Notes Module 4
Notes Module 4
Network diagram
It is the flow of diagram consisting of activities and events connected logically and sequentially.
Majorly there have been two systems of networking in project management. These are
1 PERT
2 CPM
1 Activity-on-Arrow(A-O-A)
2 Activity-on-Node(A-O-N)
Elements of a network
EVENT:
10
Tail Event
The event which marks the completion of an activity is known as head event.
If this event represents completion of entire project then it is called finish event.
It has only incoming arrow.
10
All events except the first and the last event of the project are dual role event. They
have both incoming and outgoing arrows.
Successor Events:
The event or events that follows another event are called successor events to that
event.
Predecessor Events:
The event or events that occur before another event is called predecessor events.
ACTIVITY
Activity is defined as actual performance of job. It requires time and resources for its completion.
Dummy activity
A dummy is an activity that neither requires time and resources for its completion it just shows the
dependency of activities upon another activities.
There are certain rules for making the network, these are as follows.
This is based on deterministic approach in which only one time estimate is is made for activity
completion.
Example;
H E,I 22
I F 2
J F 12
The network diagram will be
C
A
G
B D
H
E
J
F
Paths are as follows
A-C-G = 5+8+8= 21
B-D-G= 4+8+8= 20
B-E-H = 4+8+22= 34 (This is the longest duration hence this will be the critical path).
B-F-J= 4+5+12= 21
B-F-I-H= 4+5+2+22= 33
PERT stands for Programme evaluation and review technique. It is an numerical technique and it is
generally used for the project where time cannot be estimated accurately such as research projects.
1 Optimistic time (to): This is the minimum possible time in which an activity can be completed
under the most ideal condition.
2 Pessimistic time (tp): This is the maximum time required for completing an activity under
worst possible condition.
3 Most Likely Time: This is the time require for completing an activity under normal working
condition.
The following table shows the job of a network along with their time estimates
5-8 3 3 9
7-8 8 17 32
Question 3) Calculate the earliest and latest occurrence for each event.
Question 3) Calculate the earliest and latest occurrence for each event.
Answer) At first the estimated is calculated using the formula provided above.
21
7 32
21
14 3 11
7 32
0 36
2 25
7 5
0 4 36
5 12 7
1 8
4
6 18 18
7
17
6
11
6 7
FLOAT
The float represents the time availability (cannot be negative). It is the range within which start or
finish time of an activity may fluctuate without affecting the project completion time.
1. Total float= Total float is the amount of time an activity in a project can be delayed without
delaying the project's completion date. It's also known as slack.
2. Free float= Additional time available.
3. Independent float.
Free float
5 10 EF
ES
5
4 9
LS 10 15 LF
From this figure it is understandable that 4, 9 are event. The floats can be calculated as follows.
Independent float= EF – D – LS
Free Float = EF – D – ES
PERT CPM
It is event oriented It is activity oriented
It has probabilistic approach It is an deterministic approach
Three types of time are estimated on the basis It is one time estimate
of whi9ch expected time is derived
Cost is directly proportional to time Time and cost are related by the given curve.
It is suitable for newer type product. It is used for repetitive type of work.
Example: Research work Example: Construction work.