Exam For HR
Exam For HR
Choose the correct answer for each question, Circle it clearly within the given time limit, and
ensure all work is done independently. Allocated time (30 Min)
13. What type of contract uses a fixed price for the total scope of work?
a) Cost Plus Contract
b) Lump-Sum Contract
c) Time and Materials Contract
d) Unit Price Contract
20. In risk management, which term refers to reducing the impact of a risk?
A) Risk avoidance
B) Risk mitigation
C) Risk transfer
D) Risk acceptance
1. Contract Administration Expert
II. Provide clear, concise, and well-structured answers to each question, using relevant examples
or explanations where necessary, Allocated time for each (5 min)
Question 1:
For each type, discuss the advantages and disadvantages from the perspectives of both the owner
and the contractor.
Question 2:
During the execution of a road construction project, the contractor identifies the following issues:
How should the contractor submit a claim for these issues? List the key steps.
What supporting documents are necessary to justify the claim?
Question 3:
A dispute has arisen between the owner and the contractor regarding the quality of the concrete
used in the construction of a railway overpass bridge. The contract specifies a minimum concrete
strength of 40 MPa, but the test results show 35 MPa in certain sections.
II. Provide clear, concise, and well-structured answers to each question, using relevant examples
or explanations where necessary, Allocated time for each (5 min)
Question 1:
Explain the concept of a claim in construction projects and discuss the following types of claims:
1. Time-Related Claims
2. Cost-Related Claims
3. Disruption Claims
For each type, provide one example of a scenario where the claim might arise and outline the steps
for proper submission.
Question 2:
Client-caused delay: The client delayed providing access to the construction site by 45 days.
Weather delay: Unseasonal heavy rainfall caused a 20-day delay in earthworks.
1. Differentiate between excusable and non-excusable delays and classify the above delays.
2. Prepare a delay analysis method to justify a time extension claim for the client-caused
delay.
Question 3:
A contractor incurred additional costs due to the following events during a railway track
construction project:
Question 1:
Explain the tendering process in a construction project from the pre-tender phase to the post-
tender phase. Discuss the key roles of a Tender Engineer in ensuring the preparation and
submission of a competitive bid.
Question 2:
As a Tender Engineer, you are tasked to estimate the cost for reinforced concrete work with the
following details:
Task:
You are reviewing the tender document for a large road construction project. Identify and discuss:
1. The critical components of the tender document that must be reviewed for compliance.
2. Two common risks during the tender preparation process and how to mitigate them.
5. Construction Planning Engineer
II. Provide clear, concise, and well-structured answers to each question, using relevant examples
or explanations where necessary, Allocated time for each (5 min)
Question 1:
You have been assigned to prepare a construction schedule for a highway construction project
that includes the following phases:
1. Site Preparation
2. Earthworks (Excavation and Filling)
3. Sub-Base and Base Layer Construction
4. Asphalt Paving
5. Road Marking and Signage
You are managing a construction project and need to develop a resource allocation plan for the
following tasks:
You have a total of 10 workers available on site, but you must ensure that no worker is over-
utilized beyond their capacity of working 8 hours per day.
1. Develop a resource leveling plan to allocate the workers efficiently across the tasks.
2. Explain how you would address any potential conflicts or overloading of resources.
3. Discuss the impact of poor resource leveling on project timelines.
Question 3:
A construction project is at the midway point. The planned duration for the entire project is 180
days, and the scheduled progress for 90 days was 50%. However, after 90 days, only 40% of
the work has been completed. As a Construction Planning Engineer, explain:
1. How you would calculate the Schedule Performance Index (SPI) and interpret its
meaning.
2. What corrective actions would you recommend to bring the project back on track.
3. Discuss the importance of continuous project monitoring and control during
construction.
6. Senior Quantity Surveyor
II. Provide clear, concise, and well-structured answers to each question, using relevant examples
or explanations where necessary, Allocated time for each (5 min)
Question 1:
Question 2:
Question 3:
You are tasked with preparing a detailed cost estimate for a building project with the following
details:
Project Scope:
o Foundation works: 250 m³ of concrete (C-25)
o Wall construction: 1,500 m² brick masonry
o Plastering works: 1,200 m² internal walls
o Roofing: 800 m² corrugated metal sheets
Unit Costs:
o Concrete (C-25): 6,500 ETB/m³
o Brick masonry: 450 ETB/m²
o Plastering: 250 ETB/m²
o Roofing: 1,000 ETB/m²
1. Calculate the total cost for each work item and determine the total estimated project
cost.
2. Discuss three factors that may cause variations in cost during project execution.
Question 5:
You are required to measure quantities and prepare a Bill of Quantities (BOQ) for the following
works:
1. Excavation: 60 meters long, 1.5 meters wide, and 1 meter deep trench.
2. Concrete Slab: 100 m² of slab with a thickness of 0.2 meters.
3. Painting: 200 m² of wall surface with two coats of paint.
Question 1:
You are tasked with ensuring the quality of the design for a bridge project. Describe the step-
by-step process you would follow to ensure the design meets all required standards and
specifications.
The design team has submitted the final structural design of a multistory building. During your
review, you notice discrepancies in the structural drawings and material specifications.
1. What standards and codes would you use to evaluate the quality of the design?
2. Describe your approach to addressing and rectifying these discrepancies.
Question 3:
During the review of a highway interchange design, you identify a potential risk of drainage
failure due to improper slope calculations.
1. What steps would you take to verify the design and eliminate this risk?
2. Describe how you would incorporate risk management measures in the design process
to avoid similar issues in future projects.