 Tower Erec on MC Walkdown
Pre-Commissioning 175 04-Jul-19 06-Feb-20 0 06-Feb-20, Pre-Commissioning
PRECOM_60000 Intenal Rec fica on Works - Sec on 1 Stringing 175 04-Jul-19 06-Feb-20 0 Intenal Rec fica on Works - Sec on 1 Strin
PRECOM_60100 Intenal Rec fica on Works - Sec on 2 Stringing 96 12-Oct-19 06-Feb-20 0 Intenal Rec fica on Works - Sec on 2 Strin
PRECOM_60400 Splicing of OPGW 12 31-Dec-19 14-Jan-20 10 Splicing of OPGW
PRECOM_60500 Laying OPUG to Marudi Junc on Sub 4 31-Dec-19 04-Jan-20 10 Laying OPUG to Marudi Junc on Sub
Final Tes ng and Commissioning 20 17-Jan-20 11-Feb-20 0 11-Feb-20, Final Tes ng and Commissionin
FTCOM_70000 Final Tower and Line Checking by Owner's Staff 16 17-Jan-20 06-Feb-20 0 Final Tower and Line Checking by Owner's S
FTCOM_70100 Rec fica on as per Defect List 15 17-Jan-20 05-Feb-20 1 Rec fica on as per Defect List
FTCOM_70300 OPGW End to End Test 2 21-Jan-20 22-Jan-20 13 OPGW End to End Test
FTCOM_70400 Final Line Test 2 07-Feb-20 08-Feb-20 0 Final Line Test
FTCOM_70500 Line Commissioning 2 10-Feb-20 11-Feb-20 0 Line Commissioning
Demobilisa on and Handover 15 23-Jan-20 11-Feb-20 0 11-Feb-20, Demobilisa on and Handover
DEMOB_8000 Demobilisa on of Construc on Team 15 23-Jan-20 11-Feb-20 0 Demobilisa on of Construc on Team
DEMOB_8200 Submission of OPGW End to End Test 2 23-Jan-20 24-Jan-20 13 Submission of OPGW End to End Test
DEMOB_8100 Site Handing Over 3 09-Feb-20 11-Feb-20 0 Site Handing Over
DEMOB_8300 Project Comple on 0 11-Feb-20 0 Project Comple on,
Remaining Level of Effort Remaining Work summary Date Revision Checked Approved
Page 14 of 14
Project Schedule
Actual Level of Effort Critical Remaining Work
Actual Work Milestone