9 - MS-Project-Install-and-navigation-reference-V2.0

This document serves as a reference guide for installing and navigating MS Project 2016, detailing installation steps and key navigation features such as the Ribbon, Task Ribbon Menu, and various project management functionalities. It includes instructions for setting up calendars, baselines, and tracking tasks, along with links for further assistance. The author disclaims responsibility for any changes made by Microsoft to the software or its site.

Uploaded by

ZI Site
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views15 pages

9 - MS-Project-Install-and-navigation-reference-V2.0

This document serves as a reference guide for installing and navigating MS Project 2016, detailing installation steps and key navigation features such as the Ribbon, Task Ribbon Menu, and various project management functionalities. It includes instructions for setting up calendars, baselines, and tracking tasks, along with links for further assistance. The author disclaims responsibility for any changes made by Microsoft to the software or its site.

Uploaded by

ZI Site
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

MS project 2016 – Install and Navigation

Reference

Disclaimer: This is for reference and assistance purpose only. The author of this document is not
responsible for changes or revision made by Microsoft on MS project or its site at any point of time

Updated by Guha Rajan, Sep 2018


Contents
1.Installation ........................................................................................................................................................................... 1
Note: .................................................................................................................................................................................... 1
2. MS project professional – navigation ............................................................................................................................... 2
Ribbon.............................................................................................................................................................................. 2
Task Ribbon Menu ........................................................................................................................................................... 3
Task entry and Gantt Chart .............................................................................................................................................. 4
Resource Ribbon .............................................................................................................................................................. 5
Project Ribbon ................................................................................................................................................................. 6
Calender Set up ................................................................................................................................................................ 7
Project Baseline ............................................................................................................................................................... 9
Project  Project Info  Statistics (Base line & variance) ............................................................................................ 9
Tracking Gantt ............................................................................................................................................................... 10
To update Task Status .................................................................................................................................................... 11
View Ribbon .................................................................................................................................................................. 12
Report Ribbon ................................................................................................................................................................ 12

Note: There are many functionalities which can be explored. These are some of the critical & basic functionality of
navigation and not a complete list.

Updated by Guha Rajan, Sep 2018 ii


Page
1.Installation

To install MS project please visit

https://products.office.com/en-us/project/project-online-professional

User can opt to purchase and try for free, follow the procedure to get Project online professional

Note:
• For your specific country change ‘en-us’ appropriately to your country in link or check in Microsoft
website or google.
• Refer to FAQ link https://products.office.com/en-us/project/microsoft-project-faq
• When you opt for project online you have option to install project profession during the installation
process.

Updated by Guha Rajan, Sep 2018

Page 1
2. MS project professional – navigation

Ribbon

Task Ribbon

Updated by Guha Rajan, Sep 2018 2


Page
Task Ribbon Menu

In the above Task ribbon, click on Gantt Chart. There is a drop down menu list of option.

The critical ones:

• Select Gantt Chart – Entry for Task


o Choose Task mode – ‘Manually Scheduled’ or ‘ Auto Scheduled’. Auto schedule is for automatic
defaulting of Task Date
• Select Resourse Sheet – Entry for Resource details

Updated by Guha Rajan, Sep 2018 3


Page
Task entry and Gantt Chart

Task mode Predecessor Gantt Chart


Task
Dependency
creation

Parent or child
task

Updated by Guha Rajan, Sep 2018 4


Page
Resource Ribbon

Level Resource - Overallocation

Updated by Guha Rajan, Sep 2018 5


Page
Project Ribbon

Enter project Calendar Project Project


information set up baseline status update

Updated by Guha Rajan, Sep 2018 6


Page
Calender Set up

Create custom calendar  click on Create New calendar and make a copy/name it

Updated by Guha Rajan, Sep 2018 7


Page
Assign to Project

Updated by Guha Rajan, Sep 2018 8


Page
Project Baseline

Project Ribbon  Set Baseline

Project  Project Info  Statistics (Base line & variance)

Updated by Guha Rajan, Sep 2018 9


Page
Now, click on Statistics

Tracking Gantt

Task  Gantt Chart  Tracking Gantt

Updated by Guha Rajan, Sep 2018 10


Page
Note: Once project is baselined – There is two line image Gantt, bottom showing baseline Gantt and top about the
progress.

To update Task Status

Task  Information  Percentage complete

Updated by Guha Rajan, Sep 2018 11


Page
View Ribbon

More Tables select appropriate ‘Earned Value’

• From more tables option in View, you can select tables for calculation from Earned value – Refer Earned
value analysis

Report Ribbon

Updated by Guha Rajan, Sep 2018 12


Page
Many reports which can be explored based on project need and reporting

Updated by Guha Rajan, Sep 2018 13


Page