Problem No
Problem No
1
Local barangay – health center
1200 sqm
4% towards road
Zoning category – 6 I GENERAL INSTITUTIONAL
Using table 7.1 chapter VII of NBCP, under what classification is the project
categorized? D-2
SOLAR RADIATION is the major consideration when locating a waste and disposal
facility of Site environmental factor for medical grade refuse.
DIFFUSED maximize the lighting needs of the project.
GENERAL TRIAS CAVITE has the best air quality during habagat season.
IMPERVIOUS SURFACE AREA (ISA) the percentage of the maximum allowable
floor area of any paved, tiled or hardscaped surface at the ground floor/grade level
(located outside the main building/structure) in relation to the Total Lot Area (TLA).
Cockfighting arena is under division H2
3.6m x 18.0m minimum parking slot for an articulated truck as per NBCP (12-
16wheeler)
Entrance or exit steps shall have treads of not less than 300 mm. Minimum number
of steps shall be 2 risers not exceeding 100mm.
50% Maximum PSO of the project
50% Maximum allowable building footprint expressed in sq m if setbacks are
followed.
33 How many pieces of gypsum board will be consumed if it is to be used as a
ceiling finish for the eaves with an area of 93sqm?
Eaves (side or rear)
2m -0.75 = 1.25
Front
5m -0.75 = 1.67
Reception directly accessible from the congregation/ waiting area.
Southern corner utilities like Pump rooms, STP, MRF be located.
2.40 Difference in the slope of the site grade.
Ground floor Measurement of the percentage of site occupancy is taken at what
level?
North Side of the structure exposed to the Sun for approx. 4 months. Jan to april
South Side of the structure exposed to the Sun for approx. 8 months. May to
December
1 slot is required for hotels of any size Under PD 1096, Standard truck parking
space for hotels.
Storage and hazardous Group G Occupancy ¸Under PD 1096.
15% Percentage of open space for business and mercantile occupancies
constructed on an inside lot.
Residential In the high-rise residential condominium with basement, commercial
podium, and tower components projects, which NBCP standard should the mixed-
use development follow?
Assume that the development is maximized and firewalls were provided, what is the
TGFA of the project based on table VII.1?