PDFES505
PDFES505
KLM Technology
Group Rev: 01
Project Engineering
Standard
Feb 2011
www.klmtechgroup.com
TABLE OF CONTENT
SCOPE 2
REFERENCES 2
DEFINITIONS AND TERMINOLOGY 3
SYMBOLS AND ABBREVIATIONS 3
UNITS 3
GENERAL 4
MINIMUM INFORMATION TO BE SHOWN ON P&I DIAGRAMS 10
DESIGN CRITERIA FOR PREPARATION OF P&I DIAGRAMS 25
CRITERIA FOR UTILITY FLOW DIAGRAMS 35
ABBREVIATIONS / GRAPHICAL SYMBOLS / IDENTIFICATIONS 37
PREPARATION OF P&I DIAGRAMS 38
APPENDIX A 51
APPENDIX B 118
APPENDIX C 120
APPENDIX D 121
APPENDIX E 122
APPENDIX F 123
APPENDIX G 124
APPENDIX H 126
APPENDIX I 128
APPENDIX J 129
PIPING AND Page 2 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
SCOPE
This Engineering Standard Specification covers the format and technical basis
for the Piping and Instrumentation Diagrams (P&IDs) and Utility Distribution Flow
Diagrams (UDFDs) for process, offsite and utility plants. Namely, the purpose of
this manual is to indicate in general terms, the extents of detailing, valving
philosophy and instrumentation requirements of similar process designs.
This Standard is also intended to establish uniform symbols for equipment, piping
and instrumentation on P&IDs and UDFDs throughout the Oil, Gas and
Petrochemical (OGP) projects.
REFERENCES
Throughout this Standard the following dated and undated standards/codes are
referred to. These referenced documents shall, to the extent specified herein,
form a part of this standard. For dated references, the edition cited applies. The
applicability of changes in dated references that occur after the cited date shall
be mutually agreed upon by the Company and the Vendor. For undated
references, the latest edition of the referenced documents (including any
supplements and amendments) applies.
1. ASME(AMERICAN SOCIETY OF MECHANICAL ENGINEERS)
- B31 Series "For Pressure Piping"
- B16.1 "Cast Iron Pipe Flange and Flanged Fittings, Class 25,
1st.Ed.,1989"
2. ISA (THE INTERNATIONAL SOCIETY OF AUTOMATION )
- S5.1 "Instrumentation Symbols and Identification 1st. Ed., 1984"
- S5.2 "Binary Logic Diagrams for Process Operations 2nd. Ed., 1981
(Reaffirmed 1992)"
- S5.3 "Graphic Symbols for Distributed Control / Shared Display
Instrumentation, Logic and Computer Systems “Ed.,1983"
- S5.4 "Instrument Loop Diagrams Ed., 1991"
- S5.5 "Graphic Symbols for Process Displays 1st. Ed., 1985"
- S18.1 "Annunciator Sequences and Specifications 1st. Ed., 1979
(Reaffirmed 1992)"
PIPING AND Page 3 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Licenser - A company duly organized and existing under the laws of the said
company’s country and as referred to in the preamble to the contract.
Unit- one or all process, offsite and/or utility Units and facilities as applicable to
form a complete operable oil, gas and/or petrochemical plant.
UNITS
GENERAL
Definition
The Piping and Instrument Diagram (P&ID), based on the Process Flow Diagram
(PFD), represents the technical realization of a process by means of graphical
symbols for equipment and piping as well as graphical symbols for process
measurement and control functions. The Utility Distribution Flow Diagram
(UDFD) is a special type of a P&ID which represents the utility systems within a
process plant showing all lines and other means required for the transport,
distribution and collection of utilities. The process equipment in the UDFD can be
represented as a box with inscription (e.g., identification number) and with utility
connections.
Representation
All equipment shall be represented such that the consistency in their dimensions
is considered if not in contrast to the good representation of the equipment.
Drafting
1. General rules
Drafting shall be in accordance with the requirements outlined in this
Standard. The drafting must be of sufficiently high quality to maintain legibility
when the drawing is reduced to an A3 size sheet.
PIPING AND Page 5 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
4. Line widths
To obtain a clear representation, different line widths shall be used. Main flow
lines or main piping shall be highlighted.
The following line widths shall be applied:
- 0.8 mm for main process lines;
PIPING AND Page 6 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
- 0.5 mm for other process lines; utility lines, and underground lines;
- 0.5 mm for graphical symbols for equipment and machinery, except valves
and fittings and piping accessories;
- 0.5 mm for rectangular boxes for illustrating Unit operations, process
equipment, etc.;
- 0.5 mm for subsidiary flow lines or subsidiary product lines and for energy
carrier lines and auxiliary system lines;
- 0.4 mm for class changes designation;
- 0.3 mm for graphical symbols for valves and fittings and piping
accessories and for symbols for process measurement and control
functions, control and data transmission lines;
- 0.3 mm for all electrical, computer and instrument signals;
- 0.3 mm for reference lines;
Line widths of less than 0.3 mm shall not be used.
5. Line spacing
The space between parallel lines shall not be less than twice the width of the
heaviest of these lines with a minimum value of 1 mm. A spacing of 10 mm
and more is desirable between flow lines.
6. Direction of flow
In general, the main direction of flow proceeds from left to right and from top
to bottom. Inlet and outlet arrows are used for indicating the inlet and outlet of
flows into or out of the diagram. Arrows are incorporated in the line for
indicating the direction of the flows within the flow diagram. If necessary for
proper understanding, arrows may be used at the inlets to equipment and
machinery (except for pumps) and upstream of pipe branches. If a diagram
consists of several sheets, the incoming and outgoing flow lines or piping on a
sheet may be drawn in such a manner that the lines continue at the same
level when the individual sheets are horizontally aligned.
7. Connections
Connections between flow lines or pipelines shall be drawn as shown in Fig. 1
and 2 below:
PIPING AND Page 7 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Fig.1 Fig.2
Figs. 3 and 4 show two flow lines or pipelines, which are not connected:
Fig.3 Fig.4
8. Inscriptions
a. Type of lettering
Lettering in accordance with ISO 3098 Part 1, Type B vertical, to be used.
b. Height of lettering
The height of letters should be:
- 7 mm for drawing number;
- 5 mm for drawing title and identification numbers of major equipment;
- 3 mm for other inscriptions.
c. Arrangement of inscription
i) Equipment
Identification numbers for equipment should be located close to the
relevant graphical symbol, and should not be written into it. Further
PIPING AND Page 8 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Piping and Instrument Diagrams shall be divided into equivalent intervals (each
in 50 mm) either in length or width. The intervals shall be designated with
numbers from 1 to 23 in length and alphabets from "A" to "P" in width. Equipment
location on each diagram shall be addressed by the relevant coordinates where
required. In upper right-hand area of the flow diagram under title of "Item Index"
all main equipment shall be listed by equipment number, alphabetically and
numerically and equipment location coordinates. In a separate sheet apart from
P&IDs, an "Item Index" shall be prepared to summarize all equipment of the
Unit/Plant with reference P&IDs and equipment location.
Arrangement
1. The preferred arrangement is such that towers, vessels and fired heaters are
shown in the upper half of the diagram, heat exchange equipment in the
upper three quarters as practical, and machinery equipment in the lower
quarter. The spacing of equipment and flow lines shall permit identification
and tracing of the lines easily.
2. The area above the title block on each sheet shall be completely left open for
notes.
PIPING AND Page 9 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
3. The general flow scheme shall be from left to right. Unnecessary line crossing
should be avoided.
4. Process lines entering and leaving the diagram from/to other drawings in the
Unit shall be terminated at the left-hand or right-hand side of the drawing.
Lines from/to higher number drawings shall enter and leave the drawing on
the right-hand end and vice versa.
5. Each process line entering or leaving the side of the drawing should indicate
the following requirements in an identification box (see Appendix B):
a. The line service
b. The origin or destination equipment item number
c. Continuation drawing number with the relevant coordinates.
6. Process lines to/from other Units should be terminated at the bottom of the
drawing at a box indicating the following requirements (see also Appendix B):
a. The line service
b. Source or destination Unit name and number
c. The drawing number of the connecting flow diagrams with the relevant
coordinates.
7. All utility lines entering or leaving the diagram shall be terminated at any
convenient location at a box indicating the relevant utility service abbreviation
(e.g., CWS, CWR, IA, etc.). See Appendix A of this Standard for utility
services abbreviations. “Utilities Identification Table” Showing utility services
with the reference drawings should be provided at top or left hand side of
each drawing title block (see Appendix C).
8. Instrument, control system and software linkage signals from sheet to sheet
shall be terminated preferably at the side of sheet or in an appropriate
location at a box indicating the continuation instrument number, location, and
drawing number (see Appendix B).
9. Equipment descriptions of towers, vessels, tanks, furnaces, exchangers,
mixers and other equipment except machinery shall be located along the top
of the flow diagram. Machinery descriptions shall be along the bottom.
PIPING AND Page 10 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
General
Each P&ID shall present all information as required herein below during
implementation of a project in detailed design phase. Extent of information shown
on each P&ID in the basic design stage shall be agreed by Company in advance.
Vendor supplied packages with an outline of the main components shall be
shown in a dashed/dotted box. Letter "PU" referring to package shall be indicated
adjacent to each equipment and instrument of the package.
Equipment, instruments or piping which are traced or jacketed, shall be shown.
The identification number and service presentation shall be shown for each piece
of equipment. This information shall be indicated in or adjacent to towers, drums,
heaters, tanks and heat exchangers, etc.
Equipment Indication
Notes:
i) For draw-offs only "NLL" shall be shown. The other liquid positions
will be shown as required.
ii) Indication of "HHLL" and "LLLL" shall be made when they are
actuating start/stop of an equipment or machinery through a switch.
iii) "HLL", "NLL" and "LLL" shall be shown for all cases except as
specified under Note i) above.
- All flanged connections; [all connections whose purpose is not readily]
evident shall indicate the purpose (e.g., spare inlet, catalyst draw-off,
etc.)
- Catalyst beds, packings, demisters, chimney trays, distributors, grids,
baffles, rotating discs, mixers, cyclones, tangential inlet and all other
internals;
- Water drop-out boots;
- Maintenance blinds for the vessel nozzles.
b. Important notes:
- All nozzles and connections indicated on the equipment data sheet
shall be shown in their correct positions.
- All indications shall be such that the consistency in the dimensions is
considered, although not necessarily to scale.
- Numbering of the trays shall be from bottom to top.
- Height of the vessel bottom tangent line shall be indicated.
- Self standing : Skirt height
- Elevated vessel: Minimum required height shall be shown as "min. ...."
- A valved drain for all columns and vessels shall be indicated.
Generally, this valve is to be located on the bottom line outside the
skirt and between the vessel and the first pipe line shut-off location
(valve or blinding flange). The drain valve shall be located on the
bottom of the vessel when:
i) No bottom line is present, or
ii) The bottom line is not flushed with the lowest point of the vessel.
- The valved vent with blind flange for all columns and vessels provided
on the top of the vessel should be indicated.
PIPING AND Page 12 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
b. Equipment description
- Equipment item number (this number will also appear adjacent to the
equipment);
- Service;
- Duty (kJ/s);
- Tube side design pressure (internal and external) and design
temperature.
6. Rotary machineries
a. The following requirements shall be shown:
i) Pumps
- All nozzles including instrument connections;
- Pump suction valve and strainer, and discharge valve and check
valve. Provision of wafer type check valve should be avoided
unless otherwise specified;
- Pump drains and vents piping and destination.
- The type of pump;
- Pump auxiliary system connections such as, cooling water, seal oil
and lube oil, steam, etc.;
- Detail of lube and seal oil /sealing systems, cooling water piping
arrangement, and minimum flow bypass line requirement for
pumps;
- Winterization and/or heat conservation (steam or electrical) where
required;
- Warm-up and flushing oil lines detail; a DN20 (¾ inch) bypass/drain
from the check valve to the pump discharge line shall be provided
as warm-up line for the cases specified in item 8.1.4 of this
Standard;
- Pressure gage located on the discharge of each pump; the gage
shall be installed between the pump discharge nozzle and the
check valve;
- Pressure relief safety valves (if any);
- Automatic start-up of standby unit (if required);
- Balanced or equalized line for vacuum service.
PIPING AND Page 17 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
7. Miscellaneous equipment
Depending on the type of equipment (silencer, flame arrestor, filter, etc.) the
following information shall be presented:
a. All nozzles, instrument connections, vents, drains, etc.;
b. Equipment description at top of the flow diagram and including:
- Equipment item number;
- Service;
- Tracing/insulation requirements;
- Design pressure and temperature;
- Capacity
Instrumentation
Piping
1. General
a. All piping shall be shown on P&I Diagrams, including:
- Process lines;
- Utility/common facility branch lines (e.g., sealing and flushing lines,
cooling water lines, steam-out lines and connection, nitrogen lines,
etc.);
- Flare lines, including safety/relief valves discharge lines;
- Start-up and shut-down lines;
- Pump-out lines;
- Drain and vent lines and connections;
- Purge and steam-out facilities;
- Catalyst regeneration lines;
- Catalyst sulphiding lines;
- Catalyst reduction lines;
- Equipment and control valve bypasses;
- Detail of spool pieces, equipment internals, etc., when required;
- Steam tracing and steam jacketing.
b. All line numbers, sizes and line classification shall be shown.
c. The direction of normal flow shall be shown for all lines.
PIPING AND Page 21 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
d. The points or spec. breaks at which line sizes or line specifications change
shall be clearly indicated.
e. All blinds shall be indicated on the drawings, and the symbols used shall
distinguish between tab blinds and spectacle blinds.
f. All vent and drain connections shall be identified whether screw caped or
blind flanged, if required.
g. Steam traced lines and steam jacketed lines shall be so indicated.
h. All equipment flanges, all reducers and non-standard fittings, such as
expansion bellows, flexible tubes, shall be shown.
i. All valves shall be shown by a symbol representing the type of valve. Any
special orientation or location required for process reason and/or
operability shall be shown. It is not necessary to show flanges at flanged
valves except for those cases where the flanges deviate from the piping
specification for the line in question, in which case flange and rating shall
be shown. Any isolating valve shall be shown locked, normally open or
closed.
j. Control valve sizes shall be shown.
k. All valves shown on the flow diagram shall have their size indicated by the
valve, if different from line size.
l. Insulation and tracing requirements shall be covered in the line numbering
system and shown above the line. Tracing requirement shall be noted on
P&IDs by a dashed line parallel to the line to be traced.
m. Valve boxes/valve pits shall be shown by two embraced squares or
rectangular with indication of "Valve Box" or "Valve Pit".
n. Safety relief valves type, inlet and outlet size and rating and set pressure
should be shown.
o. For pressure ratings designations-nominal size and pipe component-
nominal size see Appendices F & G of this Standard respectively.
2. Special requirements
a. High point vents and low point drains are shown only when they are
connected to a closed system, or are required for process reasons.
b. Utility lines originate and terminate adjacent to the equipment involved
shall be shown. Only the length of line necessary for valving,
instrumentation and line numbering is shown. Utility line origin and
terminus is indicated by reference symbol or abbreviation only. Main utility
PIPING AND Page 22 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
headers are not shown on the P&IDs; they are shown on the utility system
flow diagrams.
c. Pertinent information regarding a line such as "do not pocket" or "slope",
etc., shall be noted adjacent to the line.
d. Typical air cooler manifold piping arrangement should be shown.
e. Connections on process lines which require being blanked or deblanked
for flow direction under special circumstances to be shown on P&ID.
f. Reduction and enlargement in line size are indicated by line size
designation, and reducer and expander symbols.
g. Calculated wall thicknesses and/or schedules not already prespecified in
the individual line classes shall be shown on the flow diagrams.
h. Corrosion allowances other than the nominal allowances indicated in the
individual line classes shall be shown on the diagrams.
i. All operating drains shall be noted and sized on the flow diagrams and
shall be routed to a drain funnel. Destination of the drains shall be
according to the relevant specifications. All drains carrying light
hydrocarbons (Reid vapor pressure 34.5 kPa absolute or greater) shall be
segregated from the oily sewer system, and shall be connected to the flare
system.
j. Sample and test connections shall be shown on the diagrams where
required. Samples which require cooling and connections to the flare shall
be shown with the cooling and flare lines connections.
k. Emergency showers, eye wash fountains and utility stations shall be
shown on the Utility Distribution Flow Diagrams.
l. Any locations where slopes, straight runs, minimum mixing runs, etc., are
required for process reasons must be indicated.
m. The necessary instrumentation and piping for start-up, control and shut-
down, etc., sall be shown for any equipment on P&ID wherever applicable.
n. Break points between underground and aboveground piping with
insulating flanges (if required) shall be shown.
o. Minimum distance requirement for in line blending to be indicated.
p. Weep hole requirement to be shown.
PIPING AND Page 23 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
General Notes
General notes to be put on the front sheet of P&I Diagrams of each "Unit" under
title of "General Notes". Reference should be made to the front sheet drawing
No. showing "General Notes", on each P&I Diagram.
1. The following general notes shall be specified as minimum requirement:
a. All dimensions are in millimeters except as noted.
b. Elevations shown are above the highest point of paving.
PIPING AND Page 24 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
The following design criteria shall be applied for preparation of P&I Diagrams
unless otherwise specified in the relevant piping and/or equipment specifications
of the Company. In case of any conflict, the specific piping and/or equipment
specifications will be governed.
2. Pump strainer
The suction strainer of pumps shall be selected in accordance with the
following criteria:
PIPING AND Page 26 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Strainers DN150 (6 inch) and larger shall have DN 25 (one inch) drain valve.
1. The vent valve shall be directly mounted on the vent nozzle with blind flange.
2. A blanked off ventilation nozzle shall also be provided on the top of the all
horizontal vessels near the end opposite the manway.
PIPING AND Page 27 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
The bypass shall be provided for venting the hydrocarbon gas or toxic gas to
flare system while plant shut-down or start-up. Provision of bypass shall be as
per following criteria:
1. Vessels
Bypass shall be provided unless otherwise specified in the relevant
Company’s specifications.
2. Piping/equipment
a. Gas service
- If there is other purge line to flare on same stream line, bypass is not
required for safety/relief valve.
- In case of no purge line to flare for toxic or flammable hydrocarbon,
bypass valve shall be provided. The size of bypass valve and line shall
be same as the vent size of piping/equipment.
b. Liquid service
Bypass valves are generally not provided for liquid service unless
otherwise specified.
Line Numbering
1. Line numbers shall be assigned to all lines with the following origins and
destinations:
PIPING AND Page 28 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Utility Connections
PIPING AND Page 29 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Utility connections to process line and equipment for steam and nitrogen shall be
as follows:
1. Connections to process line and/or equipment (see Figs. 5 and 6):
Fig. 5
Fig. 6
PIPING AND Page 30 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Fig. 7
Sample Connections
Fig. 14
b. Heat conservation
The following symbol can be used in place of the steam trap assembly
shown below in Fig.15 on P&IDs and UFDs.
Fig. 15
Fig. 16
CRITERIA FOR UTILITY FLOW DIAGRAMS
7. The finger area is defined as being the area that serves a particular process
area which may consist of one or more process Units. In addition to the
equipment that is located alongside the finger pipe rack, the finger area also
includes the equipment located alongside the main pipe rack.
8. Utility Flow Diagram shall be arranged to cover the whole refinery/plant area
and these are divided into separate sheets each with corresponding match
lines. Depending on the complexity and extent of the particular utility/common
facility, sheets may be combined, extended or omitted as required.
9. All equipment that is supplying a particular utility common facility either from
the system (e.g., steam boilers) or from a process Unit (e.g., waste heat
boilers) shall be shown in a "box" in geographical location. This "box" shall
give relevant equipment number(s), Unit number and sheet number of the
drawing in which the equipment is detailed.
General
PIPING AND Page 39 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
As the P&I Diagram contain a large amount of plant design information, its
revision will have a great effect on the subsequent engineering works.
Accordingly for the purpose of minimizing the revisions and avoiding
unnecessary works, the steps for preparing the P&I Diagrams shall be
established. The following steps should be realized in preparing the P&I
Diagrams. Upon the information which can be prepared as engineering work
proceeds, steps 2, 3 and 4 may be combined or extended to more steps as
required.
- Step 1 Preparatory Step for Preparation of the P&I Diagrams
- Step 2 P&I Diagrams for Engineering Start
- Step 3 P&I Diagrams for Piping Layout
- Step 4 P&I Diagrams for Piping Drawings
- Step 5 P&I Diagrams for Construction
- Step 6 P&I Diagrams As-built
In the case where the P&I Diagrams are prepared by the Licensor, only a part of
the above-mentioned steps is applied and the main Contractor shall be
responsible to complete the P&IDs preparation steps. The extent of Licensor’s
and Contractor’s scope of work will be according to the relevant contracts.
- Title;
- Drafting;
- Arrangement;
- Equipment description;
- Interconnection.
b. Numbering system
- Drawing No.;
- Equipment No.;
- Instrument tag No.;
- Line No.
c. Symbol
- Equipment;
- Piping components;
- Instrument symbol;
- Process stream symbol;
- Utility symbol.
d. Valve arrangement around equipment
- Valve arrangement for drain, vent and purge;
- Valve arrangement for steam-out;
- Sizes of the nozzles for installing the instruments;
- Valve arrangement around the heater and exchanger;
- Valve arrangement around the pump and compressor;
- Valve arrangement around the steam turbine.
e. Piping
- Piping classification standards;
- Valve arrangement at the battery limit;
- Valve arrangement for drain, vent, purge and steam-out on piping;
- Valve arrangement around the steam trap;
PIPING AND Page 41 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Chemical cleaning;
Steaming-out;
Evacuation;
Drying;
Water operation;
Cold circulation;
Hot circulation;
Catalyst pretreating such as sulfiding, reduction, etc.;
Feed cut-in;
Off-spec. product handling.
Catalyst regeneration.
iv) Safety operation
Location of safety/relief valves;
Failure action of control valves;
Prealarm system;
Emergency shut-down system;
Auto start of equipment/system.
Results of hazard analysis and operability (HAZOP) study (if
any). Note: Contractor shall perform the HAZOP study (if
required by the owner) using PFD, P&ID and plot plan together
with equipment data sheets and related safety equipment
checklist. Contractor shall provide information about the
reported accidents in similar process units in the world during
HAZOP meetings.
The Contractor should prepare both the draft of the basic items for
preparation of the P&ID and all necessary operation and safety
features as mentioned above to Company’s review and approval
before issuance of official revision of P&ID for engineering start.
2. Step 2, P&ID for engineering start
The following information as minimum requirement shall be reviewed and
completed at this stage:
a. Equipment
- Number of equipment;
- Type of equipment;
- Equipment No. and name.
b. Piping
- Size of main piping;
- Winterizing/heat conservation requirement;
- Valve type;
- Provision of drain and vent;
PIPING AND Page 44 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
The draft of the P&ID for engineering start shall be sent to the
Company’s review. After the joint meeting between the Company and
Contractor, the P&ID for engineering start can be officially issued
based on the established Company’s comments as per the agreed
items mentioned in the relevant minutes of meeting.
3. Step 3, P&ID for piping layout
The purpose of issuing the P&ID for piping layout is the Company’s approval
on the basis of detailed design for piping layout.
The minimum information which should be added on the P&ID at this stage
shall be as follows:
a. Equipment
- Elevation of equipment;
- Size of equipment;
- Internal of equipment.
b. Piping
- Line class;
- Miscellaneous piping size (except around the safety/relief valve and
control valve);
- Thermal and cold insulation;
PIPING AND Page 45 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
The P&ID shall be issued for construction after completion of the following
activities:
- Piping material table;
- Piping class and all relevant job specifications;
- All job specifications and standard drawings in relation to the preparation
of P&ID;
- Logic diagram of the main equipment;
- Hydraulic of system;
- Size of all piping, valves and instrumentation components;
- Vendor’s information.
Absolutely, required revisions after freezing of the P&ID shall be made only
by conducting of design activities using the relevant field sketches and
executing the required modifications approved by the Company. This is
applicable to revisions called for at the design department. The frozen P&ID
shall not be revised.
6. Step 6, P&ID as-built
The P&ID as-built shall be prepared upon completion of the project for filing
and submission to the Company. Since the P&ID is intended for use in
conducting operation control, maintenance or revamping, therefore, the
prepared drawings shall be entirely in conformity with the completed facilities.
The P&ID as-built shall be prepared in accordance with the results of line
checking and the final edition of the field sketches.
The specified piping and instrument take-off and branch points shall be
observed as strictly as possible and shall be implemented on the P&ID.
Although bearing no relationship to piping layout, none of the flange, cap,
drain pot, spectacle blind and other miscellaneous piping designed for
installation at the ends of the drain and vent required for operational purposes
shall be omitted.
Revisions of P&ID
1. General
Generally P&ID can be revised in the following conditions if complied with the
requirements as outlined in Section 11 of this Standard:
- For correction of typographical and/or engineering errors;
- As per the Company’s instructions;
- Implementation of pertinent information in the course of execution of the
relevant engineering work on P&ID;
- Addition of information concerning vendors.
Upon agreement with the Company, revisions made after the issuance of the
"P&ID for piping layout" may not be needed by directly revising the P&ID but
by issuing the NPIC "Notification of P&ID Change".
2. Revisions
The P&ID shall be revised depending on necessity at each step in addition to
the required edition(s) which shall be issued per each step. Accordingly it
does not follow that the step No. and revision No. coincide with each other. At
the time of revising the P&ID the NPIC issued up to that time and information
concerning vendors obtained up thereto shall be incorporated on the P&ID.
3. NPIC
Issuance of Notification of P&ID Change (NPIC) and manner of presentation
shall be agreed in advance with the Company. NPIC shall be issued in a
PIPING AND Page 50 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
NPIC form finalized with the Company. In general issuance of NPIC should
consider:
- Minimization of P&ID revisions;
- Not accumulation of a large amount of additions/changes which should be
incorporated on the new revisions of P&ID.
Approval of P&ID
1. Company’s approval of the basic items for preparation of P&ID shall be
obtained prior to commencement of the P&ID preparation work.
2. The Company’s approval at step 2 " P&ID for engineering start" shall be
obtained regardless of the cases that P&ID is prepared by the Contractor or
Licenser or both.
3. Where the P&ID prepared by Licenser has been reviewed or verified in step 3
"P&ID for piping layout" by the Contractor, Company’s approval is needed
before any official revision.
4. In general, Company’s approval is required for any change, deletion and/or
addition on the P&ID.
PIPING AND Page 51 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
PIPING AND Page 52 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
APPENDICES
APPENDIX A
ABBREVIATIONS/GRAPHICAL SYMBOLS/IDENTIFICATIONS
Abbreviations
3. Piping abbreviations
CM Chrome Moly
CS Carbon Steel
DN Diameter Nomina
FF Flat Face
FS Forged Steel
HB Hammer Blind
LJ Lap Joint
MI Malleable Iron
PB Pressure Blind
PN Pressure Nominal
PTP Pipe Tap Plugged
RF Raised Face
RS Removable Spool
RSP Ring Spacer
RTJ Ring Type Joint
SF Socket Weld Line Blind with Flexitallic Gaskets
SB Spectacle Blind
SPB Spade Blind
SO Slip on
SS Stainless Steel
ST(W) Steam Trap (Winterizing)
ST(H) Steam Trap (Heat Conservation)
SV Socket Weld Line Blind with Viton Gaskets
SW Socket Weld
VB Vapor Blind
WN Weld Neck
4. Miscellaneous designations
AG Above Ground
BL Battery Limit
COF Center of Float
DCS Distributed Control System
F Furnished
F&P Furnished & Piped
HCB Hydrocarbon
HCH Hydrocarbon with Hydrogen
HHLL High High Liquid Level
HIL High Interface Liquid Level
HLL High Liquid Level
LF Liquid Foam
PIPING AND Page 55 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
LG Level Gage
LIL Low Interface Liquid Level
LLL Low Liquid Level
LLLL Low Low Liquid Level
LSHH Level Switch High High
LSLL Level Switch Low Low
MW Manway
NIL Normal Interface Liquid Level
NLL Normal Liquid Level
P Pressure
PB Push Bottom
PFD Process Flow Diagram
PG Pressure Gage
PI Pressure Indicator
P&ID Piping & Instrumentation Diagram
PO Pump Out
PT Pressure Test Connection
RES Residue
RG Refrigerant Gas
RL Refrigerant Liquid
RO Restriction Orifice
RS Remote Setpoint
RTD Resistance Temperature Detector
RVP Reid Vapor Pressure
SC Sample Connection
SCL Sample Cooler
SG Sight Glass
SF Solution Foam
SP Set Point
SP.GR Relative Mass Density (Specific Gravity)
STO Steam Out
TI Temperature Indicator
T/T Tangent to Tangent
TW Thermo well
UFD Utility Flow Diagram
UG Under Ground
VB Vortex Breaker
Graphical SYMBOLS
1. Instrumentation
a. Instrument line symbols
ISA-S5.1 (latest revision) section 6.2 shall be used with the following
amendments:
- Heat Traced Line
- Steam Jacketed Line
The following abbreviations shall be used to denote the types of power
supply. These designations may also be applied to purge fluid supplies:
AS Air Supply
IA Instrument Air
PA Plant Air
ES Electric Supply
GS Gas Supply
HS Hydraulic Supply
NS Nitrogen Supply
SS Steam Supply
WS Water Supply
The supply level may be added to the instrument supply line, e.g., IA-600
"a 600 kPa instrument air supply; ES-24 VDC “a 24-volt direct current
power supply".
Symbol Description
Output exists if one or ore input
exists
Symbol Description
Field mounted PLC integral to DCS not
normally accessible to operator
Symbol Description
Field mounted instrument not normally
accessible to operator
Panel mounted instrument not normally
accessible to operator
Local panel mounted instrument normally
accessible to operator
Instrument mounted behind control panel in
control room not normally accessible to
operator
Instrument mounted behind local panel not
normally accessible to operator
Symbol Description
Field mounted instrument (not normally
accessible to operator)
Indicator/controller/alarm (normally
accessible to operator)
Symbol Description
Field mounted instrument
Symbol Description
Steam traced instrument
Symbol Description
Purge or flushing device
diaphragm
Note:
For specific logic symbols, see ISA standard S5.2.
PIPING AND Page 62 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
= multiplying
= dividing
= high selecting
= low selecting
= high limiting
= low limiting
= time function
= summing
= averaging
= root extraction
PIPING AND Page 63 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
= exponential
= derivative
= integral
= pneumatic to current
= proportional
= reverse proportional
= difference
= convert
= velocity limiter
PIPING AND Page 64 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
= bias
= reverse action
= inverse derivative
= solenoid
= boost
= integrate
= on-off
= analog/digital
DESIGNATION SIGNAL
E Voltage
I Current (Electrical)
H Hand
O Electromagnetic
P Pneumatic, Pressure, Vacuum
R Radiation
MV Milivolts
A Analog
D Digital
PIPING AND Page 65 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Notes:
1. The function designations associated with controllers, computing
devices, converters and relay may be used individually or in
combination (also, see Table 1, Note 14 of ISA-S5.1). The use of a box
avoids confusion by setting off the symbol from other markings on a
diagram and permits the function to be used as a stand-alone block on
conceptual designs.
2. See ISA-S5.1, Table 3 for math equation, graphic representation and
definition.
l. Actuator symbols
See article 6.5 of ISA-S5.1
PIPING AND Page 66 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
SYMBOL 2DESCRIPTION
Main process line (arrow of 30o
indicates Direction of fluid flow )
Heat traced pipe line
Underground pipeline
Existing line
Future line
Vendor package
Jacketed or double containment
pipeline
Line crossing (connected)
Lines junction
Drip funnel
Platform
a) change in slope
b) change in piping class
PIPING AND Page 67 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
c) change in responsibility
slope
Level reference
Limit , general
Contractor/ vendor
Battery limit
Hood , general
SYMBOL DESCRIPTION
Open vent
Bursting disc
Sight glass
Level gage
SYMBOL DESCRIPTION
Butt welded joint
Flanged joint
Swivel joint
SYMBOL DESCRIPTION
Ring spacer
Spade blind
Hammer blind
expansion bellow
sleeve extension
expansion loop
SYMBOL DESCRIPTION
Desuperheater
Ejector
Jet mixer
Ring header
Explosion-proof flame
arrestor (explosion comes
From the side of the
rectangular)
Detonation –proof flame
arrestor
PIPING AND Page 72 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Silencer
SYMBOL DESCRIPTION
Bucket (basket) type strainer
T-type strainer
Duplex strainer
PIPING AND Page 73 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Pulsation dampener
Filter (general)
Propller mixer
Turbo mixer
SYMBOL DESCRIPTION
Loading arm (basic
symbol)
Portable extinguisher
Wheeled extinguisher
Foam chamber
Insulation on equipment
Spray
SYMBOL DESCRIPTION
Manway
Swing elbow
Breather
PIPING AND Page 75 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Emergency (safety)
shower equipped with no
freezing drain valve
Vortex breaker
Exhaust head
SYMBOL DESCRIPTION
Sample connection (non
toxic gas ), see
Appendix G for details
(type 1)
Sample connection (toxic
gas or light liquid (RVP34.5
kPa) ,see appendix G for
details ,(type 2)
PIPING AND Page 76 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
SYMBOL DESCRIPTION
Gate valve (basic symbol)
Globe valve
Ball valve
Four-way valve
Butterfly valve
PIPING AND Page 77 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Hydraulic control
Metering cock
Needle valve
Plug valve
S=solenoid valve
R= Manual reset when
indicated
Diaphragm valve
SYMBOL DESCRIPTION
Self contained regulator
Three-way valve
Rotary valve
Slide valve
PIPING AND Page 78 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Knife valve
Piston valve
Y- type blow down valve
Float valve
SYMBOL DESCRIPTION
Lift check valve
Swing check valve
Stop check
Damper valve
SYMBOL DESCRIPTION
Foot valve
Fire hydrant
Deluge valve
Fire monitor
Yard hydrant
= Hose reel
Hose gouse
SYMBOL DESCRIPTION
Elevated fire monitor
Foam monitor
Equipment
1. Tower, column, vessel and reactor
a. Tower, column
Column
PIPING AND Page 83 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Reactor
b. Horizontal vessel
PIPING AND Page 84 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
i) Horizontal vessel
Dearator
Cone roof
(with agitator electric drive)
2. Strorage tanks
Floating roof
PIPING AND Page 86 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Sphere
Note:
All tanks and spheres on each flow diagram have to be shown in Approximate
relative size to each other.
Internal (covered) floating tank with swing suction pipe float type
PIPING AND Page 87 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Concrete sump
Stab-in exchanger
c. Air coolers
Note:
1) Indicate percentage of fans with automatic-variable pitch.
PIPING AND Page 93 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
d. Film evaporator
Film evaporator
4. Machinery
a. Pumps
Centrifugal pump
PIPING AND Page 94 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Rotary pump
(gear pump)
Reciprocating pump
Centrifugal compressor
Fan (blower)
Rotary compressor
Gyratory crusher
b. Screen
Screen bed
Revolving screen
Can conveyor
PIPING AND Page 103 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
c. Drier
Belt drier
Rotary drier
Drying oven
Drum drier
Spray drier
Flash drier
PIPING AND Page 105 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
d. Centrifuge
e. Mill
f. Agitator (Mixer)
g. Extruder
h. Separator
i. Filter
Basket filter
j. Bulk loading
Rotary kiln
PIPING AND Page 114 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Autoclave
Breaker gyratory
Ribbon blender
Kneader
Pelletizer
Grinder
Concrete/Birck/Soil
Brickwork
Concrete (reinforced)
Refractory clay,
Refractory bricks
Soil
PIPING AND Page 119 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
APPENDIX B
1. Reference blocks at the bottom of the drawing (only to be used for process
and instrument lines routing over the subject Unit battery limit).
2. Reference blocks at the side of drawing (only to be used for process and
instrument lines inside the same Unit).
PIPING AND Page 120 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
3. Reference arrows for instrument, control system and software linkage signals
at the inside of drawing (for the signals terminating or originating at the side
or bottom of drawing see items 1 and 2 above).
PIPING AND Page 121 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
APPENDIX C
UTILITIES IDENTIFICATION
REF. REF. REF.
DESCRIPTION DESCRIPTION DESCRIPTION
DWG DWG DWG
FWA Fire water HPS HP Steam FLR Flare discharge
DWA Drinking water MPS MP Steam IA Instrum ent ai r
Deminerized
DMW LPS LP Steam PA Plant air
water
Plant water Low Low
PWA LLPS NIT Nitrogen
(service water) Pressure Steam
RWA Raw water HPC HP Condensate RFO Refinery fuel oil
Hp boiler feed
HBW MPC MP Condensate FLG Fuel gas
water
Mp boiler feed
MBW LPC LP Condensate NG Natural gas
water
Cooling water
CWS COC Cold condensate
supply
Cooling water
CWR BFW Boiler feed work
return
Refrigerated
RFW
water
BFW Boiler feed water
PIPING AND Page 122 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
APPENDIX D
A,A2 Inlets
B Outlet
C Condensate
D Drain or Draw-off
E*
F Feed
G Level gage or gage glass
H Handhole
J Pumpout
K*
L Level instrument (also LT, LI)
M Manhole
N Reboiler connection
P Pressure connection (also PT, PI)
R Reflux
S Steam or sample connection
T Temperature connection (also TI, TE, TW)
V Vapor or vent
W Relief valve connection
(Oversize unless actual size known)
APPENDIX E
IMPERIAL-METRIC
IMPERIAL METRIC
Notes:
1) As per ASME B16.1 for cast iron valves.
2) As per API 602 for steel valves.
PIPING AND Page 124 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
APPENDIX F
The purpose of this Appendix is to present an equivalent identity for the piping
components nominal size in SI system and imperial unit system, in accordance
with ISO 6708-1980.
APPENDIX G
APPENDIX H
Block and bypass valve system may not be necessary where the process can be
shut-down to repair the control valve without significant economic loss or where
the process can not be feasibly operated through the bypass. However, the
consequences of shutting down a process Unit to perform a simple task ( such as
replacing control valve packing) should always be considered. In cases where
the block and bypass valves are not used, the control valve should be equipped
with a hand wheel or other operating devices.
Block and bypass valves are not always necessary in the following cases:
1. In instances where it is desirable to reduce the sources of leakage of
hazardous fluids, such as hydrogen, phenol, or hydrofluoric acid;
2. In clean service whererating conditions are mild, and o valves will not
jeopardize the safety or operability of the Unit;
3. In temporary services such as start-up or shut-down, and where the other
operation modes are possible while the repairing of control valve, such as
blending system of oil;
4. Pressure self regulating valves;
5. Shut-off valves
The following services should be provided with block and bypass valves:
1. Services where omission of valves will jeopardize the safety or operability of
the Unit;
2. Services containing abrasive solids or corrosive fluids result in damage of
trim of control valve, and require the repair;
3. In lethal services;
4. In product rundown and feed supplying services;
PIPING AND Page 128 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Notwithstanding the requirements outlined above the following notes should also
be considered:
1. Provide an upstream isolation valve for all control valves unless the upstream
system is to be shutdown on control valve failure.
2. Provide a downstream isolation valve whenever the downstream side of the
control valve can not be isolated from other continuously operating pressure
sources.
3. Provide a drain valve upstream of all control valves.
4. Provide a drain valve downstream of the control valve only when the process
fluid is toxic or corrosive and for tight shut-off services and fail to close valve.
PIPING AND Page 129 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
APPENDIX I
APPENDIX J
Note:
All details shall be consistent with the relevant process flow diagram and other
process documents.
1. All process equipment including installed stand-by equipment.
2. Insulation equipments of lines (heat conservation, process stabilization or
"not insulated") shall be shown on the P & ID.
3. Equipment, instruments or piping which are traced, jacketed or insulated.
4. Tower and vertical drum elevations from ground and tangent line elevations.
5. Horizontal drum minimum elevations and slope.
6. Relative elevations of all equipment and piping where gravity or 2- phase
flow is taking place, e.g. reboilers. Condensers, seal pots.
7. Equipment characteristic parameters dimension plus design temperature,
pressure and material of construction shall be given at the top of the P &ID.
8. Required line slope, relative, location of equipment or special conditions such
ad required vertical loop dimensions, gravity lines with or without pockets,
etc.
9. Vents and drains required for process or operating reasons (not hydraulic
testing).
10. Steam, hot water or solvent tracing of lines and instruments.
11. Gas or liquid purging or flushing of control valves, instruments or relief
valves, including their inlet and outlet isolating valves.
12. All start 0 up, by- pass, shutdown and emergency lines and lines for
anticipated alternative operations.
13. All instruments required for proper operation of the PLANT.
14. Instrumentation control loops including interlocks, sequence and emergency
shutdown.
PIPING AND Page 131 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
iii) Elevation required for process reasons, Thermo wells shall be provided
between each shell side and tube side of the same services when
exchangers are in series,
iv) The position of high liquid level (HLL), normal liquid level (NLL) and
low liquid level (LLL) for kettle type reboilers,
v) Direction of flow each side of exchanger.
b. Air coolers:
i) All nozzles, instrument connection, drains and vents,
ii) Blinds for the isolation,
iii) Any automatic control (fan pitch control or louver control) and any
alarm (vibration alarm, etc),
iv) Configuration of inlet and outlet headers and the branches,
v) Steam coil and condensate recovery system (if required),
vi) Isolation valves (if required),
vii) Valved vent and valved drain connection for each header (in detail
design stage),
viii) A board mounted TI at inlet and outlet. Thermo wells shall be
provided on the outlet of each bundle for bundles.
c. Vessels, Reactors, Towers and Drums:
i) Tray numbers, top and bottom trays and those trays witch are
necessary to locate feed, reflux and product lines. Trays shall be
numbered from bottom to top,
ii) All draw-off trays with tray no. And diagrammatic representation of
the down-comer position (e.g., side of center),
iii) Changes of shell diameter (if any),
iv) All nozzles, manholes, instrument connection, drains, vents, pump-
out and steam0out connection, blank-off ventilation, vortex breakers,
safety relief valve connection, sample connection and handholes. All
nozzles and connection shall be shown in correct position as
indicated in the equipment data sheet,
v) Skirt or legs, top and bottom tangent lines,
vi) Insulation/fire proofing requirement,
PIPING AND Page 134 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
- Sample tappings for gas samples shall be from the top of the
main line. For liquid samples tapping shall be done from the
side.
- Except for process reasons, low point drains and high point
vents are not shown
- All items marked (PU) can be supplied as part of package Units.
- Temperature instruments shown with "M" are provided with
Monel well.
The following general notes may be specified required:
o Piping drains and vents (if applicable for process reasons): Low
point drains and high point vents piping shall be provided in
accordance with the following requirements:
(a) Drains for all sizes:
- Alloy piping: DN 20 (¾ inch) gate valve with blind flange,
based on the fluid, operating condition and valid
standards.
- Carbon steel piping: DN 20 (¾ inch) gate valve with
threaded plug, based on the fluid, operating condition
and valid standards.
(b) Vents for DN 50 (2 inch) and larger:
High point vent shall be provide for the DN 50 (2 inch) and
larger. Size and type are based on the following:
- Alloy piping: DN 20 (¾ inch) gate valve with blind flange,
based on the fluid, operating condition and valid
standards;
- Carbon steel piping: DN 20(¾ inch) gate valve with
threaded plug, based on the fluid, operating condition
and valid standards;
- The vent provided for hydrostatic testing shall be DN
20(¾ inch) boss with threaded plug based on the fluid,
operating condition and valid standards.
o Block valves on orifice tap (in detail engineering stage):
- DN 15 (½inch) single gate valve shall be provided for the all
orifices of the piping class of PN 100 (600#) and less.
- DN 20 (¾inch) single gate valve shall be provided for the all
orifices of the piping class of PN 150 (900#) and over:
o Drain valve of level gages and instruments (in detail
engineering stage):
- Drin valves [DN 20 (¾ inch) gate valve] shall be provided.
- The provisions should be made for routing the drain of
liquids with RVP of greater that 34.5 kPa (abs) to flare).
PIPING AND Page 141 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Pump strainer:
The suction strainer of pumps shall be selected in accordance with
the following criteria:
LINE SIZE STRAINER TYPE
DN 80 (3 inch) and larger T
DN 50 (2 inch) and smaller Y
Warming-Up line:
The provisions for warming-up of pump is required for the pump
operated at 170ºc and higher when the process fluid solidifies at
ambient condition or the fluid are corrosive toxic.
Auxiliary piping of pump:
Details of auxiliary piping such as, cooling water, plant water, steam
and condensate, mechanical seal flush fluid, which are required as
per pump data sheet shall be shown on a separate drawing.
Reference to the auxiliary piping drawing shall be noted under the
pump description (in detail engineering stage).
v) Steam-out, Drain and Vent for Vessels:
Size and requirement of steam-out, vent and drain nozzles of
vessels shall according to the requirements stipulated in the
Employer’s requirements (design criteria of “Basic Engineering
Design Data”). The vent valve shall be directly mounted on the vent
nozzle with blind flange.
In addition to the vents required above, a blanked off ventilation
nozzle as requested in the Employer’s design criteria shall be
provided on the top of the all horizontal vessels near the end the
end opposite the man way.
Vent connections must be located on top of the vertical and
horizontal vessels.
The drain valve sill be provided as follows:
- For low pressure services, up to design pressure of 3800 kPa,
provide single block valve with blind plate.
- For high pressure services over design pressure of 3800 kPa,
or where the nature of liquid requires it, provide double block
valves with blind plate.
vi) Bypass for Safety/Relief Valve:
The bypass shall be provided for venting the hydrocarbon gas or toxic
gas to flare system while plant shut-down or start-up. Provision of
bypass shall be as per following criteria:
PIPING AND Page 143 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)
Vessels:
Bypass shall be provided unless otherwise specified in the relevant
Company ̀s specifications.
Piping/Equipment:
o Gas service:
- If there is other purge line to flare on same stream line,
bypass is not required for safety/relief valve.
- In case of no purge line to flare for toxic or flammable
hydrocarbon, bypass valve shall be provided. The size of
bypass valve and line shall be same as the vent size of
piping/equipment.
o Liquid service:
Bypass valves are generally not provided for liquid service
unless otherwise specified.
vii) Line numbering:
For line numbering system reference should be made to the
Employer’s line numbering specification.
Line numbers shall be assigned to all lines with the following origins
and destinations:
- From individual equipment item to individual equipment item;
- From individual equipment item and vice versa. Another
number is required for the line located at the downstream of
equipment;
- From line to line (exceptions: control valve bypass, block valve
warm-up and equalizing bypasses, and safety relief valve
bypass;
- From unique equipment to the same unique equipment item
(except level standpipes);
- From line or equipment to atmosphere, funnel, of closed
drainage system (exception: continuous process vent stacks
and process drains).
PIPING AND Page 144 of 144
KLM Technology INSTRUMENTATION DIAGRAMS
Group Rev: 07
(P&ID)
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2011
SPECIFICATIONS)