Letter No: REPL/SPV/Aarvee/11.2/2084 To Team Leader Independent Engineer, Aarvee Associates Architects Engineers & Consultants Pvt. Ltd. Plot No.225, Lalitha Nagar, NGOs Colony, Nandyal 518 502, Dear Sir, Sub: Design Engineering, Financing, Procurement, Construction, Operation and Maintenance of for four laning of Cuddapah Kurnool section of NH-18 from the existing Km 167.750 to Km 356.502 in the state of Andhra Pradesh under NHDP Phase-III BOT Basis Change of Scope Reg. Dated: 23.02.2012
Ref: 1. Concession Agreement for above mentioned Project was signed on 11 February 2010 between NHAI and REPL. The appointed Date of the Project had been declared by NHAI as 15 November 2010. 2. In accordance with the Concession Agreement, the scope of the Project during construction period include construction of the Project Highway on the site set forth in Schedule-A and as specified in Schedule-B together with provision of Project facilities as specified in Schedule-C, and in conformity with the specifications and standards set forth in schedule-D. 3. In Schedule-B of the Concession Agreement, the features of 4-laning are included. These features include different types of cross sections required to be developed in different segments of the Project Highway. This Schedule also specifies that the alignment plan and vertical profile of the Project Highway are to be designed as per provisions of manual of specification and standards for 4-laning of National Highways through PPP published by Ministry of Road Transport and Highways. Among others, this Schedule comprises details of various structures to be constructed as part of Project Highway. 4. Schedule-C of the Concession Agreement includes details of Project Facilities to be constructed. 5. Schedule-D of the Concession Agreement deals with specification and standards for 4-laning. 6. In compliance with the obligation set forth in Clause-12.3 of the Concession Agreement, the Concessionaire has been furnishing drawings for review to the Independent Engineer and proceeding with construction thereafter. 7. Additional works and services, which are not included in the Scope of the Project as contemplated by the Concession Agreement, are to be dealt in accordance with Atricle-16 of the Concession Agreement. 8. Details of additional works not covered under Scope of the Project defined vide Para-2 above are brought out as below.
9. Details of additional cost on account of Change of Scope of ROBs will be submitted after approval of the detailed design and drawings by Railway Authorities. 10. Aforementioned proposals along with the proposals have already been submitted (shown below) under Change of Scope which are summarized at Annexure 1.