Lec 05 Project Time MGMT
Lec 05 Project Time MGMT
Lecture # 5
How
What
much
By
when
whom
The Plan
How where
Why
PMI defines project management plan as a ‘‘formal,
approved document that defines how the project is
executed, monitored and controlled”
Why we need a Plan
To establish time frame and organize construction activities
To provide a communication tool between all parties involved
(contractors, consultants, owner etc)
Used as a document for future projects
Can refer to for modifications
To show the impact of productivity-related problems on project
completion
Materials Manpower
Crew size and
Quantities takeoff
composition
Availability and probable Availability
delivery time Time required to perform
Type of materials each activity
Money
Equipment
Account receivable,
Sel of the type of eqpt account payable
Avail and delivery time Time
Beginning
Decision for purchase or End date
renting Milestones
To calculate the project completion
To calculate the start or end of a specific activity
To expose and adjust conflict between subcontractor
To predict and calculate the cash flow
To evaluate the effect of change orders
To serve as an effective project control tool
To improve work efficiency
Project
Networks
A bar chart is ‘‘a graphic representation of project
activities, shown in a time-scaled bar line with no links
shown between activities’’
The bar chart was originally developed by Henry L. Gantt
in 1917 and is alternatively called a Gantt chart
The bar may not indicate continuous work from the
start of the activity until its end.
or
Non continuous (dashed) bars are sometimes used to
distinguish between real work (solid line) and inactive
periods (gaps between solid lines)
The bar may be loaded with more information
Advantages
Time-scaled
Simple to prepare
Improper Solution
Solution
Class Exercise
Draw the arrow network for the project given next
Activity IPA
A -
B A
C A
D B
E B,C
F C
Class Exercise
Draw the node network for the project given next
Activity IPA
A -
B A
C A
D B,C
Draw the logic network and perform the CPM calculations for the
schedule shown below
5,9
B
0,5 9,11
4
A D
5 2
5,8
C
3
Forward pass: The process of navigating through a network from start to end
and calculating the completion date for the project and the early dates for each
activity
Activity IPA Duration
A - 5
B A 4
C A 3
D B,C 2
5,9
B
0,5 9,11
4
A 5,9 D
5 2
5,8
0,5 9,11
C
3
6,9
5,9
B
0,5 9,11
4
A 5,9 D
5 2
5,8
0,5 9,11
C
3
6,9
Activity Duratio
n
ES EF LS LF TF FF Formula
A 5 0 5 0 5 TF = LF - EF (or
B 4 5 9 5 13 LS - ES)
C 3 5 8 10 16 FF = ES of next
D 2 9 11 13 22 activity –
Critical activity EF
Note : FF ≤ TF
For Activity F
Total Float = LF of F – EF of F => 8 – 5 = 3 Free Float = ES of G – EF of F => 5 – 5 = 0
For Activity J
Total Float = LF of J – EF of J => 8 – 3 = 5 Free Float = ES of G – EF of J => 5 – 3 = 2
Class Exercise
Requirement
1. Draw Network Diagrams (AON)
2. Perform CPM calculations
Activity Duration IPA
3. Calculate TF & FF of activities
A 5 -
4. Determine Critical Path B 8 A
C 6 A
D 9 B
E 6 B,C
F 3 C
G 1 D,E,F
Class Exercise
Requirement
1. Draw Network Diagrams (AON) Activity Duration IPA Lag
A 5 -
2. Perform CPM calculations B 3 -
C 6 -
3. Calculate TF & FF of activities
D 7 A
4. Determine Critical Path E 7 A
B 4
F 4 A,B,C
G 5 E
F 3
H 6 D
G 2
I 3 D,G
A D H
5 7 6
2
B 4 E G I
PS PF
3 7 5 3
Activity Duration IPA Lag
A 5 -
3 B 3 -
C F C 6 -
6 4
D 7 A
E 7 A
B 4
F 4 A,B,C
G 5 E
F 3
H 6 D
G 2
I 3 D,G
0, 5 5, 12 21, 27
A D H
5 7 6
14, 21 2 21, 27
2, 7
0 0, 3 7, 14 14, 19 19, 22 27
B 4 E G I
PS PF
3 7 5 3
0 0, 3 7, 14 14, 19 24, 27 27
0, 6 6, 10 3
C F
6 4
1, 7 7, 11
Tabular Solution
0, 5 5, 12 21, 27
A D H
5 7 6
14, 21 2 21, 27
2, 7
0 0, 3 7, 14 14, 19 19, 22 27
B 4 E G I
PS PF
3 7 5 3
0 0, 3 7, 14 14, 19 24, 27 27
0, 6 6, 10 3
C F
6 4
1, 7 7, 11
Activity ES EF LS LF TF FF
A 0 5 2 7 2 0
B 0 3 0 3 0 0
C 0 6 1 7 1 0
D 5 12 14 21 9 7
E 7 14 7 14 0 0
F 6 10 7 11 1 1
G 14 19 14 19 0 0
H 21 27 21 27 0 0 47
I 19 22 24 27 5 5
Repeat Fol Example with imposed finish date of 28
days
L
2
A C F J
5 5 4 2 PF
D G H K
3 4 7 3
Original Solution
5, 11 1 11, 14 15, 23
B E I
6 3 8
23, 25
5, 11 12, 15 15, 23
L
1 5, 10 5 15, 17 2
0, 5 11, 15 25
23, 25
A C F J
5 5 4 2 PF
0, 5 6, 11 11, 15 20, 22
25
3 5, 8 3 8, 12 3 3
12, 19 19, 22
D G H K
3 4 7 3
8, 11 11, 15 15, 22 22, 25
Imposed Finish Date > Calculated Finish Date
3 4 3
5, 11 11, 14 15, 23
B E I
6 3 8 3
23, 25
8, 14 15, 18 18, 26
L
3 4 8
0, 5 5, 10
3
11, 15 15, 17
2 25
26, 28
A C F J
5 5 4 2 PF
3, 8 9, 14 14, 18 23, 25
28
6 6 6 6
5, 8 8, 12 12, 19 19, 22
D G H K
3 4 7 3
11, 14 14, 18 18, 25 25, 28
Imposed Finish Date < Calculated Finish Date
-3 -2 -3
5, 11 11, 14 15, 23
B E I
6 3 8 -3
23, 25
2, 8 9, 12 12, 20
L
-3
0, 5
-2
5, 10
-3
11, 15
2
15, 17
2 25
20, 22
A C F J
5 5 4 2 PF
-3, 2 3, 8 8, 12 17, 19
22
0 0 0 0
5, 8 8, 12 12, 19 19, 22
D G H K
3 4 7 3
5, 8 8, 12 12, 19 19, 22
Definitions
Activity, or task: A basic unit of work as part of the total project that is
easily measured and controlled. It is time- and resource consuming.
Critical activity: An activity on the critical path. Any delay in the start or
finish of a critical activity will result in a delay in the entire project.
Critical path: The longest path in a network, from start to finish, including
lags and constraints.
.
October 17, 2024 52
Early dates: The early start date and early finish date of an activity.
Early finish (EF): The earliest date on which an activity can finish within project constraints.
Early start (ES): The earliest date on which an activity can start within project constraints.
Forward pass: The process of navigating through a network from start to end and calculating
the completion date for the project and the early dates for each activity.
Late dates: The late start date and late finish date of an activity.
Late finish (LF): The latest date on which an activity can finish without extending the project
duration.
Late start (LS): The latest date on which an activity can start without extending the project
duration.
time estimate”
Optimistic Estimate
Pessimistic Estimate
Computing the mean estimate of the activity:
What is the probability that the critical path
activities will be completed within a specified
time when uncertainty is associated with
each of the activities in the path?
Question
Duration
Optimistic Most Pessimistic
Activity Likely
(To) (TP)
(Tm)
A 2 4 7
B 5 8 14
C 4 6 8
D 2 2 2
E 7 10 21
Solution
Duration Expected
Optimistic Most Likely Pessimistic Duration
Activity
(To) (Tm) (TP) (Te)
A 2 4 7 4.167
B 5 8 14 8.500
C 4 6 8 6.000
D 2 2 2 2.000
E 7 10 21 11.333
TE = 32