DownloadPfdFile Aspx
DownloadPfdFile Aspx
Prepared By:
March, 2019
REVISION STATUS
October
R1 DPR for 3000 TPD capacity plant was submitted to MCGM.
2016
DPR for 600 TPD capacity plant is being submitted as per the
R2 March 2019
change in project structure
R2 30-03-2019 SSL AK AK
REV. CHECKED
DATE PREPARED BY CLEARED BY APPROVED BY
NO. BY
TCE 10176A-2024-DPR-R2 i
4.3.1 Air Quality Standards ................................................................................................. 50
4.3.2 Water Quality Standards ............................................................................................ 52
4.3.3 Leachate Quality Standards ....................................................................................... 52
4.4 Consent from Airport Authority of India ................................................................. 56
4.4.1 Noise Quality Standards............................................................................................. 57
CHAPTER 5: Project Design Concept ........................................................................... 59
5.1 Technology Description:........................................................................................ 59
5.2 Case Study: Incineration based WtE ..................................................................... 60
5.2.1 Project requirement .................................................................................................... 60
5.2.2 Approach.................................................................................................................... 60
5.2.3 Assessment of Land availability and requirement ....................................................... 60
5.2.4 Assessment of Water availability and requirement ..................................................... 66
5.2.5 Assessment of Power Availability and Requirement ................................................... 67
5.2.6 Components of Waste to Energy Plant ....................................................................... 67
5.2.7 Layout Planning ......................................................................................................... 67
5.2.8 Demarcation of land on the proposed site .................................................................. 67
5.2.9 Weighbridge ............................................................................................................... 68
5.2.10 MSW Receiving Pit/ Platform ................................................................................... 69
5.3 MSW Handling and Pre-processing Plant (MHP) .................................................. 69
5.3.1 Pre-Processing Stages............................................................................................... 70
5.3.2 Storage shed/ Drying area ......................................................................................... 72
5.3.3 Feedstock Feeder System (FFS) ............................................................................... 72
5.3.4 Feedstock .................................................................................................................. 72
5.3.5 Advantage of Pre-processing ..................................................................................... 74
5.4 Incinerator/ Steam Generator for MSW ................................................................. 75
5.4.1 Moving Grate Incinerator ............................................................................................ 75
5.4.2 Fluidized Bed Incinerator ............................................................................................ 77
5.4.3 Rotary Kiln Incinerator ................................................................................................ 78
5.4.4 Steam Turbine Generator and Auxiliaries ................................................................... 80
5.4.5 Water system ............................................................................................................. 82
5.4.6 Water Treatment Plant ............................................................................................... 87
5.4.7 Service and Potable Water System ............................................................................ 89
5.4.8 Fire Protection System ............................................................................................... 89
5.4.9 Effluent Disposal System ........................................................................................... 89
5.4.10 Electrical Systems for Power Plant ........................................................................... 90
5.4.11 Auxiliary Power Supply System ................................................................................ 90
5.4.12 Auxiliary Power Supply system ................................................................................ 94
5.4.13 Control & Instrumentation (C&I) System ................................................................... 99
5.4.14 Fire Fighting ........................................................................................................... 104
TCE 10176A-2024-DPR-R2 ii
5.4.15 Emission Control System (ECS) ............................................................................. 109
5.4.16 Ash Collection and Management System ............................................................... 112
5.4.17 Leachate Collection and Management System....................................................... 116
5.4.18 Treatment of Effluent from Ash Pond ..................................................................... 117
5.4.19 Effluent Treatment Plant ......................................................................................... 118
5.4.20 Sewage Treatment plant ........................................................................................ 118
5.4.21 Process Water Conveyance Pipeline ..................................................................... 118
5.4.22 Storm Water Drainage System ............................................................................... 119
5.4.23 Internal/ Service Road Network .............................................................................. 121
5.4.24 Boundary Wall ........................................................................................................ 122
5.4.25 Administration office ............................................................................................... 123
5.4.26 Worker’s Area ........................................................................................................ 123
5.4.27 Security Cabin ........................................................................................................ 123
5.4.28 Various Plant Buildings/ Structures ........................................................................ 124
5.4.29 Ground Improvement Measures ............................................................................. 125
5.4.30 Field Testing .......................................................................................................... 126
5.4.31 Further Scope ........................................................................................................ 126
5.4.32 Foundations ........................................................................................................... 126
5.4.33 Specification of Materials ....................................................................................... 127
5.4.34 Design Codes and Standards................................................................................. 128
5.4.35 Information Communication Technology (ICT) ....................................................... 131
5.5 Reject Management ............................................................................................ 131
5.5.1 Inert waste: C&D ...................................................................................................... 131
5.5.2 Recyclable Waste .................................................................................................... 132
5.5.3 Leachate .................................................................................................................. 132
5.5.4 Sludge...................................................................................................................... 133
5.5.5 Fly ash ..................................................................................................................... 134
5.5.6 Bottom ash ............................................................................................................... 137
5.5.7 Flue-gas desulfurization (FGD) ................................................................................ 137
5.6 Continuous Emission Monitoring Systems (CEMS) ............................................. 138
5.6.1 Utilities Requirements .............................................................................................. 139
5.6.2 Measuring Principle of SO2, NOx, CO Analyzer Module – Nondispersive Infrared Sensor
(NDIR) .............................................................................................................................. 139
5.6.3 Measuring of Principle of VOC Analyzer Module ...................................................... 140
5.6.4 Bill of Material .......................................................................................................... 140
5.7 Landscape strategy:............................................................................................ 142
5.7.1 Tree Buffer/ Green Belt Development: ..................................................................... 142
5.7.2 Landscape pockets .................................................................................................. 142
5.7.3 Landscape Costing .................................................................................................. 145
TCE 10176A-2024-DPR-R2 iv
7.4 Environmental Monitoring Plan & Implementation Arrangements ........................ 174
7.4.1 Environmental Management Cell ............................................................................. 174
7.4.2 Environmental Monitoring Program .......................................................................... 175
7.4.3 Record Keeping and Reporting ................................................................................ 178
7.4.4 Environmental Audits and Corrective Action Plans ................................................... 178
CHAPTER 8: Project Risk Management ...................................................................... 180
CHAPTER 9: Quantity and Cost Estimation ............................................................... 185
9.1 Quantity Estimates .............................................................................................. 185
9.2 Cost Estimates.................................................................................................... 185
9.3 Financial feasibility of the Project ........................................................................ 186
CHAPTER 10: Funding Scenarios and Financial Model .............................................. 187
10.1 Project Funding Models ...................................................................................... 187
10.2 Levelized Tariff ................................................................................................... 190
CHAPTER 11: 190
11.1 Cost of Generation of Power ............................................................................... 190
11.1.1 In house consumption of power generated ............................................................. 190
11.1.2 Sale of Power Vs Internal Consumption ................................................................. 191
Two option for MCGM ....................................................................................................... 191
CHAPTER 12: Project Implementation Strategy ........................................................... 193
12.1 Maintenance Requirements ............................................................................. 193
12.2 Project Milestone ................................................................................................ 194
12.3 Issues Requiring Attention of MCGM .................................................................. 194
12.4 Interim Plan for Site Management ....................................................................... 196
CHAPTER 13: Literature Review ................................................................................... 199
LIST OF TABLES:
TABLE 2-1:SALIENT FEATURES OF DEONAR DUMPING GROUND ................................................ 5
TABLE 2-2: AIR QUALITY LEVELS FROM APRIL 2010 TO OCTOBER 2015 ..................................... 8
TABLE 2-3: SUMMARY OF WIND PATTERN - IMD COLABA DATA ................................................. 10
TABLE 2-4:PHYSICAL COMPOSITION AND CHEMICAL CHARACTERISTICS OF WASTE IN
INDIAN CITIES.............................................................................................................................. 13
TABLE 2-5: CALORIFIC VALUE RANGE AND THE RELATIVE OCCURRENCE PERCENTAGE .... 14
TABLE 2-6: ANNUAL NET POWER GENERATION (ESTIMATED) .................................................... 19
TABLE 2-7: KEY FINDINGS OF THE TOPOGRAPHIC SURVEY ....................................................... 22
TABLE 2-8 KEY FINDINGS FROM THE GEOTECHNICAL INVESTIGATION REPORT.................... 23
TABLE 2-9: WTE PLANT REFERENCE LIST FROM IDECK REPORT .............................................. 27
TABLE 3-1: ADVANTAGES AND DISADVANTAGES OF BIOMETHANATION TECHNOLOGY ....... 30
TABLE 3-2: ADVANTAGES AND DISADVANTAGES OF GASIFICATION TECHNOLOGY .............. 32
TABLE 3-3:ADVANTAGES AND DISADVANTAGES OF PYROLYSIS TECHNOLOGY..................... 34
TABLE 3-4: ADVANTAGES AND DISADVANTAGES OF PLASMA ARC TECHNOLOGY ................. 35
TABLE 3-5: ADVANTAGES AND DISADVANTAGES OF INCINERATION TECHNOLOGY .............. 36
TABLE 3-6: STATUS OF DIFFERENT WTE PLANTS IN INDIA.......................................................... 38
TCE 10176A-2024-DPR-R2 v
TABLE 3-7: INTERNATIONAL STATUS OF MASS BURNING PLANTS ............................................ 40
TABLE 3-8: LESSON LEARNT FROM WTE PROJECTS IN INDIA .................................................... 40
TABLE 3-9: DETAILS OF WTE TECHNOLOGY OPTIONS ................................................................. 41
TABLE 3-10: DECISION SUPPORT MATRIX FOR SELECTION OF CENTRALIZED APPROACHES
BASED ON EXPERTS’ VALUATION ........................................................................................... 43
TABLE 3-11:WTE RELATIVE RANKING .............................................................................................. 44
TABLE 4-1: ENVIRONMENTAL CLEARANCE REQUIREMENT FOR THERMAL POWER PROJECT
(SO 1533, MODIFIED 25THJUNE 2014) ....................................................................................... 47
TABLE 4-2: PROJECT STAGES AND RESPECTIVE COMPLIANCES .............................................. 50
TABLE 4-3: AIR EMISSION STANDARDS OR INCINERATION FACILITY OF MSW (SWM RULES
2016) ............................................................................................................................................. 51
TABLE 4-4: STANDARDS FOR LEACHATE DISPOSAL AS PER SWM RULE 2016......................... 53
TABLE 4-5: WASTE WATER DISCHARGE STANDARDS BY CPCB (ENVIRONMENT PROTECTION
RULE 1986, SCHEDULE IV) ........................................................................................................ 54
TABLE 4-6: AMBIENT AIR QUALITY STANDARDS WITH RESPECT TO NOISE ............................. 57
TABLE 5-1: COMMON FACILITIES/RESOURCES FOR TECHNOLOGIES ....................................... 59
TABLE 5-2: LAND AVAILABILITY AND DEPTH OF EXISTING MSW................................................. 61
TABLE 5-3: LAND AREA REQUIREMENT .......................................................................................... 64
TABLE 5-4: COMPONENTS OF THE PROPOSED PLANT ................................................................ 67
TABLE 5-5:SPECIFICATIONS OF THE BOILER ................................................................................ 80
TABLE 5-6: RELIABILITY ANALYSIS FOR POWER GENERATED – SEASONAL VARIATION....... 80
TABLE 5-7: STEAM PARAMETERS AT DIFFERENT POINTS IN THE CYCLE ................................ 81
TABLE 5-8: PLANT WATER REQUIREMENT ..................................................................................... 84
TABLE 5-9:CW SYSTEM MAKE-UP REQUIREMENTS ...................................................................... 86
TABLE 5-10: RELAYS & METERING DETAILS ................................................................................... 95
TABLE 5-11: TRANSFORMERS DETAILS .......................................................................................... 95
TABLE 5-12: FAULT CURRENT DETAILS .......................................................................................... 98
TABLE 5-13: REQUIREMENT & SPECIFICATION DETAILS FOR EARTHING SYSTEM ................. 99
TABLE 5-14:PARTICULATE AND EMISSION STANDARD .............................................................. 109
TABLE 5-15:WET FGD SYSTEM (ESTIMATED VALUES) ................................................................ 111
TABLE 5-16: ASH POND CAPACITY (INTERIM PERIOD) ............................................................... 114
TABLE 5-17: ASH DISPOSAL OPTION-1 ......................................................................................... 114
TABLE 5-18: ASH DISPOSAL OPTION-2 ......................................................................................... 114
TABLE 5-19: INERT DISPOSAL OPTION-1....................................................................................... 115
TABLE 5-20: INERT DISPOSAL OPTION-2 ...................................................................................... 115
TABLE 5-21: EFFLUENT POND ........................................................................................................ 118
TABLE 5-22: ELECTRICAL DESIGN CODES ................................................................................... 128
TABLE 5-23: CIVIL DESIGN CODES ................................................................................................. 131
TABLE 5-24: ITEM DESCRIPTION WITH QUANTITY ....................................................................... 140
TCE 10176A-2024-DPR-R2 vi
TABLE 5-25 LANDSCAPE COST SUMMARY ................................................................................... 145
TABLE 6-1NO SIGNIFICANT IMPACTS DUE TO CONSTRUCTION ............................................... 153
TABLE 6-2 RAGPICKERS AILMENTS AND MEDICAL CONDITIONS ............................................. 158
TABLE 7-1:SUMMARY OF POTENTIAL IMPACTS AND MITIGATION MEASURES FOR
CONSTRUCTION PHASE .......................................................................................................... 166
TABLE 7-2:SUMMARY OF POTENTIAL IMPACT AND MITIGATION MEASURES FOR
OPERATIONAL PHASE ............................................................................................................. 171
TABLE 7-3: ENVIRONMENTAL MONITORING PLAN ...................................................................... 176
TABLE 7-4: RECORD KEEPING PARAMETERS WITH PARTICULARS ......................................... 178
TABLE 8-1RISK AND MITIGATION MEASURES .............................................................................. 180
TABLE 9-1: SUMMARY OF BLOCK COST ESTIMATE OF WASTE TO ENERGY PROJECT ........ 185
TABLE 10-1 COMPARISON MATRIX DBO VS PPP MODEL ........................................................... 188
TABLE 10-2: DATA INPUT FOR LEVELIZED TARIFF ...................................................................... 190
TABLE 10-3 COMPARISON BETWEEN SALE OF POWER TO DISCOM VS INTERNAL
CONSUMPTION ......................................................................................................................... 191
TABLE 12-1: COMPLIANCES/REQUIREMENTS AND AGENCY ..................................................... 194
TABLE 12-2: PROJECT MILESTONE FOR DEVELOPMENT OF WASTE TO ENERGY (WTE)
PROJECT AT DEONAR, MCGM, MUMBAI ............................................................................... 197
List of Figures
FIGURE1.1: WASTE HIERARCHY ........................................................................................................ 2
FIGURE 2.1:LOCATION OF THE PROJECT SITE ................................................................................ 7
FIGURE 2.2: THE PROJECT SITE AND SURROUNDINGS ................................................................. 7
FIGURE 2.3:SEISMIC ZONING MAP OF INDIA .................................................................................... 9
FIGURE 2.4: ANNUAL WIND ROSE BASED ON 30 YEARS DATA ................................................... 10
FIGURE 2.5: BELL CURVE SHOWING CALORIFIC VALUE IN KCAL/KG VS. OCCURRENCE
PERCENTAGE.............................................................................................................................. 14
FIGURE 2.6: MUNICIPAL SOLID WASTE FLOW DIAGRAM IN WTE PLANT ................................... 15
FIGURE 2.7: SEASONAL VARIATION IN PLANT EFFICIENCY ......................................................... 16
FIGURE 2.8: TOPOGRAPHIC SURVEY MAP OF THE DEONAR DUMPSITE ................................... 21
FIGURE 2.9: BOREHOLE LOCATIONS AS DEPICTED IN 2005 REPORT ........................................ 22
FIGURE 3.1:OPTIONS AVAILABLE FOR MSW MANAGEMENT/TREATMENT ................................ 29
FIGURE 3.2: COMPARISON BETWEEN LANDFILL AND WTE PLANT ............................................. 37
FIGURE 3.3 NET CO2 REDUCTION OF MSW INCINERATION WHEN REPLACING COAL
COMBUSTION .............................................................................................................................. 37
FIGURE 4.1: GENERAL EIA FRAMEWORK........................................................................................ 48
FIGURE 4.2: CRZ DEMARCATION MAP (1991) ................................................................................. 49
FIGURE 4.3: OVERLAY OF AAI COLOUR CODED ZONING MAP OVER DEONAR DUMPING
GROUND ...................................................................................................................................... 56
FIGURE 5.1: FLOW DIAGRAM FOR TYPICAL WTE .......................................................................... 62
List of Annexure:
List of Drawings:
TCE 10176A-2024-DPR-R2 ix
TCE 10176A-2024-DPR-R2 x
Abbreviation:
TCE 10176A-2024-DPR-R2 xi
EC Environmental Clearance
ECS Emission Control System
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EPA Environmental Protection Agency
EPABX Electronic Private Automatic Branch Exchange
System
ESP Electro Static Precipitator
ETP Effluent Treatment Plant
EU European Union
FFS Feedstock Feeder System
FGD Flue Gas Desulfurization
FID Flame Ionization Detector
GoM Government of Maharashtra
GT Generator Transformer
HDPE High-density polyethylene
HVAC Heating, Ventilation and Air Conditioning
HVWS High Velocity Water Spray
IBA Incinerator Bottom Ash
ICB International Competitive Bidding
IS Indian Standards
ISWM Integrated Solid Waste Management
LTP Leachate Treatment Plant
LVS Large Video Screen
MB Mixed Bed
MCCB Module Case Circuit Breaker
MCF Micro Cartridge Filter
MCGM Municipal Corporation of Greater Mumbai
MHP Municipal Handling and Pre Processing Plant
MoEF& CC Ministry of Environment Forest and Climate
Change
MOG Magnetic Oil level Gauge
MPCB Maharashtra Pollution Control Board
The implementation of WtE project will benefit in many ways as summarized below:
1Initial
Environmental Examination Report for 1000 TPD Waste to Energy Project for MCGM at
Deonar, Mumbai
2Report of the Task Force on Waste to Energy Volume I, 2014
Note:
Above estimate is subject to change based on following considerations
1. MCGM Schedule of Rate (SoR): 2014, Standard Manuals, Reports and Market
2. Site clearance, excavation and filling are calculated considering complete removal of legacy waste
from the proposed plant area. There is scope for the Contractor to propose innovative technology
which may lead to reduction in cost and time of site preparation.
3. Some of the sub-components considered for above estimate may not be applicable or
may get replaced depending on the selection of the pre-processing and processing technology.
4. Prices are inclusive of all Taxes and Duties.
Turbine Continuous
Generator Stack
emission
monitoring
system
• Manual Segregation
Drier Feedstoc
Total Raw • Magnetic Separator WtE Plant of
MSW (600 • Screening k 600 TPD X 1 Air pollution
50 – 70% ID
TPD= 100%) • Shredder or 300 TPD X control fan
2
Air Pollution
control residue
20%
Bottom ash
4%
Fly Ash
Effluent
Treatment
Brick making &
Plant
Extent of pre-processing is as Disposal
per technology requirement To cement
plant &
Treated
Effluent
Disposal
(i) With the project being financed by MCGM, considering 15 Years Operation Service
period the levelized is arrived at considering:
a. Recovery of only capital investment during the project life
b. Operation Service charges considered @ 2.5% per annum of the Capex Cost
with an annual escalation of 5.72% and
c. Asset Replacement Fund considered at 1% per annum of the Capex cost
The levelized tariff work out to Rs. 18.08/ kWh
(ii) Considering only Operation Service carried out by the Contractor for a period of 15
Years the levelized tariff is arrived at taking:
a. Operation Service charges considered @ 2.5% per annum of the Capex Cost
with an annual escalation of 5.72% and
b. Asset Replacement Fund considered at 1% per annum of the Capex cost
The levelized tariff works out to Rs. 7.04/kWh.
10. Project Implementation Strategy
It is proposed to award a comprehensive contract to Commission Waste to Energy
project and its Operation service, thereafter for a period of 15 years to a pre-qualified
and competitively selected private operator through an International Competitive
Bidding (ICB) process.
The project design and construction period is about 40 months, includes six months of
commissioning. The project is new technology and of very large scale. The Asset
replacement for the project is expected during 8th to 10thyear. The project needs
sufficient time for better yield. Considering all these factors, the Operation service
period for the project is considered as 15 years.