Unit 5
Unit 5
• Project Planning
• Project Scheduling
• Project Controlling
PERT was developed by US
Navy Engineers to plan and
control the huge Polaris
Submarine Programme. And Du
Pont and Remington Rand
Companies CPM to help the
process of scheduling.
Programme Evaluation and Review Technique(PERT)
It uses event oriented network in which successive events are joined by
arrows. It is preferred for projects that are non-repetitive and in which time
for various activities cannot be precisely pre-determined. There is no
significant past experience to guide, they are once through projects.
There are three time estimates in PERT.
• Optimistic Time (To)
• Pessimistic Time (Tp)
• Most Likely Time (Tm)
Examples:-
• Launching a new product in the market.
• Research a development of a new war weapon
• Launching of satellite
• Sending Space craft to Mars are PERT projects.
Critical Path Method (CPM )
It uses activity oriented network which consists of a number
of well recognized jobs ,tasks or activities . Each activity is
represented by arrow and the activities are joined together
by events. CPM is generally used for simple ,repetitive
types of projects for which the activity times and costs are
certainly and precisely known.
A ------
B -------
C A
D A,B
Wrong Example
A C
B
D
Though a dummy activity does not consume either
resources or time.
PERT AND CPM ????
1.When is each individual phase of the project
scheduled to start and finish?
9. At what cost?
ACTIVITY :
CONSUME RESOURCES AND TIME
A
TAIL / LHS
t HEAD / RHS
TYPES
2, PRECEEDING ACTIVITY
3.SUCCEEDING ACTIVITY
EVENT / NODE
DO NOT CONSUME RESOUCES AND TIME
BURSTING EVENT
A
B
2
C
MERGING EVENT
D
E
4
F
Rules of Network Construction
1.In network diagram, arrows represent activities and
circles (or nodes) the events. The length of an arrow is
of no significance.
2.Each activity must start and end in a node The
tail of an activity represents the start and head,
the completion of work.
1 2 LOOP / LOOPING
NOT ALLOWED
Though a dummy activity does not consume either
resources or time, even then it has to follow the rules (1)
and 7(ii).
Activity Immediate Predecessors
A -
B -
C A
D B
Activity Immediate Predecessors
A -
B -
C A
D A
E C, B
Beginning Event Ending Event Activity
1 2 1-2
1 3 1-3
2 4 2-4
3 4 3-4
3 5 3-5
4 6 4-6
5 6 5-6
Q1) The following table gives the activities in a construction project and other relevant
information.
i) Draw the network diagram for the project.
ii) Find the critical path
iii) Determine the expected project completion time