s10706-023-02429-1
s10706-023-02429-1
s10706-023-02429-1
https://doi.org/10.1007/s10706-023-02429-1
ORIGINAL PAPER
Received: 20 December 2022 / Accepted: 10 March 2023 / Published online: 5 April 2023
© The Author(s) 2023
Abstract This paper aims to develop a relatively all buildings are supported on foundations extending
simple approach to examining the interaction among to a relatively stiff layer, the interaction effects tend
multiple foundation systems for closely spaced high- to be relatively small. However, if one or more of the
rise structures, termed here “urban forests”, and to buildings is founded on a relatively short foundation
assess the extent to which this interaction can influ- system, interaction effects may be more significant.
ence the foundation performance of a building within An example is provided to illustrate the application of
this “forest”. To simplify the analysis and avoid the approach.
undue numerical complexity, each foundation sys-
tem is modelled as an equivalent pier, representing Keywords Analysis · Foundations · Interaction ·
the deep foundations, the connecting mat or raft, and Numerical analysis · Settlement · Tall buildings
the soil contained within the piled raft system. The
behaviour of a single equivalent pier is considered
first, with the surrounding foundations being rep- 1 Introduction
resented by an axisymmetric smeared ring outside
the pier. After examining some general behavioural The development of urban areas to accommodate
characteristics, a simplified approach using the con- burgeoning populations has led to the construction of
cept of interaction factors is developed to facilitate high-rise buildings that are concentrated in relatively
estimation of settlement interaction between multi- close proximity. This trend appears to be acceler-
ple adjacent foundations. The accuracy of this sim- ating, and may result in the formation of what may
plified approach is assessed via comparison with the be termed “high-rise urban forests”, consisting of
axisymmetric approach. The significance of the inter- a group of closely-spaced buildings that are tall and
action among foundations is examined for some sim- slender (Cardno 2022). One of many examples of
ple cases. It is found that the settlement interaction such a collection of buildings is shown in Fig. 1. It
depends largely on the characteristics of the founda- is well-recognized that wind loadings on such build-
tions surrounding the building being examined. When ings are influenced significantly by the proximity and
orientation of surrounding buildings, as is the seismic
response (Kato and Wang 2022), but when designing
H. G. Poulos (*) the foundations for such buildings, there has been a
Tetra Tech Coffey, Sydney Australia & Emeritus Professor tendency to focus on each building as an individual
of Civil Engineering, University of Sydney, Camperdown,
isolated structure. However, there is anecdotal evi-
Australia
e-mail: [email protected] dence to suggest that the foundation systems of
Vol.: (0123456789)
13
2816 Geotech Geol Eng (2023) 41:2815–2831
2 Approximate Analysis Via Axi‑Symmetric To avoid undue complexity, yet retain some ele-
Finite Element Simulation ment of reality, all of the foundation systems are
assumed initially to be identical, and are located in a
In principle, the interaction among multiple founda- two-layer soil profile. Figure 2 illustrates this simpli-
tion systems can be carried out via a three-dimen- fied representation of multiple foundations.
sional finite element analysis in which each pile The Young’s moduli of the equivalent pier and the
within each foundation system is modelled. However, smeared pier ring can be estimated approximately
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2817
by ignoring the effect of the soil and considering the Table 1 Example analyzed
stiffness of the piles only. The equivalent modulus of Quantity Value
the central pier, Ep1, is then calculated as follows:
Pile length, L (m) 40
Ep1 = n1 ⋅ Ep ⋅ Ap ∕(𝜋 ⋅ D2 ∕4) (1) Equivalent pier diameter, D (m) 50
Spacing between central and adjacent smeared pier 5
where n1 = number of piles in the central group, ring, s (m)
Ep = Young’s modulus of an individual pile, Young’s modulus of layer 1 (MPa) 20
Ap = cross-sectional area of each pile, D = diameter of Young’s modulus of layer 2 (MPa) 100
equivalent central pier. Young’s modulus of piles (MPa) 30,000
Similarly, the equivalent modulus of the adjacent Average spacing/diameter of piles 3
smeared pier ring, Ep2, is: Applied loading on each pier, p (kPa) 300
where n2 = number of piles in the smeared pier ring, surrounding the central pier. Each pier consists of
and AR = area of smeared pier ring, = 218 piles 1 m diameter, spaced at about 3 m centre
to centre.
AR = [𝜋 (1.5D + s)2 − (0.5D + s)2 (3)
( ]
From Eq. (1), the equivalent Young’s modulus of
the central pier is 2616 MPa.
where s = average centre-to-centre spacing between
The average loading on the smeared pier ring has
piles.
to take account of the fact that only the areas occu-
In most cases, the effect of the Young’s modulus
pied by the 4 piers are loaded. Thus, for the smeared
of the equivalent piers will be small, as the length of
pier ring, the average loading, p1, is found to be as
the equivalent pier in relation to the diameter will be
follows:
small, typically less than 5 for most tall buildings.
P1 = [n.p.𝜋D2 ∕4]∕AR (4)
2.1 Limitations of the Adopted Approach
where p = average pressure on each foundation, and
It is important to recognize that, in an axisymmetric n = number of piers within the smeared pier ring = 4
analysis, it is implicitly assumed that all of the adja- in this case.
cent piers are loaded simultaneously. In reality, this In this case, p1 is found to be 136 kPa.
would be highly unlikely to occur, as surrounding The number of piles in the pier ring is
buildings would be constructed at different times and n2 = 4*218 = 872, and from Eq. 2, the Young’s modu-
would be likely to have different loadings. Further- lus of the smeared pier ring is 1189 MPa.
more, the foundation dimensions would be unlikely to
be identical. 2.3 Example Results—Equal Pier Lengths
The effects of having unequal lengths of equivalent
piers are examined subsequently in this paper after Figure 3 shows the finite element mesh developed
the evolution of a simplified approach. for the example analysis. It contains 32,087 nodes
and 3957 elements. The lateral extent of the mesh
2.2 Example Analyzed is 250 m and the vertical extent is 200 m. The upper
layer is divided into two sections to enable later con-
As an example, the case described in Table 1 has sideration of piers of unequal length.
been analyzed using the program PLAXIS. To avoid The analysis involved simulation of two stages:
undue complication at this stage, both the soil strata
and the piers are assumed to behave elastically. Pois- 1. Loading of the central pier, giving the settlement
son’s ratio for both layers is assumed to be 0.3. of the building of interest under its own loading;
It is also assumed that there are 4 identical and 2. Subsequent loading of the adjacent smeared pier
equally loaded equivalent piers symmetrically ring, giving the settlements of the central pier and
Vol.: (0123456789)
13
2818 Geotech Geol Eng (2023) 41:2815–2831
the smeared pier ring at the end of load applica- the adjacent buildings has resulted in an increase
tion. in settlement, in this case, of almost 200%. Thus,
the overall final settlement of the central pier is
For the case where the central pier and the adjacent about 215 mm.
smeared pier ring are of equal length, referred to here 3. The settlement of the smeared pile ring is not uni-
as Case 1, Fig. 4 shows the computed settlement pro- form, but tends to be larger adjacent to the central
file when the centre pier is loaded, while Fig. 5 shows pier and smaller at the outer edges. This result is
the profile of additional settlements after the adjacent surprising, as it might be expected that the pres-
smeared pier ring is loaded. ence of the central pier would tend to inhibit the
From these figures, the following points can be settlement of the smeared pier ring.
noted:
1. Under its own loading, the central pier settles 2.4 Effect of Unequal Pier Lengths
about 75 mm and the settlement profile away
from the pier reduces rapidly with increasing dis- To obtain some indication of the effects of having
tance. interacting equivalent piers of different lengths, two
2. Under the loading of the adjacent smeared pier additional analyses have been carried out:
ring, a very significant increase in settlement of
the central pier occurs, with the additional settle- 1. Case 2: a shorter central pier (20 m long) adja-
ment being about 140 mm. Thus, the loading of cent to a longer (40 m) smeared pier ring.
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2819
2. Case 3: a longer (40 m) central pier adjacent to a 1. The least total settlement occurs when the cen-
shorter (20 m) smeared piled ring. tral and smeared outer piers are the same length
(Case 1).
In each case, the upper layer is 40 m deep. Thus, 2. When the central pier is shorter (Case 2), its set-
Case 2 represents a central foundation that may be tlement (173 mm) is increased considerably as
shorter than it should be and surrounded by deeper compared with the longer case (75 mm).
foundations, while Case 3 represents a deeper founda- 3. When the central pier is shorter, the additional
tion system surrounded by a series of less deep foun- settlements due to the longer smeared pier ring
dations. All piers are assumed to be loaded equally are slightly larger than for the case of all piers
with an average vertical pressure of 300 kPa. being of equal length.
The computed settlement profile for the central 4. The additional settlements due to the surrounding
pier in Case 2 is shown in Fig. 6, while the additional piers are greater when the smeared pier ring is
settlements due to loading of the adjacent smeared shorter than the central pier (Case 3). In this case,
pier ring are shown in Fig. 7. The corresponding pro- the additional settlements are increased substan-
files for Case 3 are shown in Fig. 3 (the centre pier is tially, both beneath the central pier and beneath
the same as for the previous case) and in Fig. 8 for the the smeared pier ring. The computed additional
effect of the loading of the adjacent shorter smeared settlement beneath the central pier is 131 mm,
pier ring. as compared with 75 mm when the smeared pier
The preceding figures suggest the following char- ring is longer. In addition, the settlement differ-
acteristics of behaviour:
Vol.: (0123456789)
13
2820 Geotech Geol Eng (2023) 41:2815–2831
Fig. 5 Case 1: profile of additional settlements after 40 m long outer smeared pier ring loaded
ence across the smeared pier ring is significantly consequences of multiple foundation interaction, they
greater than in the other two. have significant limitations in terms of:
5. The latter finding can be of practical importance
as it implies that, even though a foundation may 1. Not being able to simulate sequential loading of
be relatively deep, if shallower foundations are surrounding foundations.
constructed and loaded around it, the central 2. Not being able to handle non-symmetrical
pier may experience a significant increase in set- arrangements of foundations;
tlement. In other words, in this case at least, it 3. Requiring all surrounding foundations to be iden-
appears that the stiffness of the surrounding piers tical, even though they can be different to the
tends to have the main influence on the additional central foundation being considered.
settlements of the central pier. 4. Not being able to simulate the differential settle-
ments at various points across the whole founda-
Table 2 summarizes the computed settlements for tion footprint.
each of the three cases.
Consequently, it is desirable to seek an alterna-
tive approach that is more flexible and that can be
3 Development of a Simplified Analysis Approach calibrated against the axisymmetric analyses set out
above. In addition, it would be desirable that the
While the axisymmetric finite element analyses out- method should be implemented without the use of
lined above can provide useful indications on the complex software.
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2821
To this end, an attempt has been made to develop 3.1 Representation of Pile Group as an Equivalent
a simpler method involving the use of interaction Pier
factors between foundations, an approach that paral-
lels the interaction factor approach that is frequently Ideally, an equivalent pier representing a pile group
used in the analysis of pile groups. In the proposed should have a similar ultimate capacity and stiffness
simplified analysis, the following procedure is to that of the group. As discussed by Poulos (1994),
followed: in utilizing the equivalent pier approach, the follow-
ing points should be noted:
1. The foundation system of each tower is simplified
and represented as an equivalent pier. 1. Ideally, the diameter of the equivalent pier, D,
2. The interaction between pairs of piers is consid- should be such that it has an equal surface area
ered to estimate the settlement of a pier due to (shaft and base) to the enclosed “block” of piles
loading on adjacent piers. and soil. For a block of square plan of dimen-
3. Superposition is applied in an approximate man- sions BxB, D will be between 1.13B (for equal
ner to consider the settlement distribution within base area) and 1.27B (for equal shaft perimeter).
a multiple high-rise development area. From a practical viewpoint, it may be adequate to
adopt an average D = 1.2B in this case.
Each of the above steps is described in more 2. The equivalent Young’s modulus of the pier is
detail below. taken as the area-weighted average value of the
Vol.: (0123456789)
13
2822 Geotech Geol Eng (2023) 41:2815–2831
Fig. 7 Case 2: profile of additional settlements after longer outer smeared pier ring loaded
pile—soil block. If the stiffness of the soil is dis- from the estimated ultimate shaft and base resist-
regarded, and the average centre to centre spacing ances of the pile group.
of the piles is s, the equivalent pier modulus, Epe,
is approximated as: The axial stiffness of the equivalent pier can be read-
ily computed from a numerical analysis or from elas-
Epe ≈ Ep ⋅ (d∕s)2 ⋅ 𝜋∕4 (5) tic-based solutions such as those presented by Poulos
(1994). These latter solutions will be reproduced later
where Ep = Young’s modulus of the piles and d =
in the paper.
pile diameter.
In most cases, the equivalent pier is likely to be rela-
3.2 Interaction between Identical Piers
tively short, so that the pier is relatively rigid and
the effect of E
pe is minor.
The concept of settlement interaction factors between
3. In selecting the Young’s modulus of the bear-
two piles was introduced by Poulos (1968). Using this
ing stratum, considerations needs to be given to
approach, the additional settlement, D SI,j at an exist-
the effects of pile installation. An average value
ing pier i due to an identical newly-constructed pier j,
(weighted with respect to the relative depth
can be expressed as follows:
below the pier base) should be used.
4. For a non-linear analysis, equivalent shaft and DSi,j = Pj ⋅ 𝛼ij ∕Kj (6)
base resistances for the pier should be computed
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2823
Fig. 8 Case 3: profile of additional settlements after shorter outer smeared pier ring loaded
Table 2 Summary of computed settlements from PLAXIS analyses (all piers loaded equally)
Case Computed settlement mm
Central pier Inner edge of smeared Outer edge of
pier ring smeared pier
ring
Settlement Additional settlement Total settlement Settlement when Settlement when
when centre pier when smeared ring smeared ring smeared ring
loaded loaded loaded loaded
Vol.: (0123456789)
13
2824 Geotech Geol Eng (2023) 41:2815–2831
As discussed below, such effects did not appear to interaction factor 𝛼 and the distance, r, from the pier,
be significant. as shown in Fig. 9, thus indicating that the effects of
diffraction are not significant. The curve labelled as
3.3 Superposition of Settlement Increments “CLAP” has been obtained from a pile group analysis
program based on DEFPIG (Poulos 1990), while the
If all the equivalent piers are identical, then then the curve labelled “PLAXIS” has been obtained from the
overall settlement of pier i, Si, after the construction computed settlement profile shown in Fig. 3.
of a number (n) of adjacent piers is the summation The following approximate expression for the
of the settlement of Pier i under its own load, S0, plus interaction curves in this case can be derived from
the additional settlements due to each of the adjacent curve fitting:
piers, i.e.:
𝛼 ≈ 1.15.exp(−1.25r∕D) (9)
Si = S0 + ΣPj .𝛼ij ∕Kj (7)
For the shorter 20 m long piers, the computed
where S0 = settlement of pier i under its own load interaction factors from the PLAXIS analysis are
shown in Fig. 10.
= Pj ∕Kj (7a) The corresponding approximate expression for the
interaction curves in this case from curve fitting is as
and Pj = load on Pier j and Ki = stiffness of pier j.
follows:
3.4 Estimation of Interaction Factors 𝛼 ≈ 3.1.exp(−2.5r∕D) (9a)
0.7
0.5
0.6
0.4 0.5
0.3 CLAP 0.4
0.2 PLAXIS 0.3
0.1 0.2
0 0.1
0 1 2 3 4 5 0
r/D 0 0.5 1 1.5 2 2.5 3
r/D
Fig. 9 Comparison of interaction factors via CLAP and
PLAXIS for Case 1; 40 m long Piers Fig. 10 interaction factors for 20 m long Piers
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2825
4.2 Non‑Identical Piers
Table 4 Summary of some Option no Stiffness of interacting piers used Interaction factors used
possible assumptions for
pile stiffness and interaction 1 Influencing piers Influencing piers
factors
2 Influencing piers Average for influencing & influenced pier
3 Influenced pier Influencing piers
4 Influenced pier Average for influencing & influenced pier
5 Mean of influenced and influencing piers Average for influencing & influenced pier
Vol.: (0123456789)
13
2826 Geotech Geol Eng (2023) 41:2815–2831
1 88 153
2 77 177
3 153 88
The bold figures are to 4 177 77
distinguish the values from 5 107 107
the PLAXIS analysis from PLAXIS 75 170
the approximate analysis
0.100
as the ratio of the interaction factor for L/D to the 0.000
value for the base case, for a spacing of r/D = 1.5. 0 1 2 3 4 5 6 7 8
0.800
(approximately) as: 0.700
0.600
Es2/Es1=1
𝛼 = 𝛼0 .F1 .F2 (12) 0.500
Es2/Es1=2
0.400
Es2/Es1=5
By curve fitting of the graphs in these three figures, 0.300
0.200 Es2/Es1=10
the following approximate relationships are derived: 0.100
0.000
𝛼0 = 1.681.exp(−1.222r∕D) + 0.038 (13) 0 1 2 3 4 5 6 7 8
r/D
(c)
F1 = 0.835.exp(0.237.L∕D) − 0.191 (14)
Surface Foo ng
1.000
(15)
( )
F2 = 2.337.exp −1.055.Eb ∕Es + 0.718 0.900
0.800
Basic Interac on Factor
0.700
0.600
0.500
5.3 Extension to Interaction Among Multiple 0.400
Dissimilar Equivalent Piers 0.300
0.200
0.100
When the equivalent piers within the group are not all 0.000
identical, the settlement of a point A on an equiva- 0 1 2 3 4 5 6 7 8
r/D
lent Pier i due to load Pj on Equivalent Pier j is again
(d)
given by Eq. 6. This assumes that the settlement of
Vol.: (0123456789)
13
2828 Geotech Geol Eng (2023) 41:2815–2831
Eb/Es=1 1.000
1 0.900
Selement Interac on Factor
0.8
Fig. 15 Basic interaction Factor 𝛼0 for base case (L/D = 1.5,
0.6 L/D=5 Eb/Es = 2)
0.4 L/D=3
L/D=1
0.2
1.6
L/D=0.1
0 1.4
0 1 2 3 4 5 6 7 8
1.2
r/D Correcon Factor F1
(b) 1
0.8
Eb/Es=5
1 0.6
Selement Interac on Factor
0.8 0.4
0.2
0.6 L/D=2.5
0
0.4 L/D=1.5 0 0.5 1 1.5 2 2.5 3
L/D
L/D=0.5
0.2
L/D=0.1
0 Fig. 16 Correction factor F1 for L/D
0 1 2 3 4 5 6 7 8
r/D
(c)
1.8
Eb/Es=10
1.6
1
Selement Interac on Factor
0.9 1.4
Correcon Factor F2
0.8 1.2
0.7
1
0.6 L/D=2.5
0.5 0.8
0.4 L/D=1.5
0.6
0.3 L/D=0.5
0.4
0.2
L/D=0.1
0.1 0.2
0 0
0 1 2 3 4 5 6 7 8 9 10 0 2 4 6 8 10
r/D Eb/Es
(d)
Fig. 17 Correction factor F2 for base modulus ratio Eb/Es
Fig. 14 Basic interaction factors for two identical equivalent
piers. a Eb/Es = 1; b Eb/Es = 2; c Eb/Es = 5; d Eb/Es = 10
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2829
Pier i depends on the stiffness of the influencing pier The evolution of settlement will be calculated at
and the average interaction factor for the influencing the centre and at each of the corners of T0. Because
and influenced piers. of the simplified nature of the analysis, the settlement
For the entire group, the settlement of point on of T0 under its own loading is (approximately) uni-
pier i is then given by Eq. 7. This is of course an form, but settlements due to the adjacent towers will
approximation, but probably adequate for a first be dependent on the distance between the tower cen-
estimate. tre and the point in question.
The simplification of the problem proceeds as
follows:
6 Example of the Application of the Approach
1. Developing the equivalent pier for each tower
To illustrate the application of the proposed approach foundation: Assuming that the piles occupy
to a somewhat more realistic case, the example illus- the area of the tower footprint, the area is
trated in Fig. 18 has been considered. In this example, 50 × 50 = 2500 m2, so that the equivalent diam-
a cluster of 7 identical towers are to be constructed, eter is (2500 ∗ 4∕𝜏)0.5 = 56.4 m. The length L is
with the central tower (T0) being constructed first, 40 m, so that L/D = 0.71.
and then the remaining towers (T1 to T6) being con- 2. Develop an equivalent 2-layer soil profile:
structed in turn. Each tower has an average service-
ability loading of 0.3 MPa (equivalent to about a
The average Young’s modulus along the
30-storey building), and occupies a square footprint
length of the piles, E
s, can be approximated as
of 50 m by 50 m. The buildings are in close proxim-
(20x20 + 20x100)/40 = 60 MPa. Thus, Eb/Es
ity, being spaced 5 m apart.
= 100/60 = 1.67. For the above values of L/D
The ground conditions consist of a 20 m deep layer
and Eb/Es, from Figure 11, Is ≈ 0.33.
of medium clay with an average long-term Young’s
modulus of 20 MPa, overlying a 180 m deep layer of
stiffer residual clay with a long-term Young’s modu- 3. From the chart in Fig. 12, and Eq. 10:
lus of 100 MPa. The foundation system of each tower K = 56.4 × 60/0.33 = 10,255 MN/m.
consists of a series of bored piles with a total length 4. The average settlement, S 0, of tower T0 under
of 40 m, i.e. founded 20 m into the residual clay layer. its own loading can be estimated using Eq. 11:
S0 = 0.3 × 502/10255 = 0.073 m = 73 mm.
5. The influence of the adjacent buildings can now
be considered. The settlement calculations points
are the centre of T0 and the four corners of that
tower. The effect of Tower T1 is considered first,
and the calculations are shown in Table 6 where
values of the spacing from the centre of T1 to
each of the calculation points are shown. The
corresponding values of interaction factors, com-
puted from Eqs. 12 to 15, are shown, and then
the overall additional settlement at each of these
points is computed from Eq. 7.
6. Similar tables can be set up for the effects of the
other towers, T2 to T6. These calculations are
carried out most effectively via a program such
as MATHCAD, and Table 7 summarizes the final
outcome of the calculations carried out. Fig-
ure 18 summarizes the evolution of settlements at
each of the five points considered, with the load-
Fig. 18 Configuration of tower cluster
Vol.: (0123456789)
13
2830 Geotech Geol Eng (2023) 41:2815–2831
200
• Significant additional settlements are induced
150 Point B below T0 due to loading on the adjacent towers.
100 Point C The final settlement is almost 4 times the settle-
ment of T0 under its own loading.
50 Point D
• The settlements below T0 are uniform at the start
0
0 1 2 3 4 5 6
PLAXIS (all towers and finish of the loading sequence, but not at inter-
loaded)
Aer Loaded Tower No. mediate stages.
• Significant differential settlements are induced
Fig. 19 Evolution of computed settlements at various points below T0 during the loading process of the adja-
below T1 cent towers. In this example, the largest differ-
ential settlement occurs between Points D and A
after Tower T3 has been constructed and loaded
Table 6 Calculations for effect of tower T1 on tower T0 (82 mm between Points B and C), and is in excess
Calcula- Distance r r/D Interac- Additional of the initial uniform settlement of T0.
tion point from centre tion factor settlement due • In the simple case considered, where the tower
of T1 (m) 𝛼ij to T2 (mm) configuration around the tower of interest is sym-
metrical, the differential settlements will eventu-
O (centre) 55 0.975 0.549 36
ally become zero or near-zero. However, in cases
A 39.1 0.692 0.759 50
where asymmetric adjacent towers are present, or
B 39.1 0.692 0.759 50
there is a marked difference between the loadings
C 83.8 1.486 0.312 20
on the adjacent towers, there will be a residual dif-
D 83.8 1.486 0.312 20
ferential settlement of the original tower.
Table 7 Calculations for Calculation Additional settlement after tower loaded (mm)
effect of all towers on tower point
T0 T0 T1 T2 T3 T4 T5 T6
Vol:. (1234567890)
13
Geotech Geol Eng (2023) 41:2815–2831 2831
Vol.: (0123456789)
13