Area Programme

The document outlines the spatial requirements and specifications for various zones within a facility, including the Origin Zone, Create Zone, Transform Zone, and Share Zone. Each zone details the area, user group, occupancy, and technical requirements for different spaces such as offices, labs, and communal areas. The total area calculated for the facility is approximately 29,006.6 square meters, accounting for circulation and miscellaneous spaces.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

Area Programme

The document outlines the spatial requirements and specifications for various zones within a facility, including the Origin Zone, Create Zone, Transform Zone, and Share Zone. Each zone details the area, user group, occupancy, and technical requirements for different spaces such as offices, labs, and communal areas. The total area calculated for the facility is approximately 29,006.6 square meters, accounting for circulation and miscellaneous spaces.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Occupancy Standard Carpet Area Light

S.No. Area Focus Industry User Group Occupants Nos Total Area Remarks Nature Of Space Technical Requiremnets Column 1
sq.m / person sqm/unit (sq.m) Requirement
ORIGIN ZONE

A ENTRANCE

1 Entry Foyer - - 100 1 100

2 Reception Desk - - 20 1 20

3 AirLock - - 20 1 20

4 Security Room + Fire Control Room - - 25 1 25

5 Building Management System Room - - 10 1 10

6 Lounge/Waiting 90 1 90

7 Back Office - - 15 1 15

8 Toilets (male) - 2WC / 3WB / 2UR - 15 1 15

9 Toilets (female) - 3WC / 3WB - - 12 1 12

10 Toilet (Handicap) 1WB/1WC - - 2.5 1 2.5

11 Toilets (staff) - 2 WC+WB - - 4 1 4

12 Communal Changing Room + Shower (M) - - 20 1 20

13 Communal Changing Room + Shower (F) - - 20 1 20

Total Area 353.5

B ADMINISTRATION 10 1 150 150

2 Archive Room - - - 20 1 20 Private

3 Manager's Office 1 - 20 20 1 30 Private

4 Manager's Meeting Space 5 - 2.5 15 1 15 Private

5 Accounts Division 6 - 10 60 1 60 Private

6 Head's Room 1 - 18 18 3 54 Private

7 Mentor's Room 1 - 15 15 15 225 Private

8 Faculty Room 1 - 10 12 10 120 Private

9 Associates Room 1 - 8 10 10 100 Private

10 General Technician's Room 1 - 12 10 1 10 Private

11 Concierge Office - - - 25 1 25 Private

12 Storage Room - - - 15 2 30 Private

13 Toilets (male) - 2WC / 4WB / 3UR - - - 20 1 20

Total Area 709

C RESIDENCE -CO-LIVING SPACE

1 Studio unit - Incubatee 30 10 300 Private

2 Two Room Shared Unit - Incubatee 50 10 500 Private

3 Four Room Shared Unit - Incubatee 100 5 500 Private

4 Shared Kitchen - Incubatee/Staff 108 1 108 Private

5 Laundromat - Incubatee/Staff 72 2 144 Private

6 Working Space/Collaboration Space - Incubatee/Staff 108 2 216 Private

7 Storage - Incubatee 12 3 36 Private

8 Administration
Occupancy Standard Carpet Area Light
S.No. Area Focus Industry User Group Occupants Nos Total Area Remarks Nature Of Space Technical Requiremnets Column 1
sq.m / person sqm/unit (sq.m) Requirement
Total Area 1804 Private

CREATE ZONE #REF!


Technical Textiles+
Garment+ Recycling And
Upcycling Lab+Digital
E DESIGNER SPACE Fashion
Studio 1
1 All
10 Entrepreneur/ Trainers 30 2 600 Semi-Public
Studio 2
2 All
10 Entrepreneur/ Trainers 30 2 600 Semi-Public
3 Cafe 1.8 All Entrepreneur/ Trainers 50 1 50 Semi-Public
Technical Textiles+
4 Garment+ Recycling And
Collaboration Rooms Upcycling Lab Entrepreneur/ Trainers Semi-Public
5 Photo Studios Digital Fashion Entrepreneur/ Trainers 32 1 32 Semi-Public
6 Lounge Entrepreneur/ Trainers Public
Total Area 1282
Technical Textiles+
F Garment+ Recycling And
PROTOTYPING LAB 10 Upcycling Lab 10 100 10 1000 Semi-Public

G
SECTOR SPECIFIC LABS

G.1 TECHNICAL TEXTILES


1 Material Testing Lab 10 Entrepreneur/ Trainers 5 50 1 50
2 Climate Simulation Lab 10 Entrepreneur/ Trainers 5 50 1 50
3 Medical Textile Lab 10 Entrepreneur/ Trainers 5 50 1 50

G.2 GARMENT INDUSTRY


1 Textile Engineering Lab 10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
Weaving Technology Lab
2
10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
Market Research Lab
3
10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
4 Knitting Technology Laboratory 10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
5 Sewing & CAD Laboratory 10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
6 Wet-Laid -Nonwoven Technology Lab 10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
7 Dry-Laid -Nonwoven Technology Lab 10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
8 Textile Printing Lab 10 Garment Industry Entrepreneur/ Trainers 5 50 1 50 500 Lux Semi-Public 20° -23° C
G.3 DIGITAL FASHION
Phygital MicroFactory 10 Entrepreneur/ Trainers 10 100 5 500 500-600 Lux Semi-Public
G.4 SYNTHETIC/ MMF 10 10 100 100 Semi-Public
G.5 RECYCLING + UPCYCLING Semi-Public
Waste to Resource Lab 10 Entrepreneur/ Trainers 10 100 2 200 Semi-Public
H Total Area 1350 Semi-Public
TRANSFORM ZONE
Technical Textiles+
Garment+ Recycling And
I MANUFACTURING FACILITY Upcycling Lab
SECTOR SPECIFIC MANUFACTURING FACILITY
I.1 TECHNICAL TEXTILES
18° -22° C
HEPA Filtration
MediTech Technical Class 100K Clean Room
Grade 1 Tex MicroFactory 10 Textiles 50 500 1 500 500-750 Lux Semi-Public RH : 45-55%
InduTech , SporTech, 20° -25° C
Grade 2 Tex MicroFactory 10 ProTech,GeoTech Textiles 50 500 2 1000 500-800 Lux Semi-Public RH : 55-65%
AgroTech ,PackTech 20° -24° C
Grade 3 Tex MicroFactory 10 Technical Textiles 50 500 2 1000 400-550 Lux Semi-Public RH : 60-70%
Occupancy Standard Carpet Area Light
S.No. Area Focus Industry User Group Occupants Nos Total Area Remarks Nature Of Space Technical Requiremnets Column 1
sq.m / person sqm/unit (sq.m) Requirement
I.2 GARMENTS
1 Production Hall 10 Garment Industry 100 1000 3 3000 Semi-Public
2 Production Hall Offices 6 Garment Industry 5 30 5 150 Semi-Public
3 Lockers 0.5 Garment Industry 100 50 5 250 Semi-Public
4 Washrooms Garment Industry 21 5 105 Semi-Public
5 Total Area Garment Industry 3505
I.5 RECYCLING + UPCYCLING
1 Recycling Facility 10 50 500 2 1000 Semi-Public
Recycling And Upcycling +
2 MATERIAL RECOVERY CENTER 4 Garment Industry 50 2 400 Semi-Public
Total Area 4505

J WORKSHOPS 4 Rec ycling + Upcycling 50 2 400 Semi-Public


7405
SHARE ZONE
K Seminar Hall/ Multipurpose Hall 1.4 All 200 280 2 560 Public/Built
L Library 10 All 50 500 1 500 Semi-Public/Built
1 Reception Desk
2 Cloak Room
3 Security Desk
4 Librarian Office
5 Catalogue Room
6 Binding Area
7 Study Room
8 Digital Library
9 Archive Room
10 Reading Area
11 Shelves
12 StoreRooms
M Material /Fabric Resources Room 10 All 50 500 1 500 Semi-Public/Built
Lecture Hall 2 40 80 4 320 Semi-Public/Built
N Large Convention Space(Built) 1.5 All 500 750 1 750 Public/Built
1 Main Show Area
2 Backstage Area
3 Pre-Function Area
4 Conference / Meeting Room
5 Exhibition Space(Open + Expandable) 750 1 750
Total Area 3380
CHILL ZONE
O Cafeteria 1.8 All 250 2 500 Public
1 Dining Area
2 Cooking Area
3 Preparation Area
4 Dry Store
5 Cold Store
6 Deep Freeze Store
7 Dishwashing Area
8 Catering Area
9 Loading / Unloading Area
10 Locker/Changing Room
11 Washrooms
P Restaurant 1.8 All 200 360 1 360 Public
Total Area
COMMON ZONE
Public
Q OFFICE/ WORK AREA All Public
Fixed Seating 6 All 50 300 Public
Occupancy Standard Carpet Area Light
S.No. Area Focus Industry User Group Occupants Nos Total Area Remarks Nature Of Space Technical Requiremnets Column 1
sq.m / person sqm/unit (sq.m) Requirement
Flexible Seating 3 All 100 300 Public
Standing 2 All 200 400 Public
Private Cabins All 18 70 1260 Public
Mentor /Meeting /Discussion Area 4 All 100 20 400 Public
R Co-Working Spaces All
Hot Desk Area 4 All 500 2000 1 2000
Total Area 4660
SERVICE AND PLANT ROOM
1 Electrical Substation 0
2 Security Facility
3 Mechanical Services
4 Pump Room
5 Garbage Disposal
6 HVAC
7 DG Set
8 STP
SERVICE (Each Floor)
1 AHU
2 Electrical Rooms
3 Pantry
4 Janitor Room
5 Elevators

20719
Added 40% (Circulation +
Washrooms + Miscllaneous ) 29006.6