Ciap Document 102 PDF
Ciap Document 102 PDF
The purpose of this document is to familiarize the readers with the key provisions in
construction contracts, highlighting the respective rights and obligations of the
contracting parties and providing the procedures, guidelines, and the criteria to be
used in situations that normally arise or may possibly happen during project
implementation. Each section contains the gist of the provisions offered therein
underscoring the importance of each of them and citing relevant jurisprudence to
guide the readers on how to ascertain, prevent, and manage risks and issues in
construction projects. The case briefs are presented to give the readers a grasp of
the circumstances surrounding the issues and to give them insights on the practical
application of the laws, the industry practice, and the provisions in CIAP Document
102, in the interpretation of ambiguities of the contract and filling in the omission of
provisions which are ordinarily established.
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
This document specifies general conditions of contract between a private Owner and
Contractor applicable to the construction of any type of structure or works as
contemplated in Republic Act No. 4566 otherwise known as the Contractors’ License
Law.
Article 1 Definitions
This provision contains the customary definition of the terms used in
the Contract documents.
Words that are capitalized or begin with a capital letter refer to a
specific term, name, expression or document which shall have no
other meaning other than the meaning as provided for in this article,
and which shall be used and referred to as such in all of the Contract
documents.
Article 2 Execution, Correlation, Meaning of Terms, and Intent of
Documents
The purpose of this article is to provide the correlation, meaning, and
intent of the contract documents pertaining to all labor, materials,
and equipment necessary for the proper execution of the Work and
the rules in the interpretation of the provisions of Contract
documents in cases where there is an ambiguity, conflict, error, or
omission in any of them.
Page 1 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
The principle of good faith and fair dealing is often applied by the
Courts in ascertaining the facts and circumstances surrounding the
issues brought before them for decision. The Supreme Court defined
“good faith” as:
“an intangible and abstract quality with no technical meaning
or statutory definition, and it encompasses, among other
things, an honest belief, the absence of malice and the
absence of design to defraud or to seek an unconscionable
advantage. It implies honesty of intention, and freedom from
knowledge of circumstances which ought to put the holder
upon inquiry. The essence of good faith lies in an honest
belief in the validity of one’s right, ignorance of a superior
claim and absence of intention to overreach another.”
Page 2 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
Page 3 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
may, as provided for under Article 20.04, examine the work done and
require tests to ensure compliance by the Contractor with the
Specifications. In Deiparine vs. CA and Trinidad [1], it was held that
though the Contract documents do not require concrete stress test,
the Owner has the right to require a test to verify the structural
soundness of the building constructed, in view of the Contractor’s
disregard of the Owner’s instruction to get approval of the samples of
the cement mixture prior to pouring and the inconsistencies in the
results of the cylinder tests. The Supreme Court ruled that it was
rational for the Owner to require such test as it was the only means
by which it could ascertain the Contractor’s faithful compliance with
the Specifications and the integrity of the building constructed. The
structure failed in the concrete core test, thus, justifying Owner’s
rescission of the Contract.
[1] Deiparine vs. CA and Trinidad, G.R. No. 96643, April 23, 1993
Page 4 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
Article 19 Labor
Under this article, the Contractor is required to employ only qualified
and competent workers for the project to ensure the quality of the
Work.
Article 20 Work
The purpose of this article is to ensure that the Contractor is paid for
Work completed and for the Owner to retain a portion of the Contract
Price, when the retained amount and the Performance Bond, are not
sufficient to complete the Work without additional cost to the Owner.
Presented in detail under this article are the conditions affecting the
scope of Work, the quality of the Work, and the effects on Contract
Price and Completion Time if there are changes in the Work.
Page 5 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
For deductive change order initiated by the Owner for the purpose of
transferring certain work items or part of the scope of work to
another Contractor or for the Owner to supply certain construction
materials, the Contractor shall be entitled to fifteen percent (15%) of
the amount deducted in the change order to recover overhead
expenses and profit.
Article 20.04 provides the procedure for the inspection of the Work,
stipulating the responsibility of the Owner to inspect and examine
ongoing works including works which were covered up or already
completed but were purportedly done not in accordance with the
Drawings and Specifications, and assigning to the Contractor all the
costs of examination and of satisfactory reconstruction of works
found to be defective. A Supplemental Agreement is required for
special test or inspection instructed by the Owner to be performed
Page 6 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
Page 7 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
Page 8 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
The Time of Completion of the Work starts and ends on the date
stipulated in the Contract, in the absence of which, from the date the
Contractor commences the Work and ends on the stipulated date of
completion of the Work, or by a specific date.
When the time for completion of the Work is contingent upon the
date when the Contractor actually commences the Work, the
commencement date is normally indicated in the Notice to Proceed
(NTP) issued by the Owner as within seven (7) days or more days from
receipt of the NTP or on the fixed date indicated in the NTP. The
commencement date is significant in reckoning the Completion Time
or in computing liquidated damages in case there is delay in the
execution or completion of the Work. Likewise, there are obligations
of the Owner and the Contractor which are to be performed reckoned
from the commencement date of the Contract, such as Article 32.01
[Advance Payment] and Section II [Laws, Regulations, Site
Conditions, Permits and Taxes]. If the Contract does not provide for
the issuance of a Notice to Proceed, the Contractor should get
consent from the Owner for it to commence the Work on a date it so
specified.
For delay caused by events not due to the fault or neglect of the
Contractor, the Owner shall determine the reasonable adjustment of
Completion Time corresponding to such delay within fifteen (15) days
from receipt of the Contractor’s request. If the delay is authorized by
Page 9 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
the Owner or caused by the act, neglect, delay or fault of the Owner,
the adjustment is based on the period of delay caused by such
event/factor, and the Contractor may be entitled to additional costs
(See Article 20.08 [Claims for Extra Cost]). This provision should be
interpreted in conjunction with Articles 26 [Termination and
Suspension] and 29.06 [Liquidated Damages].
In DPWH v. FSI[3], the Supreme Court affirmed the finding of CIAC that
the delay of FSI was caused by DPWH for which it was awarded
extended rental costs of various equipment and standby rental cost
and overhead costs during the period those equipment went idle. In
addition, it was relieved of the liability for liquidated damages, as the
delay was caused by DPWH which failed to the right-of-way and to
turn over to FSI possession of the site free of obstructions.
Article 22 Payments
This article provides the conditions relative to payments, including
the release of retention.
[3] Department of Public Works and Highways vs. Foundation Specialists, Inc., G.R. No. 191591, June 17, 2015
Page 10 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
[4] H.L. Carlos Construction, Inc. v. Marina Properties Corporation, Jesus K. Typoco, Sr. and Tan Yu, G.R. No.
147614, January 29, 2004; Empire East Land Holdings, Inc. v. Capitol Industrial Construction Groups, Inc., G.R.
No. 168074, September 26, 2008
[5] Empire East Land Holdings Inc. v. Capitol Industrial Construction Groups, Inc., G.R. No. 168074, September
26, 2008
Page 11 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
For suspension with cause, the Owner shall issue written order to the
Contractor to stop the work or any portion thereof until the cause
thereof has been eliminated.
Page 12 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
The Owner may terminate the Contract for cause even without prior
notice to the Contractor by reason of the economic status of the
Contractor as described in Article 28.01.
The Owner may for cause also terminate the Contract upon fifteen
(15)-day written notice to the Contractor and to its Surety upon
occurrence of any event caused by the Contractor’s act, delay, fault
or neglect. The Owner has the right to exclude the Contractor from
the site and take possession of the Work and all of the Contractor’s
tools, appliances, equipment, machinery, and materials left at the
site. The Owner may take over and finish the Work and withhold any
payment due the Contractor until the Work is finished.
The Owner may terminate the Contract without cause upon fifteen
(15)-day written notice to the Contractor. This is known as
termination for the convenience of the Owner. In such case, the
Contractor shall be paid for all work accomplished and any expense
sustained as a consequence of the termination plus reasonable
termination costs.
[6] Deiparine vs. CA and Trinidad, G.R. No. 96643, April 23, 1993
Page 13 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
Such taking over of the Work shall not prevent the Owner from
recovering damages against the Contractor and its sureties, which
shall include liquidated damages and additional costs incurred in
completing the Work. The Owner is required to assess the value of
the work completed by the Contractor and the value of all usable
materials taken over, which shall be deducted from any amount
found to be due as damages from the Contractor.
[7] Art. 1191. The power to rescind obligations is implied in reciprocal ones, in case one of the obligors should not
comply with what is incumbent upon him.
The injured party may choose between the fulfillment and the rescission of the obligation, with the payment of
damages in either case. He may also seek rescission, even after he has chosen fulfillment, if the latter should
become impossible.
The court shall decree the rescission claimed, unless there be just cause authorizing the fixing of a period.
This is understood to be without prejudice to the rights of third persons who have acquired the thing, in
accordance with Articles 1385 and 1388 and the Mortgage Law.
[8] Art. 1725. The owner may withdraw at will from the construction of the work, although it may have been
commenced, indemnifying the contractor for all the latter's expenses, work, and the usefulness which the
owner may obtain therefrom, and damages.
[9] Angel V. Talampas, Jr. v. Moldex Realty, Inc., G.R. No. 170134, June 17, 2015
Page 14 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
The Supreme Court defined liquidated damages as: “the amount that
the parties agree to be paid in case of a breach, which shall answer
for damages suffered by the owner due to delays in the completion of
the project.”[10] “As long as the contractor fails to finish the works
within the period agreed upon without justifiable reason and after the
owner makes a demand, then liability for damages as a consequence
of such default arises.[11] They are in the nature of penalties. A penal
clause is an accessory undertaking to assume greater liability in case
of a breach. It is attached to the obligation in order to ensure
performance.”[12]
This section embodies the purpose of Republic Act No. 11058 (An
Act Strengthening Compliance with Occupational Safety and Health
Standards and Providing Penalties for Violations Thereof) on ensuring
the safety and health in the work environment and in preventing loss
or damage to lives and properties during construction. It delineates
the responsibilities and liabilities of the Contractor and the Owner by
requiring both of them to secure and maintain (a) insurance coverage
as will protect them from claims for injury or death or damage to
property which may arise from the implementation of the Contract,
and (b) the bonds that will guarantee faithful performance of the
[10] H.L. Carlos Construction, Inc. v. Marina Properties Corporation, 466 Phil. 182, 199-200 (2004)
[11] Atlantic Erectors, Inc. vs. Herbal Cove Realty Corporation, G.R. No. 170732, October 11, 2012
[12] H.L. Carlos Construction, Inc. v. Marina Properties Corporation, 466 Phil. 182, 199-200 (2004)
Page 15 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
Article 32.01 requires Owner to give the Contractor an Advance Payment (also
referred to as down payment), to help with the start-up of
construction, such as mobilization and procurement of materials,
conditioned upon the Contractor’s posting of an Advance Payment
Bond or surety bond to guarantee its repayment. The amount of
advance payment is a percentage of the contract price agreed upon
by the parties which shall be recouped pro rata from payment of
approved progress billings.
Article 32.04 allows the Contractor to request the Owner to furnish the Contractor
reasonable evidence that it is ready and able to fulfill its obligations
under the Contract, and unless such reasonable evidence is
provided, the Contractor may not be required to execute the Contract
or to commence or continue the Work.
Article 33.01 Liens
The purpose of this article is to ensure that the Work is free of any
legal liens prior to the release of the Final Payment to the Contractor.
The Owner may require the Contractor to execute sworn statement
and submit proof of payment of claims of sub-contractor and
suppliers and settlement of its obligations with government agencies
in regard to taxes due in connection with the Contract, the
employees’ contributions, and withholding tax on the employees’
wages, as provided for in Article 22.09 [Acceptance and Final
Payment].
Page 16 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
[13]The Church of Jesus Christ of Latter Day Saints v. BTL Construction Corporation, G.R. No. 176439, and BTL
Construction Corporation v. The Manila Mission of the Church of Jesus Christ of Latter Day Saints and BPI-MS
Insurance Corporation, G.R. No. 176718, January 15, 2014
Page 17 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
This section summarizes the prescribed time limits for the execution of
the Contract conditions as provided in this document.
CASE SYNOPSES
LIQUIDATED DAMAGES
Empire East Land Holdings Inc. v. Capitol Industrial Construction Groups, Inc., G.R.
No. 168074, September 26, 2008
As justification for its claim for liquidated damages against the Contractor, the Owner
alleged that the Contractor was in default in the performance of its obligations at the
start and for the entire duration of the construction due to insufficient manpower and
lack of technical know-how. On the other hand, the Contractor argued that the delay
in the completion of the project was attributed to the Owner’s fault, viz., (a) delayed
issuance of building permit; (b) additional works ordered by the Owner; (c) delayed
payment of progress billings; (d) delayed delivery of owner-supplied construction
materials; and (e) limitation of monthly accomplishment. Both the CIAC and the CA
found these to be the causes of the Contractor’s failure to complete the project on
time.
Liquidated damages are those that the parties agree to be paid in case of a
breach. As worded, the amount agreed upon answers for damages suffered
by the owner due to delays in the completion of the project. Under
Philippine laws, they are in the nature of penalties. They are attached to the
obligation in order to ensure performance. As a pre-condition to such
award, however, there must be proof of the fact of delay in the performance
of the obligation.
As the Contractor is not guilty of breach of its obligation under the Contract, it cannot
be held liable for liquidated damages.
Atlantic Erectors, Inc. v. Herbal Cove Realty Corporation, SC G.R. No. 170732,
October 11, 2012, 684 SCRA 55
At issue here is whether by the Owner’s termination of the Contract the Contractor
was prevented it from completing the project, thereby releasing it from liability for
liquidated damages.
Page 18 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
It is not disputed that the Contractor reneged on its obligation to complete the project
on schedule despite the extensions granted by the Owner. The Contractor did not
seek additional time after the expiration of the extended period despite its claim of
the existence of circumstances that entitle it to an extension of time, which it,
however, failed to document. Although there was a commitment from the Contractor
to complete the project, its proposed date of completion was way beyond the
extended completion date agreed upon. The Contractor argued further that the
Owner’s termination of the contract prevented it from fulfilling its commitment to
complete the project.
The Supreme Court further noted that while the contractor cited grounds which fairly
entitled it to additional time to complete the works, it never sent to the owner a
request for extension of time to finish the work. Assuming these reasons to be valid,
still the contractor is not excused from making this request, and should bear the
consequences for the delay for it deprived the owner of the right to determine the
length of extension to be given to it and, consequently adjust the period to finish the
work.
The rights to liquidated damages and to terminate the contract are distinct remedies
available to the Owner under the Contract. What is decisive of the Owner’s
entitlement to liquidated damages is the fact of delay in the completion of the works.
The Contractor’s accomplishment as of the last billing was only 62.57%. Thus,
liquidated damages in the maximum amount of 10% of the Contract price was
awarded to the Owner against the Contractor.
Issues: Whether delay should be computed until actual termination of the contract or
until substantial completion of the project.
Page 19 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
The project was not completed on the initial completion date, hence, several
extensions were granted, but still, the project was not completed on the final
extension granted. The Contractor’s accomplishment after the expiration of the
extended completion time was only at 93.18%, thus, the Owner terminated the
Contract.
The contracting parties are free to stipulate as to the terms and conditions
of the contract for as long as they are not contrary to law, morals, good
customs, public order or public policy. Corollary to this rule is that laws are
deemed written in every contract. Deemed incorporated into every contract
are the general provisions on obligations and interpretation of contracts
found in the Civil Code.
While the Contract provides for liquidated damages of 1/10 of 1% of the contract
price for every day of delay, it does not, however, provide for the period until when
such liquidated damages shall run. In this instant case, the Supreme Court said that
such omission may be supplemented by the provisions of the Civil Code (Arts. 1234
and 1376), the industry practice, and the CIAP Document 102 which have suppletory
effect on private construction contracts, provided that the Contractor successfully
proved by substantial evidence that it actually achieved 95% completion. The
Contractor, however, failed to present evidence to show what it had accomplished
from the time of the last billing up to the time the contract was terminated, and also
failed to prove that it is a practice in the construction industry to project the date of
substantial completion of a project and to compute the period of delay based on the
rate in past progress billings.
The rules are intended to balance the allocation and burden of costs
between the contractor and the project owner, so that the contractor still
achieves a return for its completed work and the project owner will not incur
further costs. To compute the period of delay when substantial compliance
is not yet achieved but merely on the assumption that it will eventually be
achieved would result in an iniquitous situation where the project owner will
bear the risks and additional costs for the period excused from liquidated
damages.
Thus, the Contractor cannot be excused from the payment of liquidated damages for
it failed to meet the condition precedent, that is, that it actually achieved 95%
completion rate.
Filinvest Land, Inc. v. The Honorable Court of Appeals, Philippine American General
Insurance Company and Pacific Equipment Corporation, G.R. No.
138980, September 20, 2005, 470 SCRA 57
Issues: Whether or not the liquidated damages agreed upon by the parties should
be reduced considering that: (a) time is of the essence of the contract; (b) the
Page 20 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
liquidated damages was fixed by the parties to serve not only as penalty in case the
Contractor fails to fulfill its obligation on time, but also as indemnity for actual and
anticipated damages which the Owner may suffer by reason of such failure; and (c)
the total liquidated damages equivalent to 32% of the total contract price was freely
and voluntarily agreed upon by the parties.
The Contractor admitted that it failed to complete the contracted work despite the
three extensions granted by the Owner because of inclement weather and Owner’s
alleged refusal to accept and pay its accomplished work and change order. The
Owner took over the project and held the Contractor liable for damages which it had
incurred and will incur to finish the project in the amount of ₱15,000 per day of delay
as stipulated in the Contract. According to the Owner, such provision in the Contract
is intended to recover from the Contractor actual anticipated and liquidated
damages, and it is not just merely for penalizing breach of the contract. It argued
that had the project been completed on time, it could have sold the lots sooner and
earned its projected income that would have been used for its other projects.
In obligations with a penal clause, the penalty shall substitute the indemnity
for damages and the payment of interests in case of noncompliance, if
there is no stipulation to the contrary. Nevertheless, damages shall be paid
if the obligor refuses to pay the penalty or is guilty of fraud in the fulfillment
of the obligation.
The penalty may be enforced only when it is demandable in accordance with the
provisions of this Code.
Page 21 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
As a general rule, courts are not at liberty to ignore the freedom of the
parties to agree on such terms and conditions as they see fit as long as they
are not contrary to law, morals, good customs, public order or public policy.
Nevertheless, courts may equitably reduce a stipulated penalty in the
contract in two instances: (1) if the principal obligation has been partly or
irregularly complied; and (2) even if there has been no compliance if the
penalty is iniquitous or unconscionable [Article 1229, Civil Code].
The construction was beset by several delays. As such, the parties entered into a
second contract increasing the contract price and extending the deadline for
completion of the project. The Owner, likewise, agreed to extend financial assistance
to the Contractor by paying directly the suppliers of construction materials. Despite
such, however, the Contractor still failed to meet the target completion date. Hence,
the Owner took over the project.
The Contractor alleged that the delay was due to the Owner’s delay in the approval
and payment of monthly billings; delivery of materials; and execution of a formal
written construction agreement. The project was already 97% complete when the
Owner took over, which at that time, the Contractor was already delayed by 294 days.
Page 22 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
There was no bad faith on the part of the Contractor as it had in fact completed 97%
of the project. The delay in the delivery of materials cannot be attributed to the
Owner as the payment of materials directly by the Owner is only an accommodation to
ensure the timely completion of the project, but the obligation to procure and have
the materials delivered on time remains with the Contractor. It was held that the total
amount of ₱11,432,190.00 as liquidated damages (1/10 of 1% of the contract price
or ₱38,885.00 per day for 294 days of delay) is unconscionable.
As a general rule, courts are not at liberty to ignore the freedom of the
parties to agree on such terms and conditions as they see fit as long as they
are not contrary to law, morals, and good custom, public policy or public
order. Nevertheless, (t)he judge shall equitably reduce the penalty when the
principal obligation has been partly or irregularly complied with by the
debtor. Even if there has been no performance, the penalty may also be
reduced by the courts if it is iniquitous or unconscionable. [Art. 1229, Civil
Code]
The Contractor failed to complete the works on time. The Owner hired an accredited
testing laboratory to assess the Contractor’s quality of work and accomplishment
rate, and it was discovered that there were substandard works and that substandard
materials were used in the project. The parties then agreed to execute a second
contract to cover the necessary corrective works and to extend the deadline for
completion of the project. Despite such, however, the Contractor still failed to finish
the project within the extended time indicated in the second contract. At that time,
the Contractor’s accomplishment was determined at 98.16%.
The Owner is not entitled to liquidated damages since the Contractor already
accomplished more than 95% required under CIAP Document 102 [Art. 20.11(A)(a)]
which is considered substantial completion of the project, and instead, awarded the
cost of the remaining works in accordance with Article 1234 of the Civil Code – “If the
obligation had been substantially performed in good faith, the obligor may recover as
though there had been a strict and complete fulfillment, less damages suffered by
the obligee”.
Page 23 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
PROLONGATION COSTS
Department of Public Works and Highways vs. Foundation Specialists, Inc., G.R. No.
191591, June 17, 2015
The Contractor demanded from the Owner the payment of extended rental costs of
various equipment, standby rental cost, and overhead costs which it incurred during
the period of delay caused by the Owner’s failure to remove all obstructions and
secure road right-of-way along the stretch of construction.
The Owner’s denial of the Contractor’s claims for extended rental and overhead costs
was not justified absent any document to prove that such claims are prohibited. The
Owner failed to present the modified Contract provision which allegedly contain such
prohibition. Moreover, such modified Contract provision was not even mentioned in
the Owner’s letters to the Contractor granting the latter’s requests for time extension.
Thus, it was concluded that no such modified version existed, and that the Owner had
no basis to deny Contractor’s claims for extended rental and overhead costs, which
the CIAC and the Court of Appeals have exhaustively deliberated upon. Hence, the
award to the Contractor of the costs of standby rental cost and overhead costs were
affirmed, but the award of the extended rental costs of various equipment was
ordered to be recomputed by the CIAC to cover only the period such various
equipment were idle due to the Owner’s delay.
PRICE ESCALATION
Hanjin Heavy Industries and Construction Co., Ltd. v. Dynamic Planners and
Construction Corp., G.R. Nos. 149408 & 170144, April 30, 2008
Among the issues resolved in this case is the legality of the award of price escalation
in favor of the Sub-Contractor.
The Contractor admitted that the Sub-Contractor is entitled to escalation cost for the
local portion of the project, but it argued that it should be computed using the 52
Page 24 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
formulas and price indexes from the National Statistics Office and the National
Statistical Coordination Board, or at 35% of the price index only.
The Contractor failed to present any of the supposed 52 formulas and price indexes
which it claimed would give a more precise price escalation amount, and it also failed
to support its assertion that it should only be at 35% of the price index. The
Subcontract Agreement provides that the Sub-Contractor is entitled to both price
adjustment and price escalation. Thus, the award of the Court of Appeals which was
pegged on the local portion of the contract price which is 65% of the Sub-Contractor’s
billings and accomplishments prior to the Contractor’s takeover, multiplied by 100%
price index was affirmed.
The parties executed an Amended Contract extending the contract period plus a
grace period of 30 days. The Contractor failed to complete the works within the
stipulated completion period and abandoned the project. The Owner, thus, contracted
out the remaining works to another entity and demanded from the Contractor the
damages it incurred. The Contractor, on the other hand, claimed for payment of its
unpaid billings, change orders and extra work, labor and material price escalation,
release of retention, and the value of materials left at site. On the Contractor’s claim
for cost escalation, the Owner averred that the Contractor is not entitled to any price
increase since it was delayed in the completion of the project, and entitling it to such
claim would be to reward it for its breach of contractual obligation.
The Contract prohibited claims for cost escalation except on the labor component of
the work.
The Contractor failed to present evidence, such as an official economic data, that
would show the increases in material costs during the period covered in its claim.
Further, its unpaid billings for change orders and extra work were not subject to
increases since they were not included in the agreed contract price and the materials
for these additional works are to be purchased only when the work was contracted or
agreed upon. Thus, the Contractor is not entitled to material cost escalation.
The labor cost escalation clause in the Contract shall cover government mandated
wage adjustment during the period of construction. The Contractor is entitled to labor
cost escalation even after the expiration of the extended completion period since the
Owner allowed it to continue with the works, and since the Owner accepted and paid
Page 25 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
the Contractor’s accomplishments, labor cost escalation has already been earned
and should be paid for.
The Contractor is very much aware that such acceleration of work necessarily entails
additional costs, thus, its silence about the lack of explicit agreement on who should
bear such additional costs contradicts the principles of fair dealing which should be
the norm of all transactions (Art. 19, Civil Code). On the other hand, the Sub-
Contractor’s similar silence cannot be presumed that it agreed to bear the increased
costs as such would result in unjust enrichment which the law abhors (Art. 2142, Civil
Code). The Sub-Contractor’s compliance with the Contractor’s request for early
completion was in effect a binding modificatory novation of the Contract. The
reasonable inference on the parties’ silence on who should bear the costs involved
was that the parties had impliedly agreed to charge the increased costs to the Sub-
Contract as a Change Order. The Contractor did not offer any compelling reason to
reverse the ruling of the Construction Industry Arbitration Commission (CIAC) on this
claim. Thus, the Court affirmed the CIAC’s ruling and award of additional costs
incurred for early completion of portion of the project covering the increased costs of
labor, materials, and equipment, which were held to be not only legally tenable, but
equitable considerations also support it.
The Contractor in this case incurred tremendous delay in executing the works for the
project. Under the Contract, the project is supposed to be completed in December
2008 but the Contractor has completed only 31.39% of the works as of 14 November
Page 26 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
2008 as per the joint evaluation conducted by the parties. The Contractor did not
ask for an extension of time to complete the project. The Owner thus terminated the
Contract, and demanded from the Contractor the payment of liquidated damages and
the return of the unrecouped down payment and overpayment. The Owner also made
a claim against the Performance Bond to recover the damages it suffered caused by
such delay. The Contractor, on the other hand, contends that the Performance Bond
merely guaranteed the 20% down payment and not the entire obligation under the
Contract, and that since its accomplishment already exceeded such amount, its
obligation under the bond had been fully extinguished.
Default or mora on the part of the debtor is the delay in the fulfillment of the
prestation by reason of a cause imputable to the former. It is the
nonfulfillment of an obligation with respect to time. It is a general rule that
one who contracts to complete certain work within a certain time is liable
for the damage for not completing it within such time, unless the delay is
excused or waived.
While the Contract contemplates delay in the completion of the project, such,
however, does not defeat the Owner’s right to claim for damages or the Contractor’s
liability under the Performance Bond. The Contract stipulates that the Owner shall be
entitled to confiscate the performance bond to compensate for all the damages it
suffered due to delay in the completion of the Project by more than thirty (30) days.
Such stipulation depicts the nature of a penalty clause, which is recognized by law as
“an accessory undertaking to assume greater liability on the part of the obligor in
case of breach of an obligation. It functions to strengthen the coercive force of
obligation and to provide, in effect, for what could be the liquidated damages
resulting from such a breach. The obligor would then be bound to pay the stipulated
indemnity without the necessity of proof on the existence and on the measure of
damages caused by the breach. It is well-settled that so long as such stipulation
does not contravene law, morals, or public order, it is strictly binding upon the
obligor”. The Surety was ordered to pay the Owner the full amount of the
Performance Bond with interest.
Philippine Charter Insurance Corporation vs. Central Colleges of the Philippines and
Dynamic Planners and Construction Corporation, G.R. No. 180631-33, February 22,
2012
The Owner terminated the Contract for failure of the Contractor to complete the
project on time. The Contractor’s accomplishment at the time of termination was only
at 57.33%. The Owner claimed against the Performance Bond and the Surety Bond
for the unrecouped down-payment. The Surety denied its liability under the bonds it
issued arguing that the reglementary period within which to file a claim against the
bonds had already expired. It contends that the claim should have been filed ten
days from the occurrence of the default.
Page 27 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
The civil law concept of delay or default commences from the time the
obligor demands, judicially or extrajudicially, the fulfillment of the obligation
from the obligee. In legal parlance, demand is the assertion of a legal or
procedural right. It is the obligor’s culpable delay, not merely the time
element, which gives the obligee the right to seek the performance of the
obligation.
In this case, the default commenced when the Owner informed the Contractor and
the Surety in writing prior to expiration of the bonds of the breach in the contract and
its plan to claim against the bonds. Upon such notice, the Surety’s liability had
already attached pursuant to Article 2047 of the Civil Code, thus, it is duty bound to
perform what it has guaranteed under the Performance and Surety Bonds, all of
which are callable on demand. The Surety and the Contractor were ordered to jointly
and severally pay the Owner the total amount of the Surety and Performance Bonds.
Due to the Contractor’s financial difficulties and losses, and upon the request of the
Contractor, the Owner and the Contractor executed a deed of assignment in favor of
the Contractor’s suppliers for the project so that they may collect directly from the
Owner. A few months thereafter, the Contractor ceased its operations for lack of
funds to pay for the cost of labor and other items necessary to complete the project.
Consequently, the Owner terminated the Contract and engaged the services of
another contractor to complete the project. The Contractor claimed for payment of its
work accomplishment and the release of retention. The Owner, however, refused to
release the retention since they have already agreed that such amount will answer for
the payment to the Contractor’s suppliers.
The nature of the 10% retention money is that it is a portion of the contract
price withheld from the contractor to function as a security for any
corrective work to be performed on the infrastructure covered by a
construction contract. As such, the 10% retention money should not be
treated as a separate and distinct liability as it merely forms part of the
contract price.
Page 28 of 30
CIAP DOCUMENT 102: Annotations with Case Synopses and Jurisprudence
While the retention will be eventually released to the Contractor, such amount should
be automatically deducted from the Contractor’s billings. Thus, the award to the
Contractor of the unpaid balance of the contract price inclusive of the 10% retention.
Page 29 of 30