Electrical Part
Electrical Part
PART-C
Scope & Specifications of Electrical & Mechanical Works
INDEX
Sr. No Description
2 Terms & Conditions for Association of Specialized Firms for E & M Works
4 General Conditions
PROFORMA OF SCHEDULES
SCHEDULE ‘A’
Schedule of quantities: As per NIT document.
SCHEDULE ‘D’
Extra schedule for specific requirements / As per NIT document.
document for the work, if any:
SCHEDULE ‘E’
Reference to General Conditions of Contract: General Conditions of Contract 2023 Construction
Works, CPWD with amendments issued upto the
last date of submission of tender.
Name of Work: Construction of GYM (Fitness Centre) at NDS
Stadium Leh, UT of Ladakh. (Balanced work
related to E&M)
Clause 10B(ii)
Whether Clause 10 B(ii) shall be applicable No
Clause 10C
Component of labour expressed as percent of Not applicable
value of work:
Clause 10CA Not applicable
Clause 10CC
Clause 10CC to be applicable in contracts with Applicable
stipulated period of completion exceeding the
period shown in next column
Component of Electrical construction materials 80%
expressed as percent of value of E&M
component of work :
Component of labour –expressed as percent of 20%
value of E&M component of work:
Clause 11
Specifications to be followed for execution of As per CPWD General specifications for
work Electrical Works, Part-I Internal (2023), Part-II
External (2023), Part-III Lifts & escalators
(2003), Part-IV Substation (2013), Part-V Wet
riser & sprinkler system (2020), Part-VI Fire
Detection and Alarm System (2018), Part-VII DG
set (2013), Part VIII Gas Based Fire
Extinguishing System – 2013, HVAC (2017).
(I) All above specifications shall be applicable
with corrections slips up to the last date of
submission/uploading of bid.
(II) Wherever the CPWD Specification are not
given, the works shall be executed as per the
additional Specification & terms & conditions
mentioned in the NIT, BIS Specifications & NBC
2016.
(III) The direction of the Engineer-in-Charge
shall be followed in absence of the above two at
Serial No. I & II.
Clause 12 Applicable
Type of Work Construction work
Clause 12.1 & Clause 12.2 As per Major component
Clause 16
Competent Authority for deciding reduced rates As per major component.
Clause 17 As per major component.
Clause 19 Competent Authority to decide penalty for each
default:
Clause 19C
Authority to decide penalty for each default EE cum SM ( E ) LPED or successor thereof
Clause 19D
Authority to decide penalty for each default EE cum SM ( E ) LPED or successor thereof
Clause 19G
Authority to decide penalty for each default EE cum SM ( E ) LPED or successor thereof
Clause 19K
Authority to decide penalty for each default EE cum SM ( E ) LPED or successor thereof
Correction = NIL, Insertion = NIL, Overwriting = NIL, Deletion = NIL
Clause 25
Constitution of Dispute Redressal Committee Same as per major component.
(DRC)
Conciliator-
Arbitrator Appointing Authority-
Place of Arbitration-
Clause 32
The Agency who will provide the Technical Staff have adequate Knowledge E&M services
Terms & Conditions for Association of specialized firms for E&M Works
Estimated cost of various electrical & Mechanical services & similar works definition are as under:
NOTE: - If the main contractor associate the OEM or its authorized channel partner for the
execution of any of the subhead given below then the minimum eligibility criteria given below shall
not be applicable.
1. Internal & External Electrical 30,70,081 The main contractor, if does not fulfill the
Installations criteria himself, shall associate with contractor
for execution of this Sub head of work,
possessing valid Electrical Contractor License
of appropriate Voltage/Class.
2. Solar PV Power Plant 20,35,120 The main contractor shall have to associate with
agency fulfilling the following eligibility
criteria having successfully completed during
last seven years ending up to previous day of
last date of submission of tender as given below
Three similar works, each of value not less than
40% of component cost.
OR
Two similar works, each of value not less than
60% of component cost.
OR
One similar works, each of value not less than
80% of component cost.
Similar work shall mean "SITC of Solar PV
Power Generation System”
3. Solar Water Heating System 2,31,918 The main contractor shall have to associate with
agency fulfilling the following eligibility
criteria having successfully completed during
last seven years ending up to previous day of
last date of submission of tender as given below
Three similar works, each of value not less than
40% of component cost.
OR
Two similar works, each of value not less than
Correction = NIL, Insertion = NIL, Overwriting = NIL, Deletion = NIL
The value of executed works shall be brought to current costing level by enhancing the actual value of
work at simple rate of 7% per annum; calculated from the date of completion to last date of
submission of bids.
However, the contractor shall also be allowed to carry out the works included in the enlistment
provisions as per the eligibility and the category of the enlistment, without associating any specialized
agency provided.
The contractor shall have to associate other agency(s) for execution of each of the work(s) mentioned
above including works of Fire Fighting & Fire Alarm System, UPS, Solar PV Power Plant and other
specialized E&M Services forming part of the tender, which fulfills the eligibility criteria for these
works(s) duly taking prior approval from the department. However, the contractor shall also be
eligible to carry out himself any or all of these works without associating any specialized agency
provided:
He fulfills the prescribed eligibility criteria respectively for these work(s).
Or
He directly procures the equipment of approved make from manufacturer and get installed from
authorized agency/service provider of the manufacturer or specialized agency as per criteria mentioned
in NIT.
Eligibility criteria of each such agency to be associated are to be set out in the tender documents. The
Contractor and the associated specialized agencies shall give required affidavit to confirm their
association.
The Department may approve change of associated agency in case it is required during the currency of
the contract.
Note. The main contractor/agency has to submit details of such agency to be associated to the
Engineer- in- charge (of E&M Work) within 15 days from date of start of work. The associated agency
shall be approved by Engineer-in-charge (of E&M Work). In case the main contractor intends to
change associated agency/agencies during the operation of the contract, he shall obtain prior approval
of Engineer- in-charge (of E&M Work). The new agency/agencies shall also have to satisfy the laid
down eligibility criteria mentioned above. In case Engineer-in-charge is not satisfied with the
performance of any agency, he can direct the main contractor to change the agency executing such
items of work and this shall be binding on the contractor.
Approval of the specialized agencies for each specialized work shall be obtained from the Engineer-
in-Charge (E&M works) within 15 days of award of work. Even if, such specialized items of work
shall be executed by the specialized agencies at later date the work shall be deemed to be executed by
the tenderer for all purposes and the responsibility of the quality of items of works executed etc. shall
continue to be that of the tenderer only.
The applicant should submit the willingness from eligible electrical contractors to get associated with
the applicant for execution of the electrical component of works in wholesome manner and as per the
conditions set out in the MOU to be entered into, between the one who is awarded the work and the
associated eligible electrical contractor. (Format of willingness and MOU is given below)
In support of the eligibility conditions of the proposed associated electrical contractor, copy of their
registration documents, Electrical Contractor’s License, GST documents, eligibility documents duly
attested by the applicants (Main Contractor) shall be submitted to the EE(E) who will submit these
documents to the CE&ED for deciding the eligibility. Such associate electrical contractor will certify
that they are not debarred as on the day of application for sale of tender.
In the event of the concerned E&M agency not performing satisfactorily or failure of associate/ sub-
contractor to complete the E&M work, the main contractor on the written direction of the department,
shall remove the Associate/sub-contractor deployed on the work and shall submit name of new
associate who fulfills the conditions mentioned in NIT to execute the leftover work without any loss of
time or variation in cost to the department in this regard. Such associates shall also enter into
Agreement with the main tenderer shall meet all the guarantee for the equipment already supplied for
which payment has been released by the department in part. If any equipment supplied for the work,
during the currency of the earlier Associate/sub-contractor and paid partly by the department becomes
redundant /not in a position to be installed and commissioned and put to beneficial use due to change
in agency for execution of E&M work, the main contractor shall be liable for replacement of the
equipment(s) at no cost to Department. No change of Electrical Contractor will be allowed without
prior approval of the CE& ED.
Executive Engineer (E) shall be the Engineer-in-charge as far as electrical works are concerned.
Special Conditions for each of electrical work subhead are appended with this tender. It will be
obligatory on the part of the contractor/tenderer to sign the tender documents for all the component
parts.
All the equipment/items shall be in consensus with the local climatic condition of the Leh-Ladakh i.e.
(-40’c to 40’c).
The main contractor shall be responsible and liable for proper and complete execution of the Electrical
work and ensure coordination and completion of both Civil and Electrical work.
The main contractor has to enter into agreement with contractor(s) associated by him for execution of
E&M subheads. Copy of such agreement shall be submitted to EE(E) in charge as well as to EE(C).
The associate or sub-contractor shall attend the inspection of the work by the Engineer-in-Charge of
E&M works as and when required.
The agencies executing the Electrical work should have valid license for LT/HT as applicable.
NET Metering facility shall be provided by the main agency to supply surplus energy generation from
the building to the main grid. If there is no policy of evacuation of surplus electricity generation by the
Power distribution department (PDD)/utility service department of the UT of Ladakh (on daily basis
and annual basis) to be submitted by the bidder.
FORM-G
PROPOSAL FOR ELIGIBLE ASSOCIATING AGENCIES FOR MINOR COMPONENTS OF
WORK
If I/we hereby propose the following agencies as per mentioned against each for executing
corresponding minor components of work. Their consent letters are also attached.
Note: Self Attested photocopies of enlistment order, valid electrical contractor license, work experience
certificates of each agency for each component of E&M work shall be submitted
Signature of Contractor
FORM – H
Name of Work: Construction of GYM (Fitness Centre) at NDS Stadium Leh, UT of Ladakh. (
Balanced work related to E&M).
I / We will execute the work as per specifications and conditions of the agreement and as per
directions of the Engineer-in-Charge for the corresponding minor work till the completion of the work.
I / We will be responsible for necessary action to handover the installations and for rectifications of
defects and repair during the maintenance / warranty period.
Also I / We will employ full time technically qualified Engineer / Supervisor for the minor
components of the work as required for the work. I / We will attend inspection of officers of the
department as and when required.
Date:
Address Address
FORM – I
Name of Work: Construction of GYM (Fitness Centre) at NDS Stadium Leh, UT of Ladakh. ( Balanced
work related to E&M)
We state that M.O.U between us will be treated as an agreement and has legality as per Indian Contract Act
(amended upto date) and the department (CPWD) can enforce all the terms and conditions of the agreement
for execution of the work. Both of us shall be responsible for the execution of the work as per agreement to
the extent this MOU allows. Both the parties can be paid consequent to the execution as per agreement to
the extent this MOU permits. In case of any dispute, either of us will go for mediation by the Engineer-in-
Charge. Any of us may appeal against the mediation to the Chief Engineer cum Executive Director,
CPWD, Leh. His decision shall be final and binding on both of us.
Date: Date:
Place: Place:
(From major component contractor side) (From minor component contractor side)
ANNEXURE – X
For M/S…………………………………………………………………
Counter Signature,
Major Contractor
GENERAL CONDITIONS
(Electrical & Mechanical Services)
Name of Work: Construction of GYM (Fitness Centre) at NDS Stadium Leh, UT of Ladakh. ( Balanced
work related to E&M)
Scope of work covers planning, Engineering, designing, supply, installation, fixing, execution, testing and
commissioning of all Electrical & Mechanical services required to be provided in the said scheme & as
detailed in the NIT. The work shall be executed as per scope & specifications of E & M works given hereafter
in respective head / part of the scheme or sub-head. If any services/work required to make the building/
scheme habitable & functional, including the statutory compliance, is not specifically mentioned in the scope
of services, the same is deemed to be included within the scope of this tender and nothing extra shall be paid
on this account. The agency has to get approval of the Engineer in charge/ CPWD for every stage of
planning and execution.
The tenderer is advised to read and examine the tender documents for the work and the set of drawings in the
tender document and also available in office of Engineer-in-charge. He should himself inspect and examine
the site and its surroundings before submitting his tender.
Separate conditions & specification and scope are included in this tender for each of the sub-head. The
contractor shall quote the amount/rates lump-sum in figure/percentage accurately in schedule of financial
quote, as prescribed there.
The contractor(s) shall submit a detailed program of execution in accordance with the master
programme/milestone within ten days from the date of issue of award letter.
Agency has to provide the fully furnished and fully heated site office suitable for all weather condition for
CPWD staff having minimum area of 50 Sq m with the supporting skilled, semiskilled and unskilled staff as
per direction of Engineer-in-Charge
Note:
All words have to be executed as per specifications provided in the bid document, CPWD Specifications,
National building Code 2016 (in case of difference, if any, stringent/ higher specification of the two shall be
followed) and ECBC2017 Code. In absence of CPWD Specifications, IS Codes, National Building Code 2016
sound engineering practices shall be adopted as per order of precedence defined in the contract. The scope of
works & specification are given in general but they are not exhaustive i.e. does not mention all the incidental
works required to be carried out for complete execution of the item of work. The work shall be carried out, all
in accordance with true intent and meaning of the specifications and the drawings taken together, regardless of
whether the same may or may not be particularly shown on the drawings and /or described in the
specification, provided that the same can be reasonably inferred there from.
There may be several incident works, which are not mentioned in the contract document/specifications but
will be necessary to complete the item in all respect. All these incidental works/ costs which are not
mentioned, but are necessary to complete the work shall be deemed to have been costs which are note
mentioned, but are necessary to complete the work shall be deemed to have been included in the overall
amount quoted by the contractor for various components of work. No adjustment of rates shall be made for
any variation in quantum of incidental works due to variation/change in actual working drawings. Also, no
adjustment of rates shall be made due to any change in incidental works or any other deviation in such
element of work (which is incidental to the items of work and are necessary to complete such items in all
respects) on account of the directions of Engineer-in-charge. Nothing extra shall be payable on this account.
In case, some items are missing in the scope of work 0or specifications in the bidding documents the same
shall be taken from the specification mentioned in similar type of items mentioned for similar type of building
in the scope of work or shall be executed as given in the CPWD Specifications, NBC-2016, IS Codes or
according to sound engineering practices so as to make the building including related services fully functional.
No claim what so ever may be entertained at later stage. All cost of providing and making building with
services works fully complete in all aspect unless specifically mentioned in the contract document and making
buildings with services fully are included in the cost tendered for this work.
clearances, structural design & drawings, constructions, & commissioning of buildings & services and
obtaining completion certificate in accordance with layout plan and architectural / structural drawings.
The contractor shall ensure quality control measures on different aspects of construction including materials,
workmanship and correct construction methodologies to be adopted. The quality assurance programme should
include method statement for various items of work to be executed along with check lists to enforce quality
control.
The contractor shall submit technical data sheet of various equipment and machinery and shop drawings of
various E&M services mentioned in the tender as per requirement of sites before execution of work for
approval.
Frequency and type of tests of various Materials/items/ article shall be conducted as per specifications and
relevant BIS-Codes. The test results confirm to the specification/code
In addition to above any data and detail asked by Engineer in charge to finalize and accept the scheme shall be
provided on the established standard/guidelines/codes etc.
Clearances to be taken by the firm before start of work: The above schemes of all the E&M works shall have
to meet all the requirements of local bodies / CEA/ NBC norms as applicable & also meet the technical
specifications of various relevant CPWD specifications/ BIS codes / NBC2016/ ECBC2017 for electrical &
mechanical services.
All the above schemes shall be got approved by respective local bodies / CFO etc. as applicable before
commencement of execution of work at site. During execution, if the local bodies etc. require a modification,
the same shall be executed without any extra cost. Finally, after execution, obtaining clearances from CEA
(central electrical authority), local fire authorities, DPCC and any other local body, shall be the responsibility
of the contractor All statutory fees / charges required for obtaining clearances from CEA shall be paid by the
contractor.
Three final copies of the documents prepared shall be submitted to Engineer-in-Charge for record. All the
documents created out of the assignment will become the sole property of the Department. The contractor
shall obtain completion certificate after completion of the project from statutory local bodies before handing
over.
Climatic Conditions
All electrical equipment, accessories and fittings employed in electrical installation shall be specified,
designed and derated for continuous and trouble-free operation in the climatic conditions of the equipment
location which are summarized as follows:
GENERAL
The works shall be executed as per CPWD’s General specification for Electrical Works amended up to the
date of opening of eligibility bid, Part-I (Internal- 2023); Part-II (External)-2023; Part-III (Lifts and
Escalators) 2003, Part-IV (Substation) 2013, Part-V (Wet Riser and Sprinkler System for Fire Fighting
Installation)-2006, Part-VI (Fire Detection and Alarm System) 2018, Part-VII DG Set 2013, Part-VIII Gas
based Fire Extinguishing System 2013, HVAC 2017, IE Rules, Indian Standards amended up to date and as
per direction of Engineer- in-Charge. The additional specifications are to be read with above and in case of
any variations; specifications given along with the tender shall apply.
In case of discrepancy between the List of Makes, Tech. Specifications, Drawings etc the following order of
preference shall be observed:
Technical Specifications
CPWD General Specifications
IS/ IEC/International Codes
List of Makes
Note:- The firm is to execute the works using materials of makes specified. However, if the make of same
items is mentioned in more than one sub head/make list, then firm may if so desire, submit its request for the
approval for using that make. The department reserves the right to approve the same, if so considered fit. The
decision of the department shall be final & binding on the firm.
In case of any discrepancy of specifications/conditions in the tender document the following order of
preference will be observed:
Drawings
CPWD general specifications
NBC-2016
IS/IEC/International Codes
The Provision with higher specifications
Decision of Engineer in Charge
Best engineering practice being followed in such works
The main tenderer has to submit the following documents for association of contractor within one month from
the start of the work. And shall get approval of association of agency from Engineer in charge of E&M work
(minor component).
In support of the eligibility conditions of the proposed Associated Contractor, copy of their Registration
documents, Electrical License, GST documents, completion certificate, copy of the final bill duly attested by
the applicants (Main Contractor) shall be submitted to the Executive Engineer cum Senior Manager (E),
CPWD, Leh for deciding the eligibility. Each such Associated Contractor will certify that they are not
debarred as on the day of application for tender participation. Proposal for associating agency for minor
components of work shall be submitted in Form- “G” of this tender document from each associate
independently for all electrical and mechanical components.
The main contractor should submit an affidavit of MoU signed with eligible associated contractor. The MoU
in the enclosed Form ‘I’ shall be signed by both the parties, main contractor as 1st party and associated
contractor as 2nd party independently for all electrical and mechanical components.
In the event of the concerned E&M agency not performing satisfactorily or failure of associated contractor to
complete the E&M work, the main contractor on written directions of the Engineer in charge, shall remove the
Associate contractor deployed on the work and shall submit name of new associate agency who fulfill the
conditions mentioned in the tender document to execute the left-over work without any loss of time or
variation in the cost to the department. Such associates shall also give an undertaking along with the man
tenderer but both of them together will stand guarantee for the equipments already supplied for which
payment has been released by the department in part. If any equipment supplied for the work, during the
currency of the earlier Associate contractor and paid partly by the Dept., becomes redundant / not in a position
to be installed and commissioned and put to beneficial use due to change in agency for execution of E&M
work, the main contractor shall be liable for replacement of the equipment(s) at no cost to Department. No
change of Associated Contractor will be allowed without prior approval of the Engineer-in-charge of the
work.
2)In respect of all works, the materials shall be procured only from the original equipment manufacturers /
authorized dealers of OEM. The contractor shall submit all documentary details in fulfillment of this
conditions regarding procurement of materials including relevant test certificates. The Contractor has to
submit in respect of all material the Bill, Manufacturer test certificates, transportation detail, Dealer
certificate, Operation, maintenance and Installation manual, Warranty/ Guarantee certificate, custom
certificate etc. and any other document as asked by Engineer in charge. The work executed by Proposed
associate agency shall be complete work including material, labour, T&P and other related activities) (No
petty/labour contract work will be considered).
It will be obligatory on the part of the contractor / tenderer to upload the tender documents for all the
component parts. The main contractor shall be responsible and liable for proper and complete execution of the
E&M work and ensure coordination and completion of both civil and E&M work. The main contractor has to
enter into agreement with contractor associated by him for execution of minor component. Copy of such
agreement shall be submitted to Executive Engineer (E) in charge of minor component. The Associate
contractor as well as main contractor shall attend the inspection of the work by the Engineer-in-Charge of
E&M works as and when required.
Before completion of defect liability period, the main contractor has to submit security deposit of 5% of 80%
of the price of LED fittings for the remaining years warranty period for Led fittings in acceptable form i.e.
FDR/ Bank guarantee to concerned Executive Engineer (E). The Security Deposit deducted from the bills of
Correction = NIL, Insertion = NIL, Overwriting = NIL, Deletion = NIL
contractor shall be refunded to the main contractor only after submission of above security deposit. Deposit
deducted for total work and balance amount only will be refunded after completion of defect liability period.
The LED Security Deposit will be released after completion of warranty period of 5 years to the main
contractor.
RATES
No foreign exchange shall be made available by the Department for importing (purchase) of equipment,
plants, machinery, materials of any kind or any other items required to be carried out during execution of the
work. No delay and no claim of any kind shall be entertained from the Contractor, on account of variation in
the foreign exchange rate.
The rates quoted by the tenderer, shall be firm and inclusive of all taxes (including works contract tax), GST,
octroi, entry tax, duties and levies and all charges for packing forwarding, insurance, freight and delivery,
installation, testing, commissioning etc. at site i/c temporary constructional storage, risks, overhead charges,
general liabilities/obligations and clearance from local authorities.
COMPLETENESS OF TENDER
All sundry equipment, fittings, unit assemblies, accessories, hardware items, foundation, foundation bolts,
painting, termination lugs for electrical connections, and all other items which are useful and necessary for
efficient assembly and installation of equipment and components of the work shall be deemed to have been
included in the tender irrespective of the fact whether such items are specifically mentioned in the tender
documents or not.
STORAGE AND CUSTODY OF MATERIALS
The Sub Station room/ or space as allowed, may be used for storage of sundry materials and erection
equipment or else the agency has to make its own arrangements. No separate storage accommodation shall be
provided by the department. Watch and ward of the stores and their safe custody shall be the responsibility of
the contractor till the final taking over of the installation by the department.
COMPLETION PERIOD
The completion period indicated in the tender documents is for the entire work of planning, designing,
approval of drawings etc., arrangement of materials &equipment, delivery at site including transportation,
installation, testing, commissioning and handing over of the entire system to the satisfaction of the Engineer-
in-charge.
GUARANTEE
All equipment shall be guaranteed for a period of minimum 24 months, from the date of taking over the
installation by the user department i.e. Central GST, against unsatisfactory performance and/or break down
due to defective design, workmanship or material. The equipment or components, or any part thereof, so
found defective during guarantee period shall be forthwith repaired or replaced free of cost, to the satisfaction
of the Engineer-in- Charge. In case it is felt by the department that undue delay is being caused by the
contractor in doing this, the same will be got done by the department at the risk and cost of the contractor. The
decision of the Engineer-in- charge in this regard shall be final & building on the contractor.
Safe mechanical and electrical stress on all parts under all specified conditions of operation.
Satisfactory operation during the maintenance period.
The successful tenderer should furnish well in advance three copies of detailed instructions and manuals of
manufacturers for all items of equipment regarding installation, adjustments, operation and maintenance
including preventive maintenance & trouble shooting together with all the relevant data sheets, spare parts
catalogue etc. all in triplicate.
EXTENT OF WORK
The work shall comprise of entire labour including supervision and all materials necessary to make a complete
installation and such tests and adjustments and commissioning, as may be required by the department. The
term complete installation shall not only mean major items of the plant and equipment covered by
specifications but all incidental sundry components necessary for complete execution and satisfactory
performance of installation with all layout charts whether or not those have been specifically mentioned in the
tender document.
17 INDEMNITY
The successful tenderer shall at all times indemnify the department, consequent on this works contract. The
successful tenderer shall be liable, in accordance with the Indian law and regulations for any accident
occurring due to any cause and the contractor shall be responsible for any accident or damage incurred or
claims arising there from during the period of erection, construction and putting into operation the equipment
and ancillary equipment under the supervision of the successful tenderer in so far as the latter is responsible.
The successful tenderer shall also provide all insurance including third party insurance as may be necessary to
cover the risk. No extra payment would be made to the successful tenderer on account of the above.
20.0 PAINTING
The work shall include cost of painting of the entire installation. The major equipment shall be factory final
finish painted. The agency shall be required to do only touching to the damages caused to the painting during
transportation, handling & installation at site, if there is no major damage to the painting. However hangers,
supports etc. of bus trunking shall be painted with required shade including painting with two coats of
anticorrosive primer paint at site.
21.0 TRAINING
The scope of works includes the on job technical training of two persons of department at site. Nothing extra
shall be payable on this account.
All electrical & mechanical fittings / fixtures / appliances, to be provided for the work, should have latest
minimum 5-star rating (of BEE), as available in market.
TESTING PLANS
The testing plan for quality control for major E&M services is attached as Annexure-A. These plans are to be
read along with following guiding notes:-
All routine tests shall be conducted before dispatch of equipment. No equipment shall be dispatched from the
manufacture’s premises without such tests being conducted and test result recorded. These test certificates
shall be given along with the supply of equipment. The Engineer In-charge shall, if he so desires inspect and
witness the pre- delivery tests. For this purpose, the contractor shall give 15 days’ advance notice. Agency
shall arrange for inspection by the department. Department shall bear expenses for inspection as far as
traveling, boarding and / lodging is concerned. However, waiver if any, for inspection shall be at the
discretion of the department without any cost implication but ROUTINE TEST& TYPE TEST Certificates
shall have to be submitted for equipment .Prior to dispatch, all equipment shall be adequately protected &
insured for the whole period of transit, storage and erection against corrosion and incidental damages etc.
from the effect of vermin sunlight, rain, heat and humid climate.
The work shall be carried out as per CPWD General Specifications of Electrical Works Part-I (Internal)
2023, Part-II (External) 2023, Part-IV Substation (2013), Part VII DG sets (2013) , DSR-2018 & DAR-
2018 (E&M) relevant IE rules, NBC 2016, IS standard as amended, Fire bye-laws & Local Bye Laws as
amended upto the last date of the tender.
The work shall be carried out in recessed MS conduit (ISI marked). Wherever required due to site
conditions the conduit shall be placed on the required size of the cable tray. The dimensions and thickness
of the perforated cable tray shall be as DSR-2018 (E&M). The support structure of the cable tray shall be as
per DAR-2018 (E&M).
The electrical& mechanical services such as fans, fittings, fixtures inside the building to be designed &
provided as per table of “Scale of Amenities (Electrical)” given in tender documents.
Lighting design should be carried out as per National lighting Code 2010/NBC-2016/ ECBC guidelines.
Wherever range of illumination for space is mentioned, higher side of Lux level must be taken for design
purpose. If as per the design, the quantity of light fixtures comes out that does not make the symmetry, then
higher number of light fixtures shall be taken to maintain the symmetry.
Ceiling fans shall be provided except staircase/ toilets/bath rooms/ terrace/corridor and open areas. Only
BLDC type ceiling fans of size 1400/1200 mm shall be used. The number of fans and their optimum sizes
for different areas shall be decided as per CPWD General Specifications for Electrical Works Part-I
(Internal)-2013. If as per the design, the quantity of ceiling fans comes out that does not make the
symmetry, then higher number of ceiling fans shall be taken to maintain the symmetry.
Wherever light fittings are proposed to be provided on the false ceiling, the respective light / fan point
wiring will have to be brought up to the terminal of the light fittings / fans by the contractor. Flexible
metallic conduits shall be used for drawing wires from ceiling junction box to the fittings duly coupled at
both ends.
All lighting fixtures shall be LED type with colour temperature of 3000/4000/4500/6000K as per site
requirement and as approved by the Engineer-In-Charge.
All switches, sockets, AC point with MCB connected Socket outlets, phone socket, Data sockets, stepped
type electronic fan regulators, bell push and accessories along with matching mounting G I boxes shall be
of modular type and shall be of the same make as that of the plate type switches and accessories.
Wiring for circuit wiring along with earth wire with the following sizes of FRLS PVC insulated copper
conductor, single core cable in surface/ recessed MS Conduit as required.
Light Circuit-3 X 1.5 sq mm.
Power Circuit for 5/15 Amp Power sockets-3 X 4sq mm.
Power Circuit for AC/Geyser Outlets-3 X 6 sq mm.
Capacity of Circuits:
Lighting circuit shall feed light/fan/ call bell points. Each circuit shall not have more than 800 Watt
connected load or more than 10 points whichever is less. However, in case of LED points where load per
point may be less, number of points may be suitably increased.
Power circuit in non-residential building will have only outlet per circuit.
Load more than 1 KW shall be controlled by suitably rated MCB and cable size shall be decided as per
calculate.
Switches & Socket Outlets
All switches, sockets, AC Starter, Telephone socket, stepped type electronic fan regulators, bell push and
accessories along with matching mounting boxes shall be of modular type.
Socket outlets modular type shall be 6A 3 pin, 16 Amp 3 pin or 16/6 Amp 6 pin. 5 pin socket outlets will
not be permitted. The third pin shall be connected to earth through protective (loop earthling) conductor. 2
pin or 5 pin sockets shall not be permitted to be used.
Sockets for the power outlets of Geyser and AC points shall be of 25Amp 3pin/6pin modular type socket
outlet with 2 modular GI box with associated plug top Near the Geyser/ AC unit location and controlling
modular type MCB/motor starter with GI box at prominent location as decided by Engineer-in-charge.
5A/6A and 15A/16A socket outlets shall be installed at the following positions, unless otherwise required
at site as per approval of Engineer in charge.
Non Residential buildings – 60 cm above floor level.
Pantry – 23 cm above working platform and away from the likely positions of stove and sink.
Bathroom–socket outlet shall be provided above 2m for fixed appliances, and at least 1 m away from
shower and MCB control at outside of Bath room.
TV Power outlets in residences – socket outlet shall be provided above 90 cm floor level and switch control
is adjacent to Power socket or any other level in special cases as desired by the Engineer-in-charge.
Unless and otherwise specified, the control switches for the 6A and 16A socket outlets shall be kept along
with the socket outlets.
Ceiling fan regulators shall be of modular type two module stepped type electronic regulators only.
Where the A.C point locations are marked in approved layout, necessary openings in wall shall be provided
by with use of 75 mm PVC pipe sleeves at suitable locations for taking refrigerant pipes and cable to
outdoor unit, so as to avoid unnecessary cutting/damage to walls at a later stage. The slope of sleeve of
PVC pipe should be towards exterior to avoid seepage of water into the room. This opening should be
sealed properly after installation to avoid entry of vermin and rain water. For condensate drain, 25/32/40
mm PVC/ HDPE pipe be also provided and taken to nearest drain or up to the stack for collection &
disposal of condensate. The slope of such pipe also should be downwards. As far as possible, joints should
be avoided in this pipe.
Rising mains: Upward transmission of power inside the buildings shall be done with the sandwich compact
type rising mains with busbar i/c all accessories i.e. adapter box, cable end box, tap-off box with MCCB,
Rising mains shall be provided separately for light, power, UPS. Rating of rising mains shall be decided as
per maximum connected load of the building and future expansion of 10% of connected load as approved
by engineer-in-charge. Rising mains shall be conforming to IEC 61439 as amendment up to date. Design of
rising main shall be as per ECBC 2017.
From rising main, suitable capacity tap off box shall be provided to connect the vertical TPDB with
incomer of suitable size 4 P MCCB through XLPE cable. Separate tap off box for light and power shall be
provided from vertical TPDB, the supply shall be connected to different Horizontal TPDBs at different
locations for further distribution to the circuits through MCBs with suitable size copper conductor cables in
MS conduit. RCCB of 100mA sensitivity shall be used in the incomer for all DBs (other than vertical
TPDBs). MCB of required rating (matching with the load current) shall be provided for protection of each
circuit).
UPS, Power and Light DB shall be separate. The size of DBs at one location shall be same irrespective of
number of circuits connected from the DBs. The make of MCDBs, MCB, RCCB shall be same everywhere.
Size of Distribution board shall be per number of light/power circuits. All circuits shall be terminated on
individual MCB. All distribution boards shall be double door type. RCCB of 1f00 ma sensitivity with MCB
of suitable rating shall be provided as main incomer in all DBs.
The rupturing capacity of the MCB’s shall be 10 KA.
In vertical DBs used for power distribution, main incomer shall be MCCB of following type:
Upto 160A MCCBs shall be of >20 KA (Ics=Icu) at 433 V short circuit current rating and should be of
thermal magnetic type.
From 200A-250A MCCBs shall be of >35 KA (Ics=Icu) at 433 V short circuit current rating and should be
of thermal magnetic type.
From 250A MCCBs shall be of >50 KA (Ics=Icu) at 433 V short circuit current rating and should be
microprocessor based having over load and short circuit protection.
MCCBs, if used as incomer then it should have earth fault protection and time delay. Earth leakage
modules are not acceptable.
All lights of staircase, parking area, street and compound shall be controlled by astronomical time switch.
There shall be arrangement of bypass switch so that in case of failure of time switch, the lights can be
operated after by passing the same.
All Substation/ HT/ LT panel rooms shall be provided with safety equipment/ items like suitable
elastomeric mat (as per relevant IS code), danger plates (HT/LT rating), safety charts, framed schematic/
SLD.
Suitable civil foundation/ trenches etc. for all substation/ switch room/ panel shall be provided.
To prevent storm water entering the switch room, the floor level of the substation/ switch room shall be at
least 300 mm above the highest flood water level may be anticipated in the locality or as directed by the
Engineer-in-Charge.
All the UPS points should be with black colored cover plate for proper identification.
The wiring and conduit route plan/drawings shall be submitted by the contractor and shall be got approved
from the Engineer-in-Charge.
To facilitate drawing of wires, 18 SWG GI fish wire shall be drawn in the entire recessed conduit.
Cable tray shall be horizontal/vertical type and made of perforated hot dipped Galvanized Iron of suitable
sizes (galvanization thickness i.e. average mass of Zinc coating shall not be less than 65 microns for 2 mm
thick & 50 microns for 1.6 mm thick as per IS standard) with perforation not more than 17.5%, in
convenient sections, joined with connectors, suspended from the ceiling with G.I. suspenders including G.I.
bolts & nuts, etc. as required. Suitable size as per site conditions shall be used with thickness 1.6 mm for
cable trays with ≤ 300 mm & thickness 2 mm for cable trays with width > 300 mm.
Inside the lift shaft there shall be arrangement of one light point at each floor level and one light point at
over-head, one light point in lift pit. All light points shall be group controlled and wired with 2.5 sq mm
FRLS copper conductor cable. 5/15 Amp 6 pin power plug with 16 Amp switch shall also be provided at
each floor. Wiring of these power plugs shall be done with 4 sq mm FRLS copper wires. LED Bulk head
fittings of suitable rating shall be provided with each light point of lift shaft. However the electrical points
etc. as per the requirement of lift OEM shall be fulfilled by the agency.
Lighting protection system shall confirm to IEC-62305. Lightning conductor conforming to Lightning
protective level (LPL I) shall be designed for the building.
Aviation obstruction lights (LED Type), if required by local bye laws, shall be provided as per local
aviation authority.
Earthing: Earthing system comprising of earth electrode, earth conductor, earth bus, protective conductor
etc. for buildings shall be carried out as per provision laid down in CPWD General Specification. Earthing
system should be designed such as to maintain earth resistance as specified in above specifications. Earth
resistance shall be checked / tested n harsh climatic conditions.
Minimum number of earthing electrodes : However there may required more earthing electrodes as per
design and requirement & the same are also included in the scope of work
LT panel – 4 sets
Lightening conductor – One number for each down conductor.
FF pumps & domestic pumps – 2 sets.
Metallic body of all the equipment shall be earthed confirming CPWD specifications for Electrical works
(Part-I), Internal 2013 corrected up to the last date of the tender.
Armoring of cables shall be connected to equipment and panel at both the ends.
All the light and fan points should be properly earthed with 1.5 sq mm FRLS PVC insulated copper wire.
After completing the work, necessary test results as envisaged in CPWD General Specifications Part-I
(Internal)-2013 corrected up to the last date of the tender, CPWD General Specifications Part-II (External)-
1994 corrected up to the last date of the tender & Indian Electricity Rules 2005, shall be recorded and
submitted to the department. The results shall be within the permissible limits.
Details of the light fittings and ceiling fan to be installed in different areas:
5 1200/1400 mm sweep BLDC ceiling fan providing Ceiling fans shall be provided in
minimum air delivery of 270 cu mtr/minute with power all areas except staircase/
consumption not more than 42 watts at the speed of 270 toilets/bath rooms/
RPM, service value greater than 7, complete in all respect terrace/corridors and open areas
powder coated aluminium die cast body & blades
(minimum 1 mm thick aluminium leaf), power factor not
less than 0.90 including providing 6 key remote along with
necessary down rod of standard length (up to 30cms)
6 Surface mounting IP-65, 9 Watt LED bulk head light Terrace, lift shafts, outside
fitting with polycarbonate diffuser, single phase, 100- pump house, outside plant room,
270V, AC, efficacy >100 Lumens/watt complete with outside substation & other like
integral electronic driver i/c connection etc. as required. places
7 36W LED post top light fitting having color temperature Compound wall gate lighting
not less than 4000K, system lumen output not less than
2880 lumens and system wattage 36 watts, built in
electronic driver with surge protection not less than 4 KV
etc. shall be installed on compound wall gates to the
entrance of each building.
Street/External Lighting
Lighting design should be carried out as per National lighting Code 2010/NBC-2016/ ECBC guidelines.
Wherever range of illumination for space is mentioned, higher side of Lux level must be taken for design
purpose. If as per the design, the quantity of light fixtures comes out that does not make the symmetry, then
higher number of light fixtures shall be taken to maintain the symmetry.
The street light Poles along the Road shall be Octagonal poles/ Designer PU coated metal poles with all
accessories as per design and approval of Engineer in charge. The light fittings for land scaping shall be
Bollards, bush lighting , ornamental fittings as per design and approval of Engineer in charge.
Each Pole shall be provided with minimum 30 W hybrid LED type Solar street light fitting with 10Hrs
battery backup of made out of die cast aluminium housing and toughened glass cover with min IP66
degree of protection, Individual LED with optical lens for better light distribution throw across and along
the road, with luminaire efficacy of greater than 120 Lumen / watt, colour rendering Index (CRI) of ≥70
and co-related colour temperature of 5700K (± 300K), The luminaire should have 5 KV surge protection,
PF ≥ 0.95, and total harmonic distortion of THD ≤ 10% impact resistant near ≥ IK05 standard, voltage
range of 140 - 280 V should be provided, well designed thermal management system with aluminium heat
sink. The Driver used be a constant current driver with efficacy of ≥ 85%. The Manufacturers LOGO must
be embossed in to the housing of luminaire. Including connection from loop box to fitting with 3 x1.5 Sq
mm FRLS copper conductor wire& loop earthing, testing and commissioning etc. as required.
The cabling of the external lighting/street lighting should be in such a way that every third
subsequent/alternate pole shall be connected from each R-Y-B phase of 3 way supply line for ensuring
minimum light at the time of failure of either of the phase.
Suitable capacity PVC sheathed, XLPE aluminium conductor armoured cable shall be laid in the required
capacity of DWC pipe @ 0.75 mtr depth from the ground. The earthing shall be provided as per CPWD
specification Internal 2013.
LT cables shall be terminated at each pole by using brass compression gland and Aluminium lugs of
suitable size as per specifications.
The street Light control panels shall be placed at the location decided by the Engineer-in-charge.
Required capacity of the switchgears in the street light control panels shall be provided. The decision of the
engineer-in-charge with regard to the switchgears shall be final and binding on the contractor. The Panels
shall have rain protection hood and hinged outer door with locking arrangement and installed on RCC base
/ foundation of height not less than 45 cm from ground level.
The external/compound lighting/Landscaping has been designed to cover the external development area of
the campus/premises of the building.
UPS
It is proposed to install 1 X 10KVA modular UPS in parallel redundant mode with 30 min. battery back-up
for following load:
Power backed up UPS with minimum 30 minutes Backup with the help of maintenance free batteries
should be installed to provide continuous, uninterrupted power to life safety circuits comprising of:
All Computer points in all areas.
Part lighting load (At least 70% fittings subject to minimum one fitting) in all areas of the building.
All the UPS shall be provided with auto phase sequence correction facility so that in the event of change of
phase sequence at the input supply, the working of UPS is not disrupted.
The complete system with all switches, cabling, safety devices, batteries, earthing including the UPS
system of capacity so calculated shall be in the scope of work.
Maintenance free lead acid batteries shall be provided on a suitable size of rack.
Works to be done by the contractor: - In addition to supply, installation, testing and commissioning of all
the equipment, as per schedule of work, and CPWD specifications, the following works shall be deemed to
be included within the scope of work to be executed by the contractor.
Correction = NIL, Insertion = NIL, Overwriting = NIL, Deletion = NIL
Any minor building work for the installation such as cutting and making good the damages.
Protection required for the equipment from rain, dust storm etc. during transportation.
Necessary equipment for commissioning the system at site and testing etc.
Inspection: - UPS and battery bank shall be offered for initial inspection & testing in the work of the
manufacturer before delivery. Contractor will give sufficient notice for the same. The department reserves
the right to inspect or not to inspect the equipment in the work of the manufacturer. In the later case
confirmation in writing will be issued by the department. The department will bear the to & fro expenses of
the officer deputed for carrying out inspection. However, nothing extra shall be paid for conducting
routine test in the presence of department’s representative. After installation, the equipment shall be tested
by the contractor, for which all consumables shall be provided by him. The inspection at site includes
operation checks and any other test as necessary to check the performance of the equipment, so as to check
conformity to tender specifications.
Warranty: - All equipment supplied and installed shall be covered by warranty for a period as per relevant
clause of GCC – 2023 against defective workmanship and material. If any equipment is found to be
defective due to faulty materials, faulty design, or inferior quality of materials it shall be repaired or
replaced at site free of charge by the successful tenderer at his own cost during the warranty period. The
warranty shall cover consequential damages to the equipment supplied and installed by the tenderer due to
poor workmanship or defective materials. All repairs shall be done promptly within a reasonable period.
The warranty period will commence from the date of handing over of the installations to the department
duly commissioned.
Painting: - The tendered cost shall include cost of painting of entire installation complete in all respect.
Extent of work: - The work shall comprise of entire labour including supervision and all materials
necessary to make a complete installation and such tests and adjustments and commissioning as may be
required by the department. The scope of works include on job technical training of two persons at site
nothing extra shall be payable on this account.
The SPV power plant shall have a total capacity of 20 Kwp. The power plant shall provide a reliable and
independent power supply to the LT Panel at 415 V. the Solar Power plant is suitable for ongrid. The
proper design of the system is to be approved by Engineer-in-charge and carry out the work as per CPWD
specification with upto date correction slip.
The minimum array capacity Solar PV power plant should be 20 KWp. Solar Photovoltaic Module of
capacity 545 Wp or above, manufactured in India, conforming to IS 14286/IEC 61215, IS/IEC 61730-Part-
1, IS/IEC 61730-Part-2.
PV modules used in solar power plants/ systems must be warranted for their output peak watt capacity,
which should not be less than 90% at the end of 10 years and 80% at the end of 25 years.
Since the modules would be used in a high voltage circuit, the high voltage insulation test shall be carried
out on each module and a test certificate to that effect provided.
Manufacturers / Contractors should confirm whether they are supplying PV module using a RF
identification tag (RFID), which must contain the following information. The RFID can be inside or outside
the module laminate, but must be able to withstand harsh environmental conditions.
Name of the manufacturer of PV Module
Name of the Manufacturer of Solar cells
Month and year of the manufacture (separately for solar cells and module)
Country of origin (separately for solar cells and module)
I-V curve for the module
Peak Wattage, Im, Vm and FF for the module Unique Serial No and Model No of the module
Date and year of obtaining IEC PV module qualification certificate
Name of the test lab issuing IEC certificate
Other relevant information on traceability of solar cells and module as per ISO 9000 series.
Other general requirement for the PV modules and subsystems shall be the following
Module shall be made up of mono or poly crystalline silicon cells.
The module frame is made of corrosion resistant materials, preferably having aluminium anodized finish.
The module shall be provided with a junction box with either provision of external screw terminal
connection or sealed type and with arrangement for provision of by-pass diode. The box shall have hinged,
weather proof lid with captive screws and cable gland entry points or may be of sealed type and IP65 rated.
Scope of work:- Designing, Supplying, Installation, Testing & Commissioning of 1000 LPD Solar Water
Heater System i/c all accessories, control etc. as required as per the satisfaction of Engineer-in-Charge.
Solar water heating system comprising of solar flat plate collector, collectors stand assembly, stainless steel
insulated hot water storage tank having epoxy coating on inner side with heat exchanger and various other
components. Solar flat plate collector component shall have:
Solar flat plate collector cover plate made of toughened glass.
Sheet for absorber made of copper/Aluminium.
Absorber made of copper/Aluminium sheet with copper tube.
Solar flat plate collector specifications: Solar flat plate collector shall be BIS marked and as per to IS:12933
(part 1) with amdt. no. 1 & 2 and IS: 12933 (part 2) /2003 and various components shall be as under:-
Cover plate:- Cover plate shall be toughened glass and thickness of 3.2mm (min.) conforming to section-1
of IS: 12933 (pt-2) /2003 The solar transmittance of cover plate shall be minimum 82 percent at near
normal incidence.
Collector Box:- Collector box shall be made of Aluminium sections only with minimum thickness 1.6mm.
Type, grade, size, workmanship and finish of the material used shall be as per section-2 of IS:12933 (pt-
2)/2003 . The minimum thickness of aluminium shall be as under:
Channel section for sides 1.4mm
Sheet for bottom 0.45mm
Correction = NIL, Insertion = NIL, Overwriting = NIL, Deletion = NIL
Heat exchanger shall be cage type and made of copper/stainless steel tubes of grade x04Cr19Ni9 Or
x07Cr18Ni9 of IS :1570 (part 5)/1985 (Reaffirmed 2004). Heat exchangers shall have a minimum of 0.24
sq. meters heat transfer area per 100 LPD capacity.
Collector stand assembly shall be made of MS angle of size 38x38x4 mm duly pretreated and stove
enameled with black colour paint. Alternatively tubular structure with powder coating/Zink plated collector
stand could also be provided.
Temperature Gauge: Dial type, duly calibrated and suitable for temperature range from 0 degree C to 120
degree C.
Other component essential for completeness of the system as per tenders specification.
The firm shall get general arrangement drawings approved from the Engineer-in-charge before supply of
the system. General arrangement drawing shall clearly show all the parts of the system (such as solar flat
plate collectors, collectors stand assembly, insulated hot water storage tank complete with heat exchanger,
Correction = NIL, Insertion = NIL, Overwriting = NIL, Deletion = NIL
sacrificial anode, electrical back up, internal and external piping, tank stand assembly, various valves,
pressure gauges, temperature gauges, water meter etc) and their fixing arrangements.
The firm shall supply two sets of instructions manual to the department without any extra cost. Instruction
manual shall containing the following details:
Schematic diagram of the solar collector and domestic hot water system.
Instructions for installation (including mounting details) and use and safety precautions.
Instructions for repair and maintenance including causes for common failures, such as, dust ingress on glass
cover, peeling of paint, scaling, damaged sealant, gasket and grommets and their remedies.
List of service outlets.
The firms shall furnish complete and satisfactory type test reports for each size/type of solar flat plate
collector as per contract specification from any MNRE approved govt. laboratory. Type test reports shall be
complete with authenticated drawing giving complete details of the various. Component used in the solar
flat plate collector. Type test reports shall include all the tests listed in IS: 12933 (part 1) with amdt. No. 1
(excluding test requirement as per cl.
7.2.7 and 7.2.8 of IS) and IS:12933 (part 2)/2003 collector as per IS: 12933 (pt 2)/2003.
Acceptance testing leakage test at 5kg/cm2 on riser and header assembly, test on piece of absorber of size
400cm2 at 175 deg Celsius for 2 hours and verification of components as per specification shall be done as
part of acceptance tests.
Calculation to co-relate performance of type tested collector with rated capacity of solar water heating
system shall be furnished at the time of supply.
The entire item shall be as per MNRE norms.
For solar water heating system for cold region the contractor shall provide required quantity of Ethyl
Glycol along with the system at no extra cost to the department as per requirement.
Acceptable makes
12. Occupancy & Daylight Sensor Philips / Wipro / ABB / HoneyWell / Legrand
SPC Electrotech Pvt Ltd/Krypton/ Precision
13. Electrical Control Panels System Control/ Tricolite/ Adlec/ Neptune/
Pristine
SPC Electrotech Pvt Ltd/Krypton/ Precision
14. Feeder Pillars System Control/ Tricolite/ Adlec/ Neptune/
Pristine/Application Control Panels/ RP Control
L&T (U-Power)/ Siemens (3WA)/ Schneider
15. ACBs (Master Pact – MVS) / ABB(E-Max)/Equivalent
model of Legrand/Havells
Siemens (3VL)/ Schneider (Master Pact – NSX) /
16. MCCBs Equivalent Moddel in ABB/ L & T/ Equivalent
model of Legrand/Havells
17. Data Rack & Accessories Schneider /Rittal/ Valrack / D-Link
18. Current Transformers Automatic Electric/ Kappa/ L&T
19. Potential Transformer Automatic Electric/ Kappa/ L&T
25. Cable Trays & Accessories Legrand / Venus/ Slotco/ Pilco/ Reeco/Rmcon
26. Capacitor (IS Marked) Neptune/ Siemens/ L&T /Schneider
27. Cable Gland/ Lugs/ Thimbles Commet/ Dowells/ Raychem / Gripwell Jainson
Emergency/Exit Lighting System and
28. Hochiki/Teknoware/ Tm / Asm / Cooper
Components, Fixtures
29. All in one fixture
2. UPS
S. No. Material / Item Approved Make
Modular UPS Emerson / APC / Mitsubishi/ ABB/Vertiv/ Fuji
1
Electric
2 Electrical Panel/All other Accessories As per IEI work
3 Maintenance free batteries Exide/ Prestolite/Amaraja/ Luminous/AMCO/Hbl
3. Solar PV System
S. No. Material / Item Make
Vikram Solar/Tata Solar/Adani/Luminous/Jackson/
1. Solar PV module
Inter Solar System
Delta/SMA/ABB/TMEIC/Sungrow/Huawei/
2. Grid Tied Solar Inverter
Hitachi/ Schneider/Luminous/Microtek
3. Solar PV Controller As per OEM standards
LT Cable/DC Cable/FRLSH PVC
4. As per IEI Work
Insulated Wire (IS Marked)
Electrical Panel/MCCB/MCB
5. /ACB /ELCB/Isolator/All other As per IEI work
Accessories
6. Maintenance free batteries Exide/ Prestolite/Amaraja/ Luminous/AMCO/Hbl
Note:
The material shall be procured as per preferred make list given above Make in India Policy and
Government of India, Ministry of Commerce and Industry order No. P-45021/2/2017-PP (BE-
11) dated 04.06.2020 and order of Govt. of India, Ministry of Finance, Department of
1. Expenditure (PPD) F.No.6/18/2019-PPD dated 23.07.2020 and as per Government of India,
Ministry of Commerce and Industry order No. P-45021/2/2017-PP (BE-11) dated 16.09.2020
and any other guidelines issued in this regard. In this regard, certificate to be furnished by
Agency and their specialized agency under Rule 144(XI) in the general Financial Rule 2017.
The contractor will use one of the approved makes as approved by the Engineer-in-Charge
2.
subject to verification of TDS.
In case of different quality/pattern of same make, the pattern/quality shall be approved by
3.
Engineer–in –charge.
For materials/equipment to be used in items of work for which approved makes are not given
4. herein, the make of such materials/equipment having equivalent specifications shall be as
decided by Engineer –in-charge.
Schedule of Quantity
Name of Work: Construction of GYM (Fitness Centre) at NDS Stadium Leh, UT of Ladakh. ( Balanced
work related to E&M)