C3-3 Shallow Foundation
C3-3 Shallow Foundation
Independent foundation
Real shot image
independent
strip
Shape and size
Raft
foundation box
Rigid
Properties of
materials
flexible
Strip foundations
Independent foundations
Box foundations
Raft foundations
Rigid foundation:
A rigid foundation is usually constructed from materials such as bricks, block stones,
rough stones, plain concrete, ternary soil, and lime soil, without the need for steel
reinforcement.
A rigid foundation can be used for civil buildings and masonry load-bearing factories
with six or fewer floors. Its characteristics are good stability, easy construction, and
the ability to withstand large loads. The main disadvantage is its self weight. When
the foundation bearing layer is soft soil, there are certain restrictions on expanding
the foundation area, and the foundation must be treated or reinforced before it can
be used.
For situations where the load is large or the upper structure is sensitive to settlement
differences, it is not suitable to use a rigid foundation as a shallow foundation when
the bearing layer is deep soft soil.
Brick foundation is the most widely used type of rigid foundation (as shown in Figure).
The dimensions of each part of the brick foundation should comply with the modulus of the brick.
Brick foundations are generally made in a stepped style, commonly known as "large footings".There
are two types of masonry methods: two layers and one interval (also known as two layers and one
interval).Two layers and one collection refers to laying two layers of bricks, which is 120mm, and
collecting 1/4 of the brick length, which is 60mm;Starting from the bottom layer, two layers of bricks
are laid with a length of 1/4 of the bricks, followed by another layer of bricks with a length of 1/4 of the
bricks. This process is repeated repeatedly.
The rubble foundation is built with unprocessed
stone and mortar, as shown in Figure.
Its advantages are easy to obtain materials locally,
low price, but high construction labor intensity.
Triple soil foundation is formed by mixing
a mixture of lime, sand, and aggregates (slag,
broken bricks, or crushed stones) with an
appropriate amount of water, and then laying
them layer by layer and compacting them in
the foundation trench, as shown in Figure
3.3.Triple soil foundation is commonly used in
civil construction projects with four or fewer
floors and lower groundwater levels in
southern China.
column
Vertical stripe
Horizontal base
stripe base
The raft foundation is similar to an inverted floor, with a large base area, which can reduce the
base pressure, improve the bearing capacity of the foundation soil, effectively enhance the overall
stiffness of the foundation, facilitate the adjustment of uneven settlement of the foundation, and
better adapt to changes in the load distribution of the upper structure.
Especially for buildings with basements or large liquid storage structures, such as water tanks, oil
depots, etc., raft foundations are an ideal foundation structure.
Raft foundation
When the load is large and the foundation soil is relatively weak, and the use of cross
shaped strip foundation cannot meet the requirements, raft foundation can be used.The raft
foundation is similar to an inverted floor, with a large base area, which can reduce the base
pressure, improve the bearing capacity of the foundation soil, effectively enhance the overall
stiffness of the foundation, facilitate the adjustment of uneven settlement of the foundation,
and better adapt to changes in the load distribution of the upper structure.Especially for
buildings with basements or large liquid storage structures, such as water tanks, oil depots,
etc., raft foundations are an ideal foundation structure.
beam
beam
column
slab
External wall
External wall
bottom slab internal wall
Construction of shallow buried rigid foundation
1. Brick foundation
a. Make a cushion layer
Underneath the large pedestal is
the foundation cushion layer. The
cushion layer is generally composed
of lime soil, crushed brick ternary
soil, or concrete.
b. Basic elastic line
Set up foundation poles and snap
lines at the corners, intersections,
and heights of the cushion layer.
C Brick foundation
Firstly, check the quality of the cushion layer and level it. During masonry, several
bricks can be laid at the corners and junctions according to the number of bricks,
and then the middle part can be laid with a straight line between them. The first
layer of bricks should be built based on the foundation bottom width line. The brick
foundation of the inner and outer walls should be built simultaneously. The large
foot section generally adopts a one in one masonry form.
D laying foundation moisture-proof layer When the bearing capacity of the
foundation is greater than or equal to 150kpa, an equal height large footing is
adopted, that is, two skins and one collection, with 1/4 brick length collected on each
side. If the bearing capacity of the foundation is less than 150kpa, unequal height
large footings are used, that is, two skin and one skin are spaced apart, with 1/4
brick length on each side.
Construction of shallow buried rigid foundation
2. Rubble foundation
Before laying the rubble foundation, remove any debris and compact the bottom. It is not
advisable to use mixed mortar. Cement mortar should be of M2.5~M5 grade. When laying the
first layer of rough stone, if the base is plain soil, mortar may not be laid; If the base is made of
various cushion layers, about 4cm of mortar should be laid first. A moisture-proof layer should
be installed 5cm below the indoor floor when the rubble is laid.
The daily masonry height should not exceed 1.2m. The top surface of the foundation is 100mm
wider than the wall on each side, and the height of each step is generally 300-400mm.
STEP TYPE trapezoid
rubble foundation
Construction of Shallow Buried Reinforced Concrete Foundation
independent foundation
Cleaning of foundation pits and leveling
Cleaning the foundation pit involves removing surface soil and disturbed soil, without
leaving any standing water. Leveling is to ensure that the elevation of the foundation bottom
meets the design requirements. Before constructing the foundation, the elevation of the
foundation bottom should be determined on the foundation surface.
Cushion construction
After the foundation trench inspection is completed, the cushion concrete construction
should be carried out immediately. C10 fine aggregate concrete cushion should be poured
on the foundation surface. The cushion concrete must be compacted and the surface
should be flat. It is strictly prohibited to air dry the foundation soil. The construction of
the cushion layer is to protect the steel bars of the foundation.
Positioning and laying out:
Use a total station to release all
the centerline and control lines of
independent foundations.
Reinforcement engineering
After the pouring of the cushion layer is completed and the concrete
reaches 1.2MPa, the surface should be marked with a line to tie the
steel bars. The steel bars should not be missed during binding.
Template engineering (formwork)
The template adopts small steel or wooden formwork, and is reinforced
with scaffolding pipes or wooden blocks.The stepped independent
foundation is made according to the dimensions of the foundation
construction drawing, and each step template is installed layer by layer
from bottom to top in the order of formwork support.
Concrete casting
Concrete should be layered continuously, with an interval time not exceeding the initial setting time of
the concrete, generally not exceeding 2 hours. To ensure the correct position of the steel bars, a layer of
5-10cm thick concrete should be poured first to fix the steel bars. Each step height of the stepped
foundation is poured and compacted as a whole. After each step is poured, pause for 0.5 hours until it
sinks, and then pour another layer.
Concrete leveling
After pouring concrete, use a flat vibrator to vibrate the concrete with a relatively
large surface, then use a scraper to scrape it flat, and then use a wooden trowel to
smooth it out. Before receiving, the elevation of the concrete surface must be checked,
and any areas that do not meet the requirements must be rectified immediately.
Concrete curing
The poured concrete should be covered and watered within about 12 hours. General
room temperature curing shall not be less than 7 days, and special concrete curing
shall not be less than 14 days.A dedicated person shall be appointed to inspect and
implement the maintenance to prevent surface cracks on the concrete caused by
untimely maintenance.
Construction of Shallow Buried Reinforced Concrete Foundation
Construction points:
① After the groove inspection, the cushion layer concrete should be poured
immediately to protect the base. The cushion layer concrete should be
vibrated with a surface vibrator, and the surface should be flat.
② After the cushion layer reaches a certain strength, snap lines, support
formwork, tie steel bars on the cushion layer, and ensure that the steel bar
protection layer meets the requirements.
③ Before pouring concrete, remove debris and wet the formwork.
④ The foundation concrete should be poured continuously in layers.
⑤ When there are reinforcing bars on the foundation, it should be ensured
that the position of the reinforcing bars is correct.
Construction of Shallow Buried Reinforced Concrete Foundation
raft foundation