100% found this document useful (1 vote)
2K views4 pages

WMS Assessment Qa

Wms assessment

Uploaded by

VASANTH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views4 pages

WMS Assessment Qa

Wms assessment

Uploaded by

VASANTH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Q:01 What is PTW approval Procedure?

Draft (PA) → Validate (AA) → Endorsement (PE) (if required) → Asset Approval
Authority (AAA) → Approval (AA) → Permit Issue (PI) → Accept (JP)

Q:02 What are PA Responsibilities?


Performing Authority (PA) shall provide clear and adequate
description about the following aspects:
 A clear and concise title and description and location of work
 Proposed / Planned start and finish date or duration
 Job Performer (JP) details namely Discipline / Department
 Expected number of people in the work party
 Equipment, material and tools to be used
 Providing documents supporting the work activity such as
Method Statement, Procedures, Checklists, Drawings etc.
Q:03 Type of Permits?
 General Work Permit
 Hot Work Permit
 Critical Work Permit
Q:04 What is PTW Closing Procedure?
Performing Authority (PA) → Permit Issuer (PI) → Area Authority (AA)
Q:05 How many permits PA can sign?
 Total:15
 HWP-5
 CWP-3
 GWP-8
Q:06 What are SIMOPs?
Multiple Activities at one location at one time.
Routine SIMOP
Non-Routine SIMOP
Q:07 What is Project Scope?

ADNOC LNG GROWTH PROJECT MARINE DREDGING WORKS – T2


 Dredging of a marine channel.
o Pre-Dredging survey.
o Intermediate Survey.
o Post Dredging Survey.
o Supply and installation of Navigation AIDS.
o Final Acceptance of dredged level.
o Disposed of dredged material.

Q:8 What is the Reason to Suspend the Permit?


 In case of Emergency
 Change in work conditions
 Bad Weather Condition

Q:9 What are the Hazards for dredging activity?


 Heavy Machinery Operation: Risks of crushing, pinching, or
entanglement from moving parts.
 Falling Overboard: Especially on barges or platforms, workers face
drowning risks.
 Slips, Trips, and Falls: Wet and uneven surfaces can lead to
accidents.
 Noise and Vibration: Prolonged exposure can lead to hearing loss or
vibration-related injuries.
 Manual Handling: Risk of musculoskeletal injuries from lifting or
moving heavy loads.
 High-pressure Lines: Potential hazards from bursting hydraulic lines
or leaks.
 Navigation Hazards: Collision risks with other vessels or underwater
structures.
Q:10 What is FRA (Formal Risk Assessment)
Formal Risk Assessment (FRA) It is an advanced tool used to identify,
evaluate, and control risks associated with activities, systems, or processes.
It is a critical component of risk management, helping organizations ensure
safety, compliance, and efficiency.
Q:11 How many Types of the JSA?
 JSA-Level 1 (Standard Hazard Control Form)
 JSA-Level 2 (Hazard Management Form)
Q:12 What is the Validity of JSA & FRA?
 JSA-Level 01 (Aling with Permit Validity)
 JSA-Level 02 (2 years)
 FRA (1 Year)
Q:13 What is dynamic Risk Assessment?
Continuous monitoring of new hazards during the Job.
Q:14 Dynamis RA Conditions?
Dredging & Survey Activity together
Q:15 How many types of Certificates?
Ten
Q:16 To whom should PA inform in case of emergency or permit suspend?
AA (Area Authority)
Q:17 What is IWAP Team?
Integrated Work Activity Planning Team
Q:18 How many members in the IWAP Team?
 Discipline Engineer
 Planning Engineer
 Asset Owner Representative
 PTW Coordinator
Q:19 What is the JP responsibility?
 Follow & implement safe system of the work at the site.
 Accept the permit
 Suspended the permit
 Conduct the TBT (Toolbox talk)
Q:20 What is WMS?
A safety tool to ensure that the work is properly controlled,
coordinated and communicated”