F5 Online - Progress Test 2 - STD
F5 Online - Progress Test 2 - STD
PROGRESS TEST 2
Paper F5 – Performance Management
Date:
Student’s name:..............................................................................
Email:...............................................................................................
Total Mark:
1. A company which makes two products, Alpha and Zeta, uses activity-
based costing to absorb its overheads. It has recently identified a new
overhead cost pool for inspection costs and has decided that the cost
driver is the number of inspections.
The following information has been provided:
Total inspection costs $250,000
Alpha Zeta
Production volume (units) 2,500 8,000
Machine hours per unit 1 1.5
Units per batch 500 1,000
Inspections per batch 4 1
What is the inspection cost per unit for product Alpha?
A. $23.81
B. $17.24
C. $71.43
D. $80.00
Alpha uses: 2500/500 x 4 = 20 inspections
Cost per cost driver – inspection: OH cost/No of inspections = 250,000/ (20 +
8) = $8,929
Cost asb to Alpha = (8,929 x 20)/2,500 = 71.43
4. The predicted selling price for a product has been set at $56 per unit. The
desired mark-up on cost is 25% and the material cost for the product is
estimated to be $16 before allowing for additional materials to allow for
shrinkage of 20% (for every 10 kg of material going in only 8 kg comes out). If
labour is the only other cost and 2 hours are needed what is the most the
business can pay per hour if a cost gap is to be avoided?
The maximum rate per hour is $ 12.4
Selling price 56
Mark up on cost 25% -> Profit 25% = 56 x 25/125 = 11.2 -> target cost = 44.8
DM = 16 x 10/8 = 20
DLB = 44.8 – 20 = 24.8 each unit used 2hrs -> rate per hr = 12.4
6. Skye Limited has a two process environment, and details of these processes
are as follows:
Process P: Each machine produces 6 units an hour and Skye has 8 machines
working at 90% capacity.
Process Q: Each machine produces 9 units per hour and Skye has 6 machines
working at 85% capacity.
One of Skye products is Cloud. Cloud is not particularly popular but does sell
at a selling price of $20 although discounts of 15% apply. Material costs are $5
and direct labour costs are double the material cost. Cloud spends 0.2 hours in
process P but 0.3 hours in process Q.
What is Cloud’s throughput per hour in its bottleneck process?
$ 60
Process P: 6 x 8 x 90% = 43,2
Process Q : 9 x 6 x 85% = 45,9
-> Process P is bottle neck
Return per factory hr = selling price – RM cost / number of hrs
Return per factory hr = (20 x 85% - 5)/0.2 = 60
1 22 1.00 0.75
2 22 0.75 1.00
3 18 1.00 0.50
A. Throughput accounting considers that the only variable costs in the short
run are materials and components.
B. Throughput accounting considers that time at a bottleneck resource has
value, not elsewhere.
C. Throughput accounting views stock building as a non-value-adding activity,
and therefore discourages it.
D. Throughput accounting was designed as a decision-making tool for
situations where there is a bottleneck in the production process.
Set-up 0.45
Inspection and testing 4.30
Total non-production costs $000
Design (salaries and technology) 2,500
Marketing consultants 1,700
Distribution 1,400
11. Which of the following statements would the finance director have
used to explain to Helot Co’s board what the benefits were of adopting a
target costing approach so early in the game’s life-cycle?
(1) Costs will be split into material, system, and delivery and disposal
categories for improved cost reduction analysis.
(2) Customer requirements for quality, cost and timescales are more likely to
be included in decisions on product development.
(3) Its key concept is based on how to turn material into sales as quickly as
possible in order to maximise net cash.
(4) The company will focus on designing out costs prior to production, rather
than cost control during live production.
12. What is the forecast cost gap for the new game?
A. $2.05
B. $0.00
C. $13.70
D. $29.25
Selling price = 45 Profit 35% -> cost 65% = 65% x 45 = 29.25
Current cost = variable cost 15,3 + allocated cost 16 = 31,3
Cost gap = 31,3 – 29,25 = 2.05
13. The board of Helot Co has asked the finance director to explain what
activities can be undertaken to close a cost gap on its computer games.
Which of the following would be appropriate ways for Helot Co to close a
cost gap?
(1) Buy cheaper, lower grade plastic for the game discs and cases.
(2) Using standard components wherever possible in production.
(3) Employ more trainee game designers on lower salaries.
(4) Use the company’s own online gaming websites for marketing.
A. (1), (2) and 3)
B. (1), (3) and (4)
C. (2) and (4)
D. (2) and (3) only
14. The direct labour cost per unit has been based on an expected
learning rate of 90% but now the finance director has realised that a
95% learning rate should be applied.
Which of the following statements is true?
A. The target cost will decrease and the cost gap will increase
B. The target cost will increase and the cost gap will decrease
C. The target cost will remain the same and the cost gap will increase
D. The target cost will remain the same and the cost gap will decrease