Fundamentals of SPM
Fundamentals of SPM
PROJECT MANAGEMENT
Lecture-14
PLAN
Specifications
ACTION Project Schedule
Correct Project budget
Resource plan
deviations
Vendor contracts MONITOR
from plan Record status
RE-PLAN as Report progress
Report cost
necessary
COMPARE
Actual status
against plan
-Schedule
-Cost
Project Control
■ Control – process and activities needed to
correct deviations from plan
■ Control the triple constraints
■ time (schedule)
■ cost (budget, expenses, etc)
■ performance (specifications, testing results, etc.)
Techniques for monitoring and
control
■ Earned Value Analysis
■ Critical Ratio
Earned Value Analysis (EVA)
■ Earned Value analysis is a method of performance
measurement
■ EVA is also called Variance Analysis
■ Metric of project tracking
■ “What you got for what you paid”
■ Physical progress
■ Pre-EVA ‘traditional’ approach
■ 1. Planned time and costs
■ 2. Actual time and costs
■ Progress: compare planned vs. actual
■ EVA adds third dimension: value
■ Planned, actual, earned
Earned Value Analysis
■ If total value of the work accomplished is in balance
with the planned (baseline) cost, and actual cost then
top mgmt has no particular need for a detailed
analysis of individual tasks
■ Old models include cost & expenditure
■ EVA adds schedule estimation
■ Measured in dollars or hours
Earned Value Analysis
1. PV- Planned Value, estimated value of the planned work
Budgeted Cost
2. EV– Earned Value, estimated value of work done Actual
work completed
3. AC – Actual Cost, what you paid
4. BAC – Budget at Completion, the budget for the total job
Derived EVA Variances
1. Planned Value (PV). Authorized budget assigned to scheduled work
for an activity or WBS component. Total PV for the project is also
known at Budget At Completion (BAC).
SV = EV – PV