Tutorial 8
Tutorial 8
1. A manager is developing a program in sustainability certification for engineers. The manager has
listed a number of activities that must be completed before a training program of this nature could be
conducted. The activities, immediate predecessors, and times appear in the accompanying table:
I b.
c.
d.
What is the critical path? en uzun
What is the total project completion time?
got
What is the slack time for each individual activity?
a
5 d
shoe
13
A
10 O
B
11
6
g 0
e
3
1 IT
6 0
8
b 5 10 3 8 AEG 13days
26
BDEG 26dg
8 cb 6
D E
CFG 18days
C B DG
2. The estimated times and immediate predecessors for the activities in a project at a retinal scanning
company are given in the following table. Assume that the activity times are independent.
E
atymt
rience
b TEA c
20
18 is
fer
TEB C
thecritical
d X 22 varience
µ TEA 20
c
A Fins d. What is the maximum time that can be crashed? How much would costs increase?
B To's
208 2915813388 900
C Eitical A 6
79119T A
α 29931 600
D 20 a.EEgtqest
72301 75
6 20
1400 300
axtim
EEEm.IT
3 16 7 9
crash
II
ᵗÉÉotease