12 m3/person/day
10.8 m3/person/day
1.5 m3/person/day
2.5 m3/person/day
1.5 m3/person/day
1.1 m2/person/day
25 m2/8Dl/mason 8 16 24
46.25 m2/10Dl/mason 10 20 30
2,765 m2/10Dl/mason 10 20 30
1.5 m2/8Dl/mason 8 16 24
2.07 m3/10Dl/mason 10 20 30
1,125 m3/8Dl/mason 8 16 24
3,245 m3/10Dl/mason 10 20 30
1,754 m3/8Dl/mason 8 16 24
2,433 m3/10Dl/mason 10 20 30
1.22 m3/8Dl/mason 8 16 24
4.42 m3/10Dl/mason 10 20 30
3,367 m3/10Dl/mason 10 20 30
2,366 m3/8Dl/mason 8 16 24
1.82 m3/10Dl/mason 10 20 30
2,525 m3/10Dl/mason 8 16 24
1.22 m3/8Dl/mason 8 16 24
2 m3/8Dl/mason
4 m3/4Dl/mason 4 8 12
1.2 m3/4Dl/mason 4 8 12
1.3 m3/4Dl/mason 4 8 12
0.975 m3/4Dl/mason 4 8 12
0.85 m3/4Dl/mason 4 8 12
1.1 m3/4Dl/mason 4 8 12
0.825 m3/4Dl/mason 4 8 12
3.6 m3/2Dl/mason 4 8 12
2 m3/4Dl/mason 4 8 12
4 m3/4Dl/mason 4 8 12
16 m2/2dl/2plasterer 2
14 m2/2dl/plasterer 2
24 m2/2dl/plasterer 2
3 3pcs/2Dl/carpenter
16 16pcs/8Dl/carpenter
69.12 m2/2Dl/Carpenter 2 4 6
42.16 m2/2Dl/Carpenter 2 4 6
8 m2/2Dl/Carpenter 2 4 6
8.5 m2/2Dl/Carpenter 2 4 6
List of Manpower and Indexed Cost List of Equipm
Daily Indexed
NO Description No
payment Cost (Birr)
1 Crafts Men 1
1 .1 Carpenter II 400 50 1.1
1 .2 Carpenter I 360 45 1.2
1 .3 Carpenter helper 160 20 1.3
1 .4 Mason II 400 50 1.4
1 .5 Mason I 360 45 1.5
1 .6 Mason helper 160 20 1.6
1 .7 Bar bender II 320 40 1.7
1 .8 Bar bender I 280 35 1.8
1 .9 Bar bender helper 160 20 1.9
1 .10 Bar Setter I 140 17.5 1 . 10
1 .11 Water proofer I 400 50 1 . 11
1 .12 Water proofer helper 160 20 1 . 12
1 .13 Welder 320 40 1 . 13
1 .14 Welder helper 160 20 1 . 14
1 .15 Chiseller II 360 45 1 . 15
1 .16 Chiseller I 240 30 2
1 .17 Glazer 320 40 2.1
1 .18 Tiller II 440 55 2.2
1 .19 Tiller I 400 50 2.3
1 .20 Tiller helper 160 20 2.4
1 .21 Painter III 480 60 2.5
1 .22 Painter II 320 40 3
1 .23 Painter I 280 35 3.1
1 .24 Painter helper 160 20 3.2
1 .25 Brick layer 440 55 4
1 .26 Gang chief 200 25 4.1
1 .27 Plasterer II 360 45 4.2
1 .28 Plasterer I 320 40 4.3
1 .29 Plasterer 280 35 4.4
1 .30 Plasterer helper 160 20 4.5
1 .31 Plumber II 440 55 4.6
1 .32 Plumber I 400 50 4.7
1 .33 Plumber helper 160 20 4.8
1 .34 Electrician II 40 5 5
1 .35 Electrician I 400 50 5.1
1 .36 Electrician helper 240 30 5.2
1 .37 Grease boy 200 25 5.3
1 .38 Driller 400 50 5.4
1 .39 Polisher 400 50 5.5
1 .40 clerk 8 1 5.6
1.41 Powderman 8 1 5.7
1.42 Explosive expert 8 1 5.8
1.43 Service man 8 1 5.9
1.44 Material Deliverer 8 1 6
1.45 Mechanic 8 1 6.1
1.46 Electrician 8 1 6.2
1.47 Senior Mechanic 8 1 6.3
1.48 Senior Electrician 8 1 7
1.49 Plant Electrician 8 1 7.1
1.50 Asphalt Melting unit 8 1 7.2
1.51 Greasing and oiling 8 1 7.3
1.52 Material receiver&del 8 1 7.4
2 Non-Skilled Manpower 7.5
2 .1 DL I 250 31.25 7.6
2 .2 DL II (Gang leaders) 200 25 7.7
2 .3 Sledge Hammer man 240 30 7.8
3 Supervisors 7.9
3 .1 Assistant Foreman 1213.44 151.68 7 . 10
3 .2 Barbender Foreman 1213.44 151.68 7. 11
3 .3 Batch Plant forman 8 1 7. 12
3 .4 Blasting Foreman III 2103.04 262.88 7. 13
3 .5 Blasting Forman 640 80 7. 14
3 .6 Carpenter Foreman III 2103.04 262.88 8
3 .7 Chief Surveyor 2426.88 303.36 8.1
3 .8 Const. Forman (road general) 640 80 8.2
3 .9 Construction Engineer 4853.76 606.72 8.3
3.10 Earthwork Foreman 1213.44 151.68
3.11 Earthwork Superintendent 2831.36 353.92
3.12 Forman (Bldg.) 300 37.5
3.13 Gang Chief 170 21.25
3.14 Material Engineer 4853.76 606.72
3.15 Material Superintendent 2426.88 303.36
3.16 Plant Superintendent 3235.85 404.48125
3.17 Project Engineer 4853.76 606.72
3.18 Project Manager 5662.72 707.84
3.19 Quarry Forman II 1213.44 151.68
3.20 Quary Foreman III 1213.44 151.68
3.21 Road Foreman III 2426.88 303.36
3.22 Structural Engineer 4853.76 606.72
3.23 Structural Foreman III 2103.04 262.88
3.24 Structural Superintendent 2831.36 353.92
4 Technicians
4 .1 Surveyor III 2022.4 252.8
4 .2 Surveyor II 1860.48 232.56
4 .3 Surveyor I 1648 206
4 .4 Chain Man 566.4 70.8
4 .5 Rod Man 485.12 60.64
4 .6 Soil Technicain 1860.48 232.56
4 .7 Quantity Surveyor 1860.48 232.56
4 .8 Draftsman 1860.48 232.56
5 Operators and Drivers
5 .1 Dozer operator 720 90
5 .2 low bed driver 0 0
5 .3 C.T.Operator 0 0
5 .4 Equipment operator III 480 60
5 .5 Equipment operator II 440 55
5 .6 Equipment operator I 360 45
5 .7 Truck Driver 400 50
5 .8 Truck Driver I 400 50
5 .9 Grader Operator 8 1
5 .10 Roller Operator 8 1
5 .11 W. Tr Oper. 8 1
5 .12 Excavator Operator 8 1
5 .13 Loader Operator 8 1
5 .14 Dump truck Driver 8 1
5 .15 Air Comp. Oper. 8 1
5 .16 W.T. Operator 8 1
5 .17 Wagon drill op 8 1
5 .18 Crusher op II 8 1
5 .19 Crusher op I 8 1
5 .20 Asp. Dist. Operator 8 1
5 .21 Grinder operator 280 35
5 .22 Sta.Equip. Oper. 8 1
5 .23 Paver Operator 8 1
5 .24 Light vehicle Driver 8 1
5 .25 mixer operator 280 35
5 .26 vibrator operator 200 25
5 .27 Crane operator 480 60
5 .28 Stat. Equip. Oper. I 8 1
5 .29 P.R. Operator 8 1
5 .30 S.R. Operator 8 1
5 .31 Sta.Eq.Ope.II 8 1
Description
(exc., carpentry, finishing)
(metal work, sanitary and electric
(painting)
Building
A. Sub Structure
Labor intensive
Labor
Unit output/day
Labor trade Name No UF
Excavation and
1
Earth Work
Daily labor I 10 1
Clearing of 20 cm thick
1.1 m2 100 Gang chif 1 1
top organic soil
Forman(Bldg) 1 0.5
Bulk excavation in Daily labor I 2 1
1.2 ordinary soil to a depth m3 3 Gang chief 1 1
< 1.5m Forman(Bldg) 1 0.5
Bulk excavation in Gang chief 1 0.5
1.3 ordinary soil to a depth m3 2.6 Forman(Bldg) 1 0.04
1.5m< x <3 m Daily labor I 2 1
1 0.5
Bulk excavation in Gang chief
1.4 m3 2.3
ordinary soil to a depth Forman(Bldg) 1 0.04
3m< x <4.5 Daily labor I 2 1
Bulk excavation in soft Gang chief 1 0.5
1.5 soil or sand to a depth m3 3.6 Forman(Bldg) 1 0.04
< 1.5m Daily labor I 2 1
Bulk excavation in soft Gang chief 1 0.5
1.6 soil or sand to a depth m3 3.12 Forman(Bldg) 1 0.04
1.5m< x <3m Daily labor I 2 1
Bulk excavation in soft Gang chief 1 0.5
1.7 soil or sand to a depth m3 2.76 Forman(Bldg) 1 0.04
3m< x < m3 Daily labor I 2 1
Bulk excavation in Gang chief 1 0.5
1.8 heavy soil or stiff clay m3 2.4 Forman(Bldg) 1 0.04
<1.5m Daily labor I 2 1
Bulk excavation in Gang chief 1 0.5
1.9 heavy soil or stiff clay m3 2.08 Forman(Bldg) 1 0.04
1.5m< x <3m Daily labor I 2 1
Bulk excavation in Gang chief 1 0.5
1.1.0 heavy soil or stiff clay m3 1.84 Forman(Bldg) 1 0.04
3m< x <4.5 Daily labor I 2 1
Gang chief 1 0.5
Bulk excavation for wet
1.11 m3 2.1 Forman(Bldg) 1 0.04
excavation < 1.5m
Daily labor I 2 1
Bulk excavation for wet Gang chief 1 0.5
1.12 excavation 1.5m< x m3 1.82 Forman(Bldg) 1 0.04
<3m
Bulk excavation for wet
1.12 excavation 1.5m< x m3 1.82
<3m Daily labor I 2 1
Bulk excavation for wet Gang chief 1 0.5
1.13 excavation 3m< x m3 1.61 Forman(Bldg) 1 0.04
<4.5m Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.14 ordinary soil to a depth m3 2.7 Forman(Bldg) 1 0.04
< 1.5m Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.15 ordinary soil to a depth m3 2.2 Forman(Bldg) 1 0.04
of 1.5m<X<3m Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.16 ordinary soil to a depth m3 1.6 Forman(Bldg) 1 0.04
of 3m < x 4.5 Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.17 soft soil or sand to a m3 3.24 Forman(Bldg) 1 0.04
depth < 1.5 Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.18 soft soil or sand to a m3 2.64 Forman(Bldg) 1 0.04
depth 1.5m<3m Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.19 soft soil or sand to a m3 1.92 Forman(Bldg) 1 0.04
depth 3m< x 4.5 Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.2.0 heavy soil or stiff clay m3 2.16 Forman(Bldg) 1 0.04
<1.5m Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.21 heavy soil or stiff clay m3 1.76 Forman(Bldg) 1 0.04
1.5m< x < 3m Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.22 heavy soil or stiff clay m3 1.28 Forman(Bldg) 1 0.04
3m< x <4.5 Daily labor I 2 1
Gang chief 1 0.5
Trench excavation for
1.23 m3 1.89 Forman(Bldg) 1 0.04
wet excavation < 1.5m
Daily labor I 2 1
Trench excavation for Gang chief 1 0.5
1.24 wet excavation 1.5m< x m3 1.54 Forman(Bldg) 1 0.04
<3m Daily labor I 2 1
Trench excavation for Gang chief 1 0.5
1.25 wet excavation 3m< x m3 1.12 Forman(Bldg) 1 0.04
<4.5m Daily labor I 2 1
Pit excavation in Gang chief 1 0.5
1.26 ordinary soil not m3 2.7 Forman(Bldg) 1 0.04
exceeding 150cm Daily labor I 2 1
Pit excavation in Gang chief 1 0.5
ordinary soil to the
1.27 m3 2.2 Forman(Bldg) 1 0.04
depth of 150cm < x
1.27 m3 2.2
depth of 150cm < x
300cm Daily labor I 2 1
Pit excavation in Gang chief 1 0.5
ordinary soil to the
1.28 m3 1.6 Forman(Bldg) 1 0.04
depth of 300cm < x <
450cm Daily labor I 2 1
Pit excavation in soft Gang chief 1 0.5
1.29 soil or sand to a depth m3 3.24 Forman(Bldg) 1 0.04
< 1.5m Daily labor I 2 1
Pit excavation in soft Gang chief 1 0.5
1.3.0 soil or sand to a depth m3 2.64 Forman(Bldg) 1 0.04
1.5m< x <3 Daily labor I 2 1
Gang chief 1 0.5
Pit excavation in heavy
1.31 m3 1.92 Forman(Bldg) 1 0.04
soil or stiff clay <1.5m
Daily labor I 2 1
Trench excavation in Gang chief 1 0.5
1.32 ordinary soil to a depth m3 2.16 Forman(Bldg) 1 0.04
< 1.5m Daily labor I 2 1
Pit excavation in heavy Gang chief 1 0.5
1.33 soil or stiff clay 1.5m< x m3 1.76 Forman(Bldg) 1 0.04
<3m Daily labor I 2 1
Pit excavation in heavy Gang chief 1 0.5
1.34 soil or stiff clay 3m< x m3 1.28 Forman(Bldg) 1 0.04
<4.5m Daily labor I 2 1
Gang chief 1 0.5
Pit excavation for wet
1.35 m3 1.89 Forman(Bldg) 1 0.04
excavation < 1.5m
Daily labor I 2 1
Pit excavation for wet Gang chief 1 0.5
1.36 excavation 1.5m< x m3 1.54 Forman(Bldg) 1 0.04
<3m Daily labor I 2 1
Pit excavation for wet Gang chief 1 0.5
1.37 excavation 3m< x m3 1.12 Forman(Bldg) 1 0.04
<4.5m Daily labor I 2 1
Bulk excavation in soft Gang chief 1 0.25
1.38 rock to a depth not m3 1.8 Forman(Bldg) 1 0.04
exceeding 1m Daily labor I 3 1
Bulk excavation in soft Gang chief 1 0.25
1.39 rock to a depth 1.5m< x m3 1.6 Forman(Bldg) 1 0.04
<3.0m Daily labor I 3 1
Bulk excavation in soft Gang chief 1 0.25
1.4.0 rock to a depth 3m < x m3 1.3 Forman(Bldg) 1 0.04
< 4.5m Daily labor I 3 1
Trench excavation in Gang chief 1 0.25
1.41 soft rock not exceeding m3 1.5 Forman(Bldg) 1 0.04
150cm Daily labor I 3 1
Trench excavation in Gang chief 1 0.25
1.42 soft rock to the depth of m3 1.2 Forman(Bldg) 1 0.04
150cm < 300cm
Trench excavation in
1.42 soft rock to the depth of m3 1.2
150cm < 300cm Daily labor I 3 1
Trench excavation in Gang chief 1 0.25
1.43 soft rock to the depth of m3 1 Forman(Bldg) 1 0.04
300cm < Daily labor I 3 1
Gang chief 1 0.25
Pit excavation soft rock
1.44 m3 1.5 Forman(Bldg) 1 0.04
not exceeding 150cm
Daily labor I 3 1
Pit excavation soft rock Gang chief 1 0.25
1.45 to the depth of 150cm < m3 1.2 Forman(Bldg) 1 0.04
x < 30 Daily labor I 3 1
Pit excavation soft rock Gang chief 1 0.25
1.46 to the depth of 300cm < m3 1 Forman(Bldg) 1 0.04
x < 450 Daily labor I 3 1
Bulk excavation in hard Gang chief 1 0.25
1.47 rock to a depth not m3 1 Forman(Bldg) 1 0.04
exceeding 1 Daily labor I 3 1
Bulk excavation in hard Gang chief 1 0.25
1.48 rock to a depth 1.5m< x m3 0.8 Forman(Bldg) 1 0.04
<3.0m Daily labor I 3 1
Bulk excavation in hard Gang chief 1 0.25
1.49 rock to a depth 3m < x m3 0.5 Forman(Bldg) 1 0.04
< 4.5m Daily labor I 3 1
Trench excavation in Gang chief 1 0.25
1.5.0 hard rock not exceeding m3 0.7 Forman(Bldg) 1 0.04
150cm. Daily labor I 3 1
Trench excavation in Gang chief 1 0.25
1.51 hard rock to the depth m3 0.5 Forman(Bldg) 1 0.04
of 150cm <300cm Daily labor I 3 1
Trench excavation in Gang chief 1 0.25
1.52 hard rock to the depth m3 0.3 Forman(Bldg) 1 0.04
of 300cm < Daily labor I 3 1
Pit excavation in hard Gang chief 1 0.25
1.53 rock not exceeding m3 0.7 Forman(Bldg) 1 0.04
150cm Daily labor I 3 1
Pit excavation in hard Gang chief 1 0.25
1.54 rock to the depth of m3 0.5 Forman(Bldg) 1 0.04
150cm < x <300cm Daily labor I 3 1
Pit excavation in hard Gang chief 1 0.25
1.55 rock to the depth of m3 0.3 Forman(Bldg) 1 0.04
300cm < x < Daily labor I 3 1
Trench excavation in
1.56 m3
rock under 1000 m3
Trench excavation in
1.57 m3
rock over 1000 m3
Trench excavation in
1.57 m3
rock over 1000 m3
Trench excavation in
1.58 m3
boulder to a depth 1.5m
Trench excavation in
1.59 boulder to a depth m3
1.5m<
Trench xexcavation
<3m in
1.6.0 boulder to a depth 3m< m3
x <4.5m
Pit excavation in
1.61 m3
boulder to a depth 1.5m
Pit excavation in
1.62 boulder to a depth m3
1.5m< x <3m in
Pit excavation
1.63 boulder to a depth 3m< m3
x <4.5m
Bulk excavation in
1.64 m3
boulder to a depth 1.5m
Bulk excavation in
1.65 boulder to a depth m3
1.5m< x <3m in
Bulk excavation
1.66 boulder to a depth 3m< m3
x <4.5m
Back fill around footing Gang chief 1 0.1
1.67 and masonry foundation m3 3 Forman(Bldg) 1 0.04
from t Daily labor I 3 1
Fill around footing and Gang chief 1 0.1
1.68 masonry foundation m3 3 Forman(Bldg) 1 0.04
from the sit Daily labor I 1 1
Gang chief 1 0.1
Back fill Under hard
1.69 m3 84 Forman(Bldg) 1 0.04
core from site
Daily labor I 1 1
Gang chief 1 0.1
Fill Under hard core
1.7.0 m3 84 Forman(Bldg) 1 0.04
from borrow
Daily labor I 1 1
Hauling surplus Gang chief 1 0.1
1.71 excavated material 2km m3 65.1 Forman(Bldg) 1 0.04
away Daily labor I 1 1
Hauling surplus Gang chief 1 0.1
1.72 excavated material 4km m3 51.8 Forman(Bldg) 1 0.04
away Daily labor I 1 1
Hauling surplus Gang chief 1 0.1
1.73 excavated material 6km m3 51.8 Forman(Bldg) 1 0.04
away Daily labor I 1 1
Hauling surplus Gang chief 1 0.1
1.74 excavated material 8km m3 44.1 Forman(Bldg) 1 0.04
away
Hauling surplus
1.74 excavated material 8km m3 44.1
away Daily labor I 1 1
Gang chief 1 0.1
Hand loading from
1.75 m3 5.4 Forman(Bldg) 1 0.04
stock pile, clay
Daily labor I 1 1
DL II (Gang leaders) 4 1
1.76 25cm thick hard core m3 14
Mason II 1 0.25
DL II (Gang leaders) 4 1
1.77 15cm thick hard core m3 14
Mason II 1 0.25
30-50 mm thick DL II (Gang leaders) 4 1
1.78 m3 48
blinding. Mason II 1 0.25
2 Concrete Work
Daily labor I 18 1
Bar bender I 1 0.25
Plasterer I 2 1
2.1 Light weight concrete m3 12 Vibrator operator 1 1
Mixer operator 1 1
Carpenter I 1 0.25
Forman (Bldg.) 1 0.5
Daily labor I 18 1
5cm thick C-5 lean Mixer operator 2 1
2.2 concrete (mechanical m3 240 Vibrator operator 1 1
mix) Carpenter I 1 0.25
Forman (Bldg.) 1 0.5
Daily labor I 18 1
Vibrator operator 1 1
Mixer operator 1 1
2.3 Other concrete grade m3 Plasterer I 2 1
Bar bender I 1 0.25
Carpenter I 1 0.25
Forman (Bldg.) 1 0.5
Bar bender helper 2 1
Bar bender I 1 1
2.4 Reinforcement bar m3
Bar bender II 1 1
Forman (Bldg.) 1 0.25
2.5 Formwork
Capenter helper 2 1
Footing, Mat foundation 1 1
A m2 Carpenter I
and Grade beam
Forman (Bldg.) 1 0.25
Capenter helper 2 1
Concrete shear wall and 1 1
B m2 Carpenter I
lift shaft
Concrete shear wall and
B m2
lift shaft
1 0.25
Forman (Bldg.)
Capenter helper 2 1
Zigba form work for
C m2 Carpenter I 1 1
foundation column
Forman (Bldg.) 1 0.25
Capenter helper 2 1
Zigba form work for
D suspended and ribbed m2 1 1
Carpenter I
slab
Forman (Bldg.) 1 0.25
Concrete Ancillary
2.6
Work
Expansion joint of width DL II (Gang leaders) 1 1
A 10cm with chipwood m2 Carpenter II 1 1
8mm thic
Expansion joint of width DL II (Gang leaders) 1 1
B 20cm with chipwood m2 Carpenter II 1 1
8mm thick
Expansion joint of width DL II (Gang leaders) 1 1
C 40cm with chipwood m3 Carpenter II 1 1
8mm thick
3 Masonry Work
Daily labor I 4 1
40 cm thick Stone 2 1
Mason II
3.1 foundation masonry 5.5
(1:4) Cement s Forman(Bldg.) 1 0.25
Daily labor I 4 1
50 cm thick Stone
Mason II 2 1
3.2 foundation masonry
(1:4) Cement s Forman(Bldg.) 1 0.25
Daily labor I 4 1
60 cm thick Stone Mason II 2 1
3.3 foundation masonry
(1:4) Cement s Forman(Bldg.) 1 0.25
Daily labor I 4 1
40 cm thick Semi Mason II 2 1
3.4 dressed stone masonry
foundation wall Forman(Bldg.) 1 0.25
40 cm thick Semi
3.4 dressed stone masonry
foundation wall
Daily labor I 4 1
50 cm thick Semi
Mason II 2 1
3.5 dressed stone masonry
foundation wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
60 cm thick Semi
Mason II 2 1
3.6 dressed stone masonry
foundation wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
50 cm thick Both side
Mason II 2 1
3.7 dressed Kotebe stone
masonry Elev. Wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
50 cm thick one side Mason II 2 1
3.8 dressed Kotebe stone
masonry Elev. Wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
25 cm thick dressed Mason II 2 1
3.9 Kotebe stone masonry
cladding Elev. Wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
50 cm thick Both side Mason II 2 1
3.1.0 dressed Ambo stone
masonry Elev. Wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
50 cm thick one side
Mason II 2 1
3.11 dressed Ambo stone
masonry Elev. Wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
25 cm thick dressed Mason II 2 1
3.12 Ambo stone masonry
cladding Elev. Wall Forman(Bldg.) 1 0.25
Daily labor I 4 1
Dressed Kebena stone Mason II 2 1
3.13 masonry cladding Elev.
wall Forman(Bldg.) 1 0.25
B Super Structure
4 Concrete Work
4.1 Ribbed slab
Labor intensive Machin intensive
Equipemet Labor
Quantity
Equipement name UF Labor trade Name output/day No UF
Sledge hammer 1 1
Hand tool set 1 2 0.8 1.6
Sledge hammer 1 1
Hand tool set 1 2 0.8 1.3
Sledge hammer 1 1
Hand tool set 1 2 0.8 1.5
Sledge hammer 1 1
Hand tool set 1 2 0.8 1.2
1.2
Sledge hammer 1 1
Hand tool set 1 2 0.8 1
Sledge hammer 1 1
Hand tool set 1 2 0.8 1.5
Sledge hammer 1 1
Hand tool set 1 2 0.8 1.2
Sledge hammer 1 1
Hand tool set 1 2 0.8 1
Sledge hammer 1 1
Hand tool set 1 2 0.8 1
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.8
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.5
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.7
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.5
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.3
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.7
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.5
Sledge hammer 1 1
Hand tool set 1 2 0.8 0.3
Forman(Bldg) 1 0.5
Equipment operator III 41 1 1
Driller 1 1
Blasting Forman 1 1
Forman(Bldg) 1 0.5
48
Equipment operator III 1 1
Driller 48 1 1
Blasting Forman 1 1
Forman (Bldg.) 1
250 1
Equipment operator III 2 1
Forman (Bldg.) 1 1
175
Equipment operator III 2 1
Forman (Bldg.) 1 1
115
Equipment operator III 2 1
Forman (Bldg.) 1 1
250
Equipment operator III 2 1
Forman (Bldg.) 1 1
175
Equipment operator III 2 1
Forman (Bldg.) 1 1
115
Equipment operator III 2 1
Forman (Bldg.) 1 1
250
Equipment operator III 2 1
Forman (Bldg.) 1 1
185
Equipment operator III 2 1
Forman (Bldg.) 1 1
140
Equipment operator III 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Hand Compactor 1 1
Hand tool set 1 2 1
Sledge hammer 1 1
Hand Tools Set 1 4 1
Sledge hammer 1 1
Hand Tools Set 1 4 1
Hand Tools Set 1 2 1
Vibrator 1 1
Mixer 1 1 Note…. Materials are 1,
Aggregate size 20cm, 2, Pumice
3, Sand
4, Cement
5, Water
Excavator0.57m3 1 1
Excavator0.57m3 1 1
Excavator0.57m3 1 1
Excavator0.57m3 1 1
Excavator0.57m4 1 1
Excavator0.57m5 1 1
Excavator0.57m6 1 1
Excavator0.57m7 1 1
Excavator0.57m8 1 1
Excavator0.57m9 1 1
Excavator0.57m10 1 1
Excavator0.57m11 1 1
Excavator0.57m12 1 1
Excavator0.57m13 1 1
Excavator0.57m14 1 1
Excavator0.57m15 1 1
Excavator0.57m16 1 1
Excavator0.57m17 1 1
Excavator0.57m18 1 1
Excavator0.57m19 1 1
Excavator0.57m20 1 1
Excavator0.57m21 1 1
Excavator0.57m22 1 1
Excavator0.57m23 1 1
Excavator0.57m24 1 1
Excavator0.57m25 1 1
Excavator0.57m26 1 1
Excavator0.57m27 1 1
Excavator0.57m28 1 1
Excavator0.57m29 1 1
Excavator0.57m30 1 1
Excavator0.57m31 1 1
Excavator0.57m32 1 1
Excavator0.57m33 1 1
Excavator0.57m34 1 1
Excavator0.57m35 1 1
Air Compressor 1 1
Drill 4inch(crawler) 1 1
Air Compressor 1 1
Drill 4inch(crawler) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Excavator (1m3) 1 1
Dozer (D8) 1 1
Basic Material Prices
Transpo
Source rt cost
Type of Materials Unit (Per
Place
Unit/km)
1. Cement
Cement -Muger Qtls Mugher 0.80
Cement - OPC Mugar Qtls Mugher 0.50
Cement - PPC Mugar Qtls Mugher 1.00
Cement - PPC Mesebo Qtls Mesebo 1.00
Cement - OPC Mesebo Qtls Mesebo 1.00
Cement - PPC Derba Qtls Derba 1.00
Cement - OPC Derba Qtls Derba 1.00
Cement - PPC Dangote Qtls Dangote 1.00
Cement - PPC Ethio Qtls Ethio 1.00
Cement - PPC Habesha Qtls Habesha 1.00
Cement - OPC Dangote Qtls Dangote 1.00
2. Aggrigate course and fine
Sand (hauling distance less than 5km in Addis Ababa) m3 0.5
Sand (hauling distance more than 5km in Addis Ababa m3 0.5
Gravel (02) Material Price at Crusher Site m3 0.5
Fino (00) material price at crusher site m3 0.5
3. Reinfercement bar
Reinforcement Bar -Ethiopia: 6mm kg 0.2
Reinforcement Bar - Ethiopia: 8mm kg 0.2
Reinforcement Bar Ethiopia: 10mm kg 0.2
Reinforcement Bar -Ethiopia: 12mm kg 0.2
Reinforcement Bar -Ethiopia: 14mm kg 0.2
Reinforcement Bar -Ethiopia: 16mm kg 0.2
Reinforcement Bar -Ethiopia: 20mm kg 0.2
Reinforcement Bar(Ethiopia): 24mm kg 0.2
Reinforcement Bar -Ethiopia: 30mm kg 0.2
Reinforcement Bar (Ethiopia): 32mm kg 0.2
Black annealed wire -1.5mm kg 0.2
4. Roof
G-32 C.I.Sheet roof cover m2 0.2
G-30 C.I.Sheet roof cover m2 0.2
G-28 C.I.Sheet roof cover m2 0.2
0.30 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.35 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.40 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.50 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.60 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.70 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.80 mm thick Galvanized EGA 300 roof cover. m2 0.2
1.00 mm thick Galvanized EGA 300 roof cover. m2 0.2
0.30 mm thick Galvanized EGA 500 roof cover. m2 0.2
0.35 mm thick Galvanized EGA 500 roof cover. m2 0.2
0.40 mm thick Galvanized EGA 500 roof cover. m2 0.2
0.50 mm thick Galvanized EGA 500 roof cover. m2 0.2
0.60 mm thick Galvanized EGA 500 roof cover. m2 0.2
0.70 mm thick Galvanized EGA 500 roof cover. m2 0.2
5. Other
Cylinderical lock pc A.A 0.0002
Flat sheet metal(1mm thick) m 2
A.A 0.0149
0.8MM thick ribbed sheet m2 A.A 0.0149
RHS(20*10*1mm)(Grill) kg A.A 0.0019
Screw for hinges (100 pcs.) packet A.A 0.0019
Electrode ( 2.5 mm ) -100Pcs packet A.A 0.0019
Anchor ( iron mongery ) pcs A.A 0.0019
Plastic Paint lit A.A 0.0005
Plastic Paint gal A.A 0.0076
Anti rust lit A.A 0.0019
Anti rust Gal A.A 0.0076
Material Prices
Transporta
Distanc tion Cost Loadin Total
Material
e from (From g /Un- costLinked
cost at Date Remark
site(K source to loading to Break
Source site) - Birr costs
m) Down
Per Unit
8
5
8
5
10
8
5
10
5
10
8
5
8
5
145
10
8
5
8
5
2
-1
24
20
22
20
5
24
20
22
20
5
24
20
22
20
5
24
22
5
24
22
5
24
20
5
24
20
5
24
21
5
24
21
5
24
21
5
24
22
5
22
21
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
20
27
5
24
22
20
27
5
24
22
20
27
5
24
22
20
27
24
22
20
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
22
5
24
21
5
40
13
24
21
5
24
21
5
40
15
24
21
5
24
21
5
24
21
5
24
21
5
26
5
25
24
5
18
25
24
5
25
24
5
25
24
5
25
24
5
40
35
8
20
40
35
8
20
24
5
24
5
24
5
24
5
INTRODUCTION
The basic cost elements incorporated in each unit cost are mainly grouped in Dire
costs .
Material cost : - This cost includes material , transportation , sales , & insuranc
Here all building materials are listed and it is suggested that pur
costs should be collected and listed at list once or twice in a yea
Also an expensive or aboundetly used types of building materials sh
be identified and / or short listed in order to know their market p
list four times in a year .
In the determination of this cost different factors witch affect the
quantity of materials like shrinkage , wastage , void spaces , denis
concrete qualities and WCR are also considered .
Labour cost : - Crew formation and production outputs are basic parameters in
rmination of this labour cost . The type of construction activities d
wether conditions & distances are measure factors that affects thi
Crews directly involved in the construction activities are mainly gr
Skilled & Un - skilled labourers .
- Skilled labourers are : - Office & Site engineers , Formen , Mas
Carpenters , Painters , Plumbers , Electricians , Welders , Mac
operators , Chislers , Plasterers , Decorators , etc .
- Un - skilled labourers are : - Helpers , Daily labourers , etc .
Overhead cost : - This cost includes costs of temporary office & store buildings c
at the construction sites , depreciation of office equipments & fur
water , lightning , telephone , & postage charges , costs of tools
ladders , scaffolds , buckets , facades , hoes , water hoses , barr
etc .
The total sum of the above expences are called the overhead cos
project and this is distributed among different items of the constr
activities . Most likely it is estimated to be some percentage of t
rial and labour costs in which it depends up on the type of proj
or grade of contractors . For more informetion refer table No. 1
GRADE OF
CONTRACTORS
Grade 1
Grade 2
Grade 3
Grade 4
Grade 5 - 10
Percentage of Overhead & Profit costs
Dimention
Timizing Squaring Discription
(LXWXD)
A.SUB STRUCTURE
1.EXCAVATION & EARTH WORK
1.01. Clear & Remove top soil
Site clearing with depth 20cm
1 9.4 L=7.65M, W=6.65M, D=0.2M
8.4
78.96 m2…………………………………………..Total site clearance
1.02 Bulk excavation
1 9.4 Bulck excavation with depth 50cm
8.4 with working space 1 m
0.5
39.48 m3……………………………………..Total bulck excavation
1.03 pit excavation
4 2.4 Pitch excavation with a depth of 2.95m
2.4 from OGL
2.25
51.84 m3………………………………………….Total pit excavation
1.04 Trench excavation
2 3.6 On axis 1 & 2
1 with working space 0.25m
0.2 depth of 0.9m from OGL
1.44
2 2.6 On axis A & B
1 with working space 0.25m
0.2 depth of 0.9m from OGL
1.04
2.48 m3………...…………………………...Total trench excavation
93.8 M3…………………….Total excavation except site clearance
2 Concrete work
2.01 Lean concrete(C-5 and depth 50mm)
A) Base of Footing pad
4 1.4 F1
1.4
7.84 m2
Dimention
Timizing Squaring Discription
(LXWXD)
B) Base of masonry
2 5.55 On axis 1 & 2
0.5
5.55
2 4.55 On axis A & B
0.5
4.55
10.1
C) Base of Grade Beam
2 5.55 On axis 1 & 2
0.3
3.33
2 4.55 On axis A & B
0.3
2.73
6.06
24 m2………………………………………….Total lean concrete
2.02 C-25 Concrete
A) Footing pad
4 1.4 F1
1.4
0.3
2.35 m3
B) Footing column
4 0.45 C1
0.45
2.5
2.03
C) Grade Beam
2 6.45 On axis 1 & 2
0.3 consider 0.1m depth from GB(from OGL)
0.1
0.39
Dimention
Timizing Squaring Discription
(LXWXD)
2 4.85 On axis A & B
Tackoff sheet G+5 RC WATER TANKER
4 Back fill
Back fill = T.E - DDT
78.44 Total back fill excluding of site clearance
5 Cart away
Cartaway = T.E - Back fill
and site clearance (cosider 0.2 depth of site ckearance)
31.152 Total Cartaway
Dimention
Timizing Squaring Discription
(LXWXD)
6 Formwork
A) Footing pad
4 1.45 F1
0.3 F1 have 4 pices and one footing have four faces
6.96 then 4*4*1.4*0.3…… footing depth 0.3m
Tackoff sheet G+5 RC WATER TANKER
B) Footing column
4 2.5 C1
0.5 C1 have 4 pices and one Column have four faces
20 and foundation column height 2.55m
C) Grade Beam side formworks
2 6.5 On axis 1 & 2
0.1
1.3 In this case outer and inner face of beam is equal but, Isn't
2 5.45 On axis A & B
0.1
1.09
2.39
Dimention
Timizing Squaring Discription
(LXWXD)
B.SUPPER STRUCTURE
1. CONCRETE WORK
1.01. Column(C-25) 1:2:3
4 0.45 C1
0.45
15
12.15
Tackoff sheet G+5 RC WATER TANKER
Dimention
Timizing Squaring Discription
(LXWXD)
2. plastering 1:3
2.01. Beam
A) Graed beam
2 6.45 On axis 1 & 2
0.35 consider 0.1m depth from GB(from OGL)(above substructed)
13.55
2 5.45 On axis A & B
0.35 consider 0.1m depth from GB(from OGL)(above substructed)
11.45
B) 1ST_5TH Floor beam include top tie beam
12 6.45 On axis 1 & 2
Tackoff sheet G+5 RC WATER TANKER
Dimention
Timizing Squaring Discription
(LXWXD)
Tackoff sheet G+5 RC WATER TANKER
Dimention
Timizing Squaring Discription
(LXWXD)
Tackoff sheet G+5 RC WATER TANKER
Project:-
G+5 RC water tanker Page:- 02
Project No:- 1 Bill No:- 01
Dimention
Timizing Squaring Discription
(LXWXD)
Tackoff sheet G+5 RC WATER TANKER
Project:-
G+5 RC water tanker Page:- 02
Project No:- 1 Bill No:- 01
Dimention
Timizing Squaring Discription
(LXWXD)
Tackoff sheet G+5 RC WATER TANKER
Project:-
G+5 RC water tanker Page:- 02
Project No:- 1 Bill No:- 01
Dimention
Timizing Squaring Discription
(LXWXD)
Project:-
G+5 RC water tanker Page:- 02
Tackoff sheet G+5 RC WATER TANKER
Dimention
Timizing Squaring Discription
(LXWXD)
Tackoff sheet G+5 RC WATER TANKER
Project No:-
arance
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
ucted)
ucted)
ucted)
ucted)
Tackoff sheet G+5 RC WATER TANKER
ucted)
ucted)
uctre)
ucted)
ucted)
ucted)
eparetly
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Tackoff sheet G+5 RC WATER TANKER
Project:-
G+5 RC water tanker Page:- 02
Project No:- 1 Bill No:- 01
Dimention
Timizing Squaring Discription
(LXWLD)
Tackoff sheet G+5 RC WATER TANKER
Project:-
G+5 RC water tanker Page:- 02
Project No:- 1 Bill No:- 01
Dimention
Timizing Squaring Discription
(LXWLD)
Bar schedul for G+4 RC Tower
No. bar
Dia Lengt per
DR.No Location Type Shape
(mm) h(m) membe
r
A) SUB
STRUCTURE
ST - 03 1.1 Footing pad F1 10 1.7 27
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
16 4.5 6
1.2 Foundation C1
ST - 03 12 4.5 2
column
Stirrup 8 1.7 14
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
On axis 1&2
Top 14 8 6
Bttom 16 6.2 6
Stirrup 10 1.4 39
ST-02 1.3 Grade beam
On axis A&B
Top 14 7.2 6
Bttom 14 7.2 4
Stirrup 10 1.4 43
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
B) SUPPER
STRUCTURE
16 3.8 6
GF
12 3.8 2
Stirrup 8 1.58 14
16 3.8 6
1ST
12 3.8 2
Stirrup 8 1.58 14
16 3.8 6
1.1 Elevation 2ND
ST - 03 12 3.8 2
column
Stirrup 8 1.58 14
16 3.8 6
3RD
12 3.8 2
Stirrup 8 1.58 14
16 4 6
4TH
12 4 2
Stirrup 8 1.58 14
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
On axis 1&2
Top 16 6.2 4
Bttom 16 6.2 6
Stirrup 10 1.4 39
ST-03 1.2 1ST Floor beam
On axis A&B
Top 14 7.2 6
Bttom 14 7.2 4
Stirrup 10 1.4 43
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
On axis 1&2
Top 14 6.2 4
Bttom 14 6.2 4
Stirrup 8 1.4 31
ST - 03 1.3 2nd floor
On axis A&B
Top 14 7.2 4
Bttom 14 7.2 3
Stirrup 8 1.4 38
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
On axis 1&2
Top 14 6.2 3
Bttom 14 6.2 3
Stirrup 8 1.4 31
ST - 03 1.4 3rd & 4th floor
On axis A&B
Top 14 7.2 3
Bttom 14 7.2 3
Stirrup 8 1.4 38
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
On axis 1&2
Top 14 6.2 3
Bttom 16 6.2 5
Stirrup 10 1.4 76
ST-03 1.5 Toptie beam
On axis A&B
ST-03 1.5 Toptie beam
Top 16 7.2 4
Bttom 16 7.2 8
Stirrup 10 1.4 110
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
X-axis strip 1&3
Top 10 2.98 72
Bttom 10 7.62 36
X-axis strip 2
Top 12 2.98 32
Bttom 12 7.62 16
ST-03 1.6 Slab
Y-axis strip A&C
Top 10 3 20
Bttom 12 6.62 29
Y-axis strip B
Top 12 3 20
Bttom 12 6.62 20
Total Length(M)
Weight per meter(kg/m)
Total weight(kg)
Sum
hedul for G+4 RC Tower
4 108 183.6
Total Length(M) 0 0 183.6 0 0 0 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 0 113.2 0 0 0 0 0 0 0
4 24 108
4 8 36
4 56 95.2
Total Length(M) 0 95.2 0 36 0 108 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 37.6 0 31.968 0 170 0 0 0 0
2 12 96
2 12 74.4
2 78 109.2
2 12 86.4
2 8 57.6
2 86 120.4
Total Length(M) 0 0 229.6 0 240 74.4 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 0 141.6 0 290.08 117 0 0 0 0
0 38 255 31.97 290.1 288 0 0 0 0
4 24 91.2
4 8 30.4
4 56 88.5
4 24 91.2
4 8 30.4
4 56 88.5
4 24 91.2
4 8 30.4
4 56 88.5
4 24 91.2
4 8 30.4
4 56 88.5
4 24 96
4 8 32
4 56 88.5
Total Length(M) 0 442 0 153.6 0 460.8 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 175 0 136.4 0 727 0 0 0 0
2 8 49.6
2 12 74.4
2 78 109.2
2 12 86.4
2 8 57.6
2 86 120.4
Total Length(M) 0 0 229.6 0 144 124 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 0 141.6 0 174 196 0 0 0 0
2 8 49.6
2 8 49.6
2 62 86.8
2 8 57.6
2 6 43.2
2 76 106
Total Length(M) 0 193 0 0 200 0 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 76.2 0 0 241.73 0 0 0 0 0
4 12 74.4
4 12 74.4
4 124 174
4 12 86.4
4 12 86.4
4 152 213
Total Length(M) 0 386 0 0 321.6 0 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 152 0 0 388.71 0 0 0 0 0
2 6 37.2
2 10 62
2 152 212.8
2 8 57.6
2 16 115.2
2 220 308
Total Length(M) 0 0 520.8 0 37.2 234.8 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 0 321.2 0 44.962 371 0 0 0 0
1 72 214.6
1 36 274.3
1 32 95.36
1 16 121.92
4 80 216
2 58 383.96
2 40 108
1 20 132.4
Total Length(M) 0 0 704.9 841.64 0 0 0 0 0 0
Weight per meter(kg/m) 0.222 0.39 0.617 0.888 1.2087 1.579 2.47 3.552 4.835 6.315
Total weight(kg) 0 0 434.7 747.38 0 0 0 0 0 0
B- SUPER STRUCTURE
1.0 - CONCRETE WORK
1.1 R.C, C-25, 365kg of cement per m3
1.1.1 In elevation column m3 12.15
1.1.2 Gread beam m 3
2.49
1.1.3 1ST _ 4TH Floor include top-tie beam m3 13.63
1.1.4 Slab m 3
9.67
1.2 Plastering ratio(1:3)
1.2.1 In elevation column m3 108.00
1.2.2 Gread beam m 3
25.00
1.2.3 1ST _ 5TH Floor include top-tie beam m 3
257.04
1.2.4 Slab m3 101.75
2.0 - Reinforcement
2.1 Elevation column
Reinforcement Bar - Ethiopia: 8mm kg 174.60
Reinforcement Bar -Ethiopia: 12mm kg 136.40
Reinforcement Bar -Ethiopia: 16mm kg 727.45
Black anield wair(1%/kg)(1kg = 100kg) kg 10.38
2.2 1ST Floor beam
Reinforcement Bar Ethiopia: 10mm kg 141.59
Reinforcement Bar Ethiopia: 14mm kg 174.05
Reinforcement Bar -Ethiopia: 16mm kg 195.75
Black anield wair(1%/kg)(1kg = 100kg) kg 5.11
2.3 2nd Floor beam
Reinforcement Bar Ethiopia: 8mm kg 76.25
Reinforcement Bar Ethiopia: 14mm kg 241.73
Black anield wair(1%/kg)(1kg = 100kg) kg 3.18
2.4 3RD_4TH Floor beam
Reinforcement Bar Ethiopia: 8mm kg 152.50
Reinforcement Bar Ethiopia: 14mm kg 388.71
Black anield wair(1%/kg)(1kg = 100kg) kg 5.41
2.5 Top tie beam
Reinforcement Bar Ethiopia: 10mm kg 321.16
Reinforcement Bar Ethiopia: 14mm kg 44.96
Reinforcement Bar -Ethiopia: 16mm kg 370.67
Black anield wair(1%/kg)(1kg = 100kg) kg 7.37
2.4 Slab
Reinforcement Bar Ethiopia: 10mm kg 434.68
Reinforcement Bar Ethiopia: 12mm kg 747.38
Black anield wair(1%/kg)(1kg = 100kg) kg 11.82
3.0 - Formwork
3.1 Elevation column m2 120.00
3.2 Gread beam m 2
16.66
3.3 1ST _ 4TH Floor include top-tie beam m 2
160.66
3.4 Soffit formwork m 2
103.18