Automatic Generation Control
Automatic Generation Control
Number of phases 3
Efficiency 98.38%
Number of phase 3
Type HLA743-LJ-280
Minimum head 80 m
Elevation of turbine 74 m
Type DJT-80WZ
Diameter of main distributing value 80 mm
Rated oil pressure 4 MPa
Power supplies DC 220V±15% AC 220V±15%
Set values of no-load condition P=3, I=0.05, D=3.5, E=0, K=30
Set values of parallel condition P=3, I=0.05, E=0.4, K=30, bp=6%
Start opening 20 %
No-load opening 20 %
Limited opening 92 %
Proportional coefficient, KP 3
Integral coefficient, KI 0.06
Differential coefficient, KD 3.5
Artificial frequency Dead band, E 0.4
42
(a)
(b)
Figure 4.2 (a) Block Diagram of Two-Area Interconnected Power System with
Primary LFC Loop
(b) Block Diagram of Two-Area Interconnected Power System
Equipped with Integral Controller in Each Area
4.5. Parameter for AGC Model
44
A two area system connected by a tie line has the following parameters on a
100 MVA common base.
Area 1 2
Speed regulation R2= 7%
R1= 6 %
Frequency-sensitive D1= 0.6 D2=0.9
load coefficient
Base power 100 MVA 100 MVA
Governor time constant τ g 1 = 0.2 sec τ g 2 =0.3 sec
Turbine time constant τ T 1 =0.5 sec τ T 2 =0.6 sec
Nominal frequency = 50 Hz
The synchronizing power coefficient , Ps = 2.0 per unit
Load change occurred in area 1 = 187.5 MW
New steady state frequency =?
187 . 5
= 100
= 1.875 pu
Steady-state frequency deviation,
45
−ΔP L
Δω ss = ( D1 +
1
R1)(
+ D2 +
1
R2 )
−1. 875
=
(
0 . 6+
1
0 . 07 )(
+ 0 . 9+
1
0 . 08 )
=−0.0663 pu
Steady-state frequency,
Δω ss ¿ f0
= −0 . 0663×50
=−3 .315 Hz
New frequency, f = f0+ Δf
= 50−3 .315
= 46.685 Hz
Change in mechanical power,
−Δωss
ΔP m 1 = R1
−(−0 . 0663 )
= 0 .07
= 0.9471pu¿ 100
= 94.71 MW
−Δωss
ΔP m 2 = R2
−(−0 . 0663 )
= 0 .08
= 0.8288 pu¿ 100
= 82.88 MW
Area 1 increase generation = 94.71 MW
Area 2 increase generation = 82.88 MW
New frequency = 46.685 Hz
Total change in generation = 94.71+82.88
= 177.59 MW
46
ΔP 12=Δω
( 1
R2
+ D2
)
=−0. 0663 ( 1
0 . 08 )
+0 . 9
=−0.8884 pu
=−0. 8884×100
=−88. 84 MW
88.84 MW flow from area-2 to area-1.
82.88 MW come from the increased generation in area-2.
5.96 MW come from the reduction in area-2, load due to frequency drop.
Figure 4.3 Simulink model of AGC with two area power system
(a)
(b)
Figure 4.4 (a) Frequency Deviation Step Response
(b) Power Deviation Step Response
48
=−98 .69 MW
= ΔP + BΔω
ACE
1
+0 . 6
=
0 .07
= 14.89
1
+0 . 9
=
0 .08
49
= 13.4
ΔP 12+ B1 Δω
1 =
ACE
(−0 . 0663 )
=−0 . 8884 +14.89¿
=
−1 .875
ΔP 21+ B 2 Δω
2 =
ACE
(a)
(b)
Figure 4.6 (a) Frequency Deviation Step Response with Integral Controller
The AGC was simulated without controller and with integral controller.
Figures show the Simulink results of the two area power system. From these results,
AGC with Integral controller shows that the reliability of generating system is
determined by its ability for maintaining voltage and frequency within permissible
limit. It can be concluded that the generating system for AGC with Integral controller
shows satisfactory performance.