Session2 2PP
Session2 2PP
Previously…
OSCM
Processes
Planning, Sourcing, Making, delivering, Returning
Goods–Services Continuum
Product–service bundling
Previously…
Competitive Dimensions
1
2023-09-18
Previously…
Chapter 5: Project
A series of related jobs usually directed toward some major output
and requiring a significant period of time to perform.
Project (Part I)
Planning, directing, and controlling resources (people, equipment,
Project management material) to meet the technical, cost, and time constraints of the
project.
Pure project
Functional project
Project Structures
Matrix project
SOW
Project milestones
Organizing Project Tasks
Work breakdown structures
Activities
McGraw-Hill Education / Jacobs Copyright ©2020 McGraw-Hill Education. All rights reserved. No reproduction or distribution
without the prior written consent of McGraw-Hill Education.
OPERATIONS MANAGEMENT
Lecture - 2
2
2023-09-18
CPM/PERT
CPM
Critical Path Method
Developed by Du Pont & Remington Rand
Developed for industrial projects for which activity times generally were
known
PERT
Program Evaluation and Review Technique
Developed by U.S. Navy for Polaris missile project
Developed to handle uncertain activity times
Today’s project management software packages have combined the
best features of both approaches
CPM/PERT
CPM and PERT have been used to plan, schedule, and control a
wide variety of projects:
R&D of new products and processes
Construction of buildings and highways
3
2023-09-18
CPM/PERT
CPM/PERT
4
2023-09-18
Project Network
Copyright ©2020 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior
written consent of McGraw-Hill Education.
Copyright ©2020 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior
written consent of McGraw-Hill Education.
10
5
2023-09-18
CPM Example 1
Consider the following consulting project:
Develop a critical path diagram and determine the duration of the critical path
and slack times for all activities
11
CPM Example 1
Immed.
Task Time
Pred.
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
D(2)
E(5)
12
6
2023-09-18
CPM Example 1
ES= 4
EF= 6
E(5)
13
CPM Example 1
Hint: Start with LF=15 or
the total time of the project
Slack=7-4=9-6=3 and go backward in the
ES= 4
EF= 6 network from G to A.
ES= 0 ES= 2 ES= 3 D(2) ES= 9 ES= 14
EF= 2 EF= 3 EF= 4 EF= 14 EF= 15
LS= 7
A(2) B(1) C(1) LF= 9 F(5) G(1)
ES= 4
EF= 9
LS= 0 LS= 2 LS= 3 LS= 9 LS= 14
LF= 2 LF= 3 LF= 4 or 7? LF= 14 LF= 15
LF= 4
E(5)
LS= 4
LF= 9
14
7
2023-09-18
0 21 36 38
21 26 26 28 31 36
A(21) G(2)
21 28 28 36
0 21 36 38
C(7) F(8)
21 28 28 36
15
For new or unique projects, estimating time for each activity are uncertain in many cases.
Or, when activity times vary, a single time estimate may not be reliable
To incorporate uncertain activity times into analysis, we need to get three time-estimates for
each activity:
Optimistic time = the minimum activity time
Most possible time = the most probable activity time
Pessimistic time = the maximum activity time
In the three-time estimate approach, the critical path is determined as if the mean times for
the activities were fixed times.
The overall project completion time is assumed to have a normal distribution with mean equal
to the sum of the means along the critical path and variance equal to the sum of the variances
along the critical path.
This allows calculation of a probability estimate of completion time
16
8
2023-09-18
17
18
9
2023-09-18
Activity
Immediate
a m b
Expected 𝒂 + 𝟒𝒎 + 𝒃
Predecessors Time (Week)
10 + 4 × 22 + 28 𝑬𝑻 =
A - 10 22 28 21 6
= 21 𝟔
𝟐
B A 4 4 10 5
𝟐
𝒃−𝒂
C A 4 6 14 7 4 + 4 × 4 + 10
=5 𝝈 =
D B 1 2 3 2 6 𝟔
E C,D 1 5 9 5
0 21 36 38
21 26 26 28 31 36
A(21) G(2)
21 28 28 36
Critical Path:
0 21 36 38
1. A C F G C(7) F(8)
2. A B D F G
21 28 28 36
Copyright ©2020 McGraw-Hill Education. All rights reserved. No reproduction or distribution
McGraw-Hill Education / Jacobs without the prior written consent of McGraw-Hill Education.
19
E C,D 1 5 9 5 1.7778
ACFG
∑𝜎 = 9 + 2.7778 + 0.1111 + 0 = 11.8889
F C,D 7 8 9 8 0.1111
ABDFG
G E,F 2 2 2 2 0
∑𝜎 = 9 + 1 + 0.1111 + 0.1111 + 0 = 10.2222
20
10
2023-09-18
A - 10 22 28 21 9
B A 4 4 10 5 1
C A 4 6 14 7 2.7778
D B 1 2 3 2 0.1111
E C,D 1 5 9 5
F C,D 7 8 9 8 0.1111
G E,F 2 2 2 2 0
Step 3: Calculate the probability of finishing
ACFG in 35 weeks
∑𝜎 = 9 + 2.7778 + 0.1111 + 0 = 11.8889
𝐷−𝑇 35 − 38
ABDFG 𝑍= = = −0.87
11.8889
∑𝜎 = 9 + 1 + 0.1111 + 0.1111 + 0 = 10.2222 ∑𝜎
𝑃 . = 𝑁𝑂𝑅𝑀. 𝑆. 𝐷𝐼𝑆𝑇 −0.87, 𝑇𝑅𝑈𝐸 = 0.1922
21
22
11
2023-09-18
What is the probability that the project duration will exceed 39 weeks?
𝐷−𝑇 39 − 38
𝑍= = = 0.29
11.8889
∑𝜎
𝑃 . = 𝑁𝑂𝑅𝑀. 𝑆. 𝐷𝐼𝑆𝑇 0.29, 𝑇𝑅𝑈𝐸 = 0.6141
𝑃 = 1 − 0.6141 = 0.3859 = 38.69%
𝑇 = 38 𝐷 = 39
What is the probability that the project duration between 35 and 39 weeks?
𝐷 = 35 𝑇 = 38 𝐷 = 39
Copyright ©2020 McGraw-Hill Education. All rights reserved. No reproduction or distribution
McGraw-Hill Education / Jacobs without the prior written consent of McGraw-Hill Education.
23
24
12
2023-09-18
PERT Exercise
25
26
13
2023-09-18
27
Project Crashing
28
14
2023-09-18
Step 2:
𝐶𝑜𝑠𝑡 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑡𝑖𝑚𝑒 =
29
30
15
2023-09-18
Activity D cannot be
reduced any further
at this point
Activity A cannot be
reduced any further
at this point
Activity C cannot be
reduced any further
at this point Crash B and C together to Project has reached
reduce both critical paths minimum duration
31
32
16
2023-09-18
33
Crashing Example
A project has been defined to contain the following list of activities, along with their
normal time (weeks), crash time (weeks), normal costs ($000), and crash costs ($000).
34
17
2023-09-18
35
18