MEC310 - Lecture 09 - 251
MEC310 - Lecture 09 - 251
DEPARTMENT
3rd Year
Lecture #09
Project control and
Monitoring (Cont.)
BAC
status
information
Solution:
EV=%Complete
x Budget
AC= given
PV= planned
Value at
period
CV=EV-AC
SV=EV-PV
Solution:
SPI=EV/PV
CPI=EV/AC
PCIB=EV/BAC
Solution:
Forecast Costs at Completion
This means that for every one dollar spent, we have done 95 cent worth of the work, or for
every one dollar spent, we received $0.95 worth of cost performance. A value > 1 indicates
that the work is being completed better than planned, whereas a value <1 indicates that
work is costing more than planned.
Schedule performance index:
A SPI value less than 1.0 indicates behind schedule. The schedule index indicates $.90 worth
of work has been accomplished for each $1.00 worth of scheduled work to date
v) Additional cost for completing the project
Estimate of cost for remaining work:
(3,000 - 1,800) * 1200 $/computer = $1,440,000
END
Lecture
You can win, if you want