Critical Path Method
Critical Path Method
(CPM)
BBA - 7
Critical Path Method (CPM)
CPM is a network diagramming technique used to predict
total project duration.
A critical path for a project is the series of activities that
determines the earliest time by which the project can be
completed.
The critical path is the longest path through the network
diagram and has the least amount of slack or float.
Slack or float is the amount of time an activity can be
delayed without delaying a succeeding activity or the project
finish date.
CPM - Approach
Calculating the Critical Path
Develop a good network diagram.
Forward
ES EF Pass
Float
Backward LS LF
Pass
3 6 6 14
Activity 2 Activity 4
Float=0 Float=0
0 3
3 6 6 14
Start Activity 1
Float=0 14 18
Activity 5
0 3
Float=0
3 9 14 18
Activity 3
Activity Duration Float=5
Activity 1 3 8 14
Activity 2 3
Paths Duration
Activity 3 6
Start, 1, 2, 4,5, End 18
Activity 4 8 End
Start, 1, 3, 5, End 13
Activity 5 4
Figure 6-8. Determining the Critical Path
for Project X
More on the Critical Path
The critical path does not necessarily contain all the
critical activities; it only accounts for time.
Example like growing grass was on the critical path for
Disney’s Animal Kingdom.
There can be more than one critical path if the
lengths of two or more paths are the same.
The critical path can change as the project
progresses.
Using the Critical Path to Shorten a
Project Schedule
Three main techniques for shortening schedules: